Meeting documents

Delegated Decisions by Cabinet Member for Transport
Friday, 6 October 2006

XT061006-05

Return to Items for Decision

Division(s): All

ITEM CMDT5

ENVIRONMENT & ECONOMY SCRUTINY COMMITTEE – 20 SEPTEMBER 2006

Cabinet Member for Transport – 6 October 2006

Transport Capital Programme 2006 - 2011

Report by Head of Transport

Introduction

  1. This report focuses primarily on the Transport Capital Programme for 2006/07 and provides an update on any significant changes plus an assessment of performance on delivery of the programme by the end of the financial year.
  2. The Local Transport Plan 2006 – 2011 (LTP2) published in July this year contains the programme of schemes for the whole of the Plan period in as much detail as is known at present. Programmes beyond the current year remain as published in LTP2, the first opportunity for a review will be in December this year when the government’s assessment of LTP2 and of the Delivery Report 2001 – 2006 is known. The assessment will have a bearing on the future level of capital funding available.
  3. The report includes the response to Councillor Joslin’s motion on Cow Lane, Didcot as adopted by Council on 20 June this year.
  4. The purpose of this report is considered and it is suggested that the regular reviews on the capital programme that have been introduced make this report unnecessary in future.
  5. Overview of the 2006/07 Transport Capital Programme as at 1 April 2006

  6. The total budget for Integrated Transport Schemes agreed at Cabinet on 21 March 2006 was £13.730 million made up of £9.079 million from the Transport Capital Settlement, £2.911 million of developer contributions and £1.740 million of on-street parking surplus.
  7. There were two main influences on the content of the programme, the priorities of LTP2 and the level of Transport Capital funding. The schemes in the five year programme are value-for-money solutions that directly contribute to the resolution of most significant, pre-identified problems of congestion, accessibility, road safety, air quality and the street environment – the priorities for LTP2. The guideline funding for the 2006 – 2011 period is £12 million less than we would have had if funding had stayed at the level of the first LTP.
  8. The combined effect is a programme that can be seen as a fresh start, not a simple continuation of what we did before, with schemes chosen to solve known problems rather than be a response to requests and with fewer schemes in the programme. A substantial part of the available budget for this year is committed to the Abingdon and Henley town centre schemes and to the Green Road roundabout improvement scheme.
  9. The capital budget for structural highway maintenance is £16.222 million made up of £13.722 from the formula based LTP2 funding and £2.450 million awarded for specific schemes on roads that were de-trunked in the last few years. Additional to this is £2.145 million carried forward from 2005/06 to co-ordinate carriageway reconstruction works on A40 at Sandhills with the Green Road roundabout improvement scheme.
  10. 2006/07 Programme Update - Overview

  11. Annex 1 (download as .doc file) lists the schemes and planned spending as at 1 April (first three columns) and the updated information as at 7 September (last three columns). This must be seen as an interim statement of the position because a quarterly update to the Capital Programme is due shortly and a further update of the position on schemes may result in some differences between Annex 1 (download as .doc file) and what appears in the revised Capital Programme booklet.
  12. Looking at the bottom line the LTP2 funding in the SCE (supported capital expenditure) column remains as at 1 April but the ‘Other’ funding shows an increase of £5.516 million. The main reasons for this are:

    1. A40 Green Road scheme – the addition of the structural maintenance money carried over from last year.
    2. Structural Maintenance – the additional allocation of £0.375 million for accelerating the Oxford High Street scheme included in the Council’s budget decisions for 2006/07.
    3. For completeness - inclusion of a line from the Capital Booklet for schemes completed in earlier years but where there may still be some expenditure – this includes a small number of LTP schemes from 2005/06 where completion ran over into the early part of this year.

  13. Otherwise, the forecast is that things are on track to deliver the original Integrated Schemes Programme with the exception of the A40 Cassington Signals scheme where a value for money solution could not be identified. The budget for this scheme will be re-allocated to the A40 Eynsham scheme delayed from 2005/06.
  14. Update on Specific 2006/07 Schemes

  15. The three largest and potentially most difficult schemes to build – Abingdon and Henley town centre schemes and the A40 Green Road roundabout improvement are progressing to plan and in most aspects have a risk rating of green on the regular scheme status review. The early involvement of the contractor in the planning of each of these schemes appears to be paying off. The one word of caution is that if there are unexpected delays on the Green Road scheme the work is at a stage where it would be difficult to make up time to recover those delays.
  16. The first phase of the Oxford High Street reconstruction and remodelling, another complex and difficult site with a lot that could potentially go wrong, has also not met any serious problems thanks again to pre-planning and good teamwork. The risk rating status for this scheme is also green. The Oxfordshire Highways personnel involved in this scheme are largely those who worked on the Abingdon Road scheme in Oxford and who won the Jacobs Performance Excellence Award 2006 for partnering work. The work in High Street has just moved on to phase two between Longwall and The Plain.
  17. The spending on the Oxford Eastern Bypass barrier scheme was originally planned to span 2005/06 and 2006/07 but as things turned out all the spending could be coded to 2005/06 which is why spending is shown as nil for this year.
  18. The increase in spending on the Thames towpath repairs in Oxford between Folly Bridge and Donnington Bridge is the result of a deliberate decision to extend the works beyond those originally planned. This money was provided by re-phasing schemes between years. The reasons for this were a rapid deterioration in the state of that length of towpath during the year and the saving in cost of the extra repairs by avoiding the contractor set-up costs that would be incurred if he had to leave and return to site.
  19. Last year’s equivalent report set out an accelerated timetable for the implementation of Controlled Parking Zones in Oxford, particularly in north-east Oxford, by the end of 2009. The budget to enable this faster implementation was included in Integrated Schemes Programme and so far the schemes are on track to meet this accelerated timetable.
  20. Two major schemes, Hennef Way, Banbury and Skimmingdish Lane, Bicester were completed some time ago but there have been substantial outstanding claims for additional payment on each of the schemes from the contractor. The contractor (who happens to be the same for both schemes) elected to use the adjudication provisions in the contract in regard to his claim on Skimmingdish Lane. The Adjudicator’s decision awarded some money to the contractor but a lot less than his claim and the Council has paid this to the contractor with the result the Skimmingdish Lane issue is now settled. The Hennef Way claim remains to be resolved and therefore some provision remains in the budget against risk of having to make further payment although the advice from the Council’s Engineer is that all money due has been paid. This provision is contained in the line for schemes from 2005/06 and earlier.
  21. Annex 2 (download as .doc file) lists the individual schemes under the Banbury Western Corridor and the Better Ways to School headings.
  22. Potential Risks to the Programme – Heat Damage to Roads

  23. The extreme heat earlier in the year caused damage to a number of roads where the bitumen became so soft that the surface stone was submerged into it. These roads now have a very slick surface which will need repair for safety reasons. Assessment of the full scale of the problem is being done but first estimates are that £4.0 million pounds will be required to correct all the damage in a long lasting way and a bid for special funding from the government is being prepared. However, warning signs and more urgent short term remedial action is needed on some roads and a figure of £0.5 million is the estimated cost for this work which will have to be done this year. The means of funding this is being considered at the moment.
  24. Cow Lane, Didcot – Council motion

  25. On 20 June this year the Council resolved as follows:
  26. "This Council notes that:

    1. a letter was sent in March this year to members of the Didcot ITS Committee to advise them that as a result of a reduction in Government funding, combined with a lack of developer contribution there were insufficient funds to take forward the Cow Lane Subway Project in LTP2;
    2. the Didcot ITS Group met on 17 November 2005 and their views expressed at the time were taken into account;
    3. the project had been approved as a Major project by the Transport Implementation Committee and the previous Executive;
    4. the project had been allocated a Project number and design work had commenced but the indicative funding the Council expected in the draft LTP2, submitted to Government in July 2005 was subsequently reduced from £55m to £43m (-£12m) and consequently many schemes that were originally planned had to be delayed or cancelled.

    The Council asks the Cabinet to confirm that the Cow Lane Project remains a positive aspiration of this Council subject to the necessary funding being identified."

  27. The position remains as noted by the Council, that Cow Lane Subway together with a number of other previously committed schemes, is not included in the 2006 – 2011 LTP Programme as they did not contribute sufficiently to solving identified transport problems relative to other priorities.
  28. We have also identified that some of the developer contributions which had been earmarked for the Cow Lane project, totalling some £178,000, would not be available for the project because of the precise terminology of the legal agreements; though this is a small issue in the context of the total cost and the priorities for the use of available funds.
  29. As the letter sent in March to the Didcot ITS Members Steering Group confirms, the Cow Lane Subway project remains an aspiration of the County Council subject to the necessary funding being available but is not a part of the 2006-2011 LTP programme.
  30. The Need for this Report in Future Years

  31. This report has been a feature of the Transport Capital Programme management for a number of years and has provided a useful means of reviewing issues affecting programming of schemes and obtaining necessary approvals to amendments in the programme before it is too late in the programme year to act on the decisions.
  32. However, the report’s origins lie in the days when there was not the regular monitoring and reporting of the capital programme that now takes place. Significant variations to spending are reported monthly to Cabinet and there is a quarterly update of the entire capital programme which provides approvals for any new schemes that are brought into the programme in the course of the year and for significant revisions. There is a regular reporting system of progress on the larger schemes within the Transport Service that is provided to the Cabinet Member for Transport. This report could be seen as superfluous in the light of the other reporting that now takes place. It does lift the Transport Capital Programme out of the other reports and provide a focus on it, but this could be just as well achieved by better and more widespread use of the Capital Programme booklet. In the interests of efficiency and avoiding unnecessary work, my recommendation is to discontinue this report and rely on the other reporting now in place.
  33. Financial and Staff Implications

  34. There are no implications to report arising from delivery of the programme as agreed in March. The largest issue is how the funding of repairs to heat damage to roads can be achieved and at the time of writing the report this is still under discussion.
  35. Links to Local Transport Plan (LTP) and Corporate Priorities

  36. The Transport Capital Programme is entirely about pursuing the LTP priorities and the corporate priorities that these contribute to as described in the LTP document.
  37. Recommendations

  38. The Cabinet Member for Transport is RECOMMENDED to:
          1. note the progress on the Transport Capital Programme;
          2. confirm that the Didcot, Cow Lane Subway scheme remains a positive aspiration of the Council subject to the necessary funding being available;
          3. agree that a report on a mid-year review of the Transport Capital Programme is no longer necessary.

(Statement of Decision)


STEVE HOWELL
Head of Transport

Background papers: Nil

Contact Officer: Richard Dix tel. 01865 815663

September 2006

Return to TOP