Return
to Items for Decision
Division(s):
Bampton, Eynsham, Hanneys and Hendreds, Kingston Bagpuize, Wootton
|
ITEM CMDT1
CABINET
MEMBER FOR TRANSPORT – 6 OCTOBER 2006
A415 ROUTE
IMPROVEMENT
Report by
Head of Transport
Introduction
- On 21 February
2006 the Cabinet regarding resolved that a route improvement of the
A415 between A40 and A34 should be included as part of the County Council’s
Longer Term Strategy for transport improvements. That report picked
up the recommendations which had been made following the completion
of the Transport Networks Review (TNR) study and had subsequently been
subject to consultation.
History
- The Route Improvement
was to include a number of schemes which had all been previously considered
separately but which would now be considered together and which would
consequently have a greater impact. The TNR saw this scheme as being
necessary as a result of increased traffic levels predicted on the A415
in the near future as traffic sought to divert away from the congested
networks in the Oxford area. The improvement would include: Marcham
Bypass, Kingston Bagpuize Link Road, Newbridge Replacement, Standlake/Brighthampton
Bypass. On-line improvements elsewhere on the route would also need
to be considered.
- Funding for a
scheme of this size would critically depend upon gaining the support
of the Regional Transport Board (RTB) through the Regional Prioritisation
Process. The Regional Funding Allocation (RFA) controlled by the RTB
provides the only means whereby large projects (i.e. cost > £5 million)
can be funded where these cannot attract sufficient developer contributions,
or where other specific sources of outside funding were unlikely. An
RFA prioritisation process had taken place in 2005 to determine priorities
for investment for 2006-2011. This process had also committed some funding
in 2011-2016 where implementation of approved schemes extended into
that period.
- Marcham Bypass
had been put forward for RFA support for the 2006-2011 period but had
not been assessed as having sufficient priority to attract funding.
It was considered at that time that, providing the rules remained the
same, a larger scheme with a wider range of benefits would stand a better
chance of attracting funding in future RFA rounds.
Regional Funding
Allocation beyond 2011
- The South East
England Regional Assembly (SEERA) published a framework for prioritising
schemes for beyond 2010/11 in July 2006. In the accompanying letter
bids were invited solely from schemes which have "been identified
as being necessary to support delivery of the South East Plan" and
stressing the importance that schemes demonstrate "the linkage between
the investment proposal and, where appropriate, the relevant sub-regional
spatial strategy."
- Given this emphasis
it would be difficult to put together a submission for the A415 Route
Improvement that is likely to achieve a high prioritisation score. It
would, for instance, probably only score positively in 8 of the 17 criteria
outlined in the prioritisation framework and in none of what are likely
to be the most important criteria – those related to schemes which enable
the South East Plan (housing) growth.
- It was therefore
not considered worthwhile to prepare and submit a prioritisation bid
for the scheme in this round. While this would technically only rule
out the scheme for the 2011-2016 period it is likely that the prioritised
schemes would also take up a large proportion of any funds available
in the subsequent period (as indeed was the case in the previous round).
It is also likely that the emphasis on schemes which are directly needed
to deliver the Regional Plan will be retained in future rounds.
- This calls into
question whether this part of the TNR strategy is now deliverable. If
the improvement is not deliverable then an early decision will ensure
that no unnecessary, or ultimately wasted, work on identifying the elements
of this strategy is undertaken. In the programme outlined in the LTP
report this work was due to take place in the immediate future. As was
stated in the February Cabinet report if schemes are removed from the
programme then it is important that their protection is removed in order
to avoid ongoing blight issues. The Council currently has protected
lines for three schemes along the route. Marcham Bypass is dealt with
below; the lines for Kingston Bagpuize Link Road and Cokethorpe Bends
would be removed from protection if this route improvement was abandoned.
- Without the upgrade
of the A415 the most effective way of minimising problems on the route
is a combination of measures to manage congestion on the A34 and measures
to reduce the attractiveness of the A415. In the longer term the suitability
of the A415 as a whole to remain as a Principal ("A"-class) Road may
need to be considered.
- A Regional Prioritisation
Bid has been prepared for the Access to Oxford strategy which includes
the first part of a long term strategy for the A34 (which includes introducing
an "Intelligent Transport System" including variable message signing
and interactive speed management) and a wider study to determine a post-2016
approach for improving the A34 through Central Oxfordshire. The Access
to Oxford Strategy also includes considering the Northern Approaches
to Oxford – which will include consideration of our long term ambitions
for the A40. It is unclear at the moment to what extent these measures
would need to be re-enforced by capacity reductions on the A415. The
need for these should be re-assessed either in the light of improved
predictions of the impact of the Access to Oxford programme and/or following
its introduction.
Retained Elements
- Marcham Bypass
– the justification for this part of the Improvement was not related
to traffic growth but with the environmental impact of the current traffic
levels on the village. The likely cost of the scheme (> £14 million)
means that the County Council cannot fund the bypass from its own resources.
However, funding opportunities may arise from the Upper Thames Reservoir
(if this is proceeded with by Thames Water) and in relation to post-2016
developments in the Wantage & Grove area. It is therefore considered
that the line protection for this scheme should be retained, at least
until these issues become clearer. In the February report to the Cabinet
it was mentioned that Frilford Parish Council had put forward an alternative
route for the eastern section of the bypass. An evaluation of the relative
benefits of this scheme, as opposed to the currently preferred scheme,
would need to be undertaken if the prospects for delivering the scheme
improve but pending such a study should not be included in the protected
route. Oxfordshire Highways has been commissioned to look at on-line
measures which could be put in place as a shorter term solution to the
problems in Marcham, or as an alternative if funding for the bypass
is not forthcoming.
- Newbridge – The
current crossing, a Listed Structure and Scheduled Ancient Monument,
is failing and has had a temporary weight limit recently placed upon
it. However it is considered that this will not arrest deterioration
in the structure and that the only long term solution is to build a
replacement structure on a new line. Allowance for a replacement structure
has been made within the LTP-funded Maintenance Programme for 2010/11.
There is considerable local concern that the removal of the constraint
caused by the present traffic signal controlled single-lane crossing
will increase traffic levels along the A415, particularly the numbers
of heavy goods vehicles. In the absence of the improvement of the route
as a whole it is considered that the development work for the new crossing
should be widened to include consideration of these issues and, if they
should prove to be valid, to identify any mitigation measures which
would be necessary to counter any such effects. This could take the
form of retaining single file "shuttle working" on the crossing, even
if the structure built was capable of two-way operation, retaining the
weight limit or building in restraint measures elsewhere on the route
to counter any increase in capacity.
Legal Implications
- The protection
of a road improvement line from development does expose the County Council
to claims for blight. Such a claim is currently being made against the
Council by the owners of one property in Kingston Bagpuize. It is to
reduce the possibilities of such claims being made that the general
principle was established in Planning Policy Guidance that protection
should only be given to schemes where there is a reasonable expectation
that they could be delivered within the current planning horizon. This
principle guided the decision in February to remove protection of all
those schemes which were not to be included in the longer term improvement
programme and, in this report, to remove protection on the lines for
Kingston Bagpuize and Cokethorpe Bends.
Sustainability Implications
- The route improvement
would have allowed for an increase in the amount of travel in the county
which if it occurred would have had negative implications for the amount
of CO2 emissions. However, the abandonment of the scheme
may mean that overall there will be increased congestion in the future
with a consequent increased amount of pollution both overall and in
specific locations. The improvement would have brought particular benefits
to residents in Standlake and Kingston Bagpuize which are unlikely to
be realised with the abandonment of the scheme.
Financial and Staff Implications
- The development
of the A415 route improvement would have required a considerable investment,
both financially and in staff time. Central Government rules require
that promoting authorities provide at least ten percent of the total
cost of a scheme if it is to be eligible for central funding support.
In practice this level of funding would be required to develop a scheme
sufficiently to make a funding bid. It is likely that the scheme would
have cost around £50 million, although this would depend on the exact
routes chosen, meaning that a minimum Council investment of £5 million
would need to be demonstrated.
- The abandonment
of the A415 route improvement will mean that staff resources can be
concentrated more on developing schemes which are more likely to be
achievable and therefore provide better value for money for the resources
invested in them.
(Statement
for Decision)
RECOMMENDATION
The
Cabinet Member for Transport is RECOMMENDED to
- remove
the A415 route improvement from the County Council’s Longer
Term Transport Improvement Programme;
- cease
to protect the lines for the Kingston Bagpuize Link Road and
Cokethorpe Bends Improvement;
- instruct
officers to take into account the need to not attract additional
traffic onto the A415 when evaluating options for the new river
crossing at Newbridge; and
- approve
the continued protection of the Marcham Bypass.
STEVE
HOWELL
Head of Transport
Background
papers: Nil
Contact
Officer: Roger O’Neill Tel: 01865 815659
September
2006
Return to TOP
|