|
Return
to Agenda
ITEM PN8
PLANNING
& REGULATION COMMITTEE –
24 FEBRUARY 2003
INSTALLATION
OF INERT WASTE RECYCLING FACILITY FOR SECONDARY AGGREGATES AT THE FORMER
CEMENT WORKS AND QUARRY, SHIPTON-ON-CHERWELL, NEAR KIDLINGTON, OXFORDSHIRE
- (APPLICATION NO. 02/02330/CM)
Report by
the Director of Environmental Services
Introduction
- This application
is for the establishment of an inert waste recycling operation on the
site of the former cement works at Shipton-on-Cherwell Quarry. An earlier
application for a similar facility, in the quarry itself, was refused
permission in January last year. That application is currently the subject
of an appeal and an Inquiry into that refusal is to be heard on the
18 of this month.
- As further background
planning permission was originally granted to construct earth berms
(banks) in the south west corner of Shipton-on-Cherwell Quarry in October
1995 in order to stabilise the quarry face in that location. This area
is referred to as Phase 1 on the attached plan. Two further permissions
were given in phase 1 to extend the time to allow completion of these
works up to 1998. Permission was refused for a further extension of
time in February 1999 on the grounds that sufficient material had already
been brought on site to complete the works.
- A further permission
for stabilisation works to the remainder of the south west face of the
quarry (Phase II on the plan) was granted in June 1999, the permission
to expire at the end of March 2003. There is currently an application
which is the subject of a separate report to this committee for stabilisation
works to the north west quarry face (Phase III – see plan).
The Site
- The site comprises
a compound measuring about 190 m x 80 m located towards the south western
end of the former Cement Works complex. The Cement Works are derelict
and partially demolished. The proposal includes a waste storage area,
a material handling area, a crushing/screening area and a vehicle manoeuvring
area. The site would be bounded by a low earth bund topped with a fence.
- Access would be
via a two-way access route across the quarry floor towards the northern
end of the quarry.
- The quarry which
is located immediately to the north of the village of Shipton-on-Cherwell
is in the Oxford Green Belt and part of the quarry incorporates a geological
SSSI.
The Proposal
- This proposal
seeks permission to receive inert waste, remove any hard material, crush
and screen that hard material as necessary and to export the secondary
aggregates, screened topsoil and the like to the open market. The applicant
states that of 72,000 tonnes per annum which would be processed through
the site 75% on average would be reclaimed and exported, the remaining
25% being used in the stabilisation berm (Phase III) proposed against
the north western face of the quarry.
- Crushing and screening
equipment would be of recent design and should incorporate appropriate
noise and dust suppression systems. Crushing would only be carried out
as and when the need arises which is anticipated to be up to two weeks
in two months. When not required the mobile crusher and associated screening
plant would be removed from site.
- It is estimated
that the facility would attract an average of about 16 extra lorry loads
per day. These lorry movements would be over and above the lorry movements
bringing waste material to the stabilisation berms. To ensure that the
wheels of lorries leaving the site are clean, a purpose made wheel wash
would be installed.
Policy
Considerations
- Relevant Structure
and Local Plan policies are set out at Annex
1 to this report.
Consultations
and Representations
- Consultations
replies are set out at Annex 2.
To date there have been five third party representations. The District
Council and Parish Council have objected on green belt and other grounds.
There have also been objections from the Oxford Green Belt Network and
local residents.
Comments
of the Director of Environmental Services
- As with all planning
applications, this proposal should be determined in accordance with
the provisions of the Development Plan unless other material considerations
indicate otherwise. The site is within the Oxford Green Belt and the
main considerations in this case, therefore, are whether there are any
exceptional circumstances which warrant a departure from green belt
policies which would normally preclude this type of development, and
if any such circumstances do exist, whether the proposal will have any
adverse environmental effects on the area, particularly in terms of
noise, dust, traffic generation and impact on the SSSI which includes
the majority of exposed faces in the quarry.
- Government guidelines
(Waste Strategy 2000) indicate that there is a presumption in favour
of recycling facilities rather than landfill. Structure Plan policies
also encourage the provision of facilities for the re-use and recycling
of waste in order to reduce the amount of waste that goes to landfill.
Policy W3 of the Minerals & Waste Local Plan says that such recycling
facilities should not cause environmental problems, should be sited
close to the source of waste or market for the recycled material and
should not conflict with Structure and Local Plan Policies.
- In terms of the
environmental impact of the proposal, the facility is to be sited towards
the southern end of an existing complex of former quarry buildings.
The nearest residential properties are over 320 metres away. The District
Council Environmental Health Officer confirms that the distances involved
between the nearest properties and the site and the barrier effect of
intervening buildings and ‘soft ground’ alteration should mean that
local residents should not be subjected to unreasonable levels of noise
as a result of this operation. Planning conditions could control the
level of noise if thought necessary. In addition, the presence of the
existing buildings and the creation of a bund around the site should
reduce any visual impact the development might have. Therefore, I conclude
that the proposal satisfies policy W3 (c) of the Minerals and Waste
Local Plan with respect to environmental nuisance.
- There are no highway
objections to the proposal. The existing junction onto the A4095 has
been improved as part of the stabilisation works permission. Under this
a new access is proposed to be created into the quarry which will take
traffic movements further away from the village of Shipton-on-Cherwell.
Although close to Bunkers Hill the new access road will be on the quarry
floor and the barrier effect of the quarry walls should protect residents
from any undue noise disturbance. I conclude that the proposal satisfies
policy W3 (b) and (c) of the Minerals and Waste Local Plan with respect
to access and traffic.
- English Nature
have not commented on the current proposal. They did suggest conditions
to be attached to the earlier recycling application to make the proposal
acceptable from their point of view. Such conditions could be attached
again if permission is to be given to the current proposal. The proposal,
therefore, does not conflict with policy EN5 (b) of the Oxfordshire
Structure Plan 2011.
- Notwithstanding
that the proposal satisfies the above policies I consider that there
are policies with which it does not accord. The current permission at
the site is for the import of inert waste material to this site, not
for landfill purposes but solely for stabilisation works to ensure the
quarry face does not collapse. The stabilisation works were considered
to be exceptional circumstances when approved in June 1999 and warranted
a relaxation of green belt policies which would normally rule against
such a development. Indeed, Phase I of the stablisation works (see plan)
was eventually refused permission for an extension of time in February
1999 because sufficient material had been imported to do these works
and there was no justification for further importation in the Green
Belt for what would in effect have been purely a landfill operation
for which there was no need.
- In this instance,
the site is within the Green Belt where there is a presumption against
inappropriate development. Whilst mineral extraction need not be inappropriate
development, the same does not apply to waste processing. It is contrary
to policy G4 of the Oxfordshire Structure Plan 2011. In my view the
only way that this recycling proposal could be viewed as exceptional
development in the Green Belt would be if it was to be linked to an
existing landfill or mineral extraction operation so that it was in
accordance with policy W4 (b) of the Minerals and Waste Local Plan.
However, the quarry is no longer a mineral extraction site, nor is it
a landfill site. The applicant has also indicated that special circumstances
exist on the basis that the revenue that will be raised by the recycling
operation will go some way towards paying for the cost of the stabilisation
works which have been undertaken (and for which there is an outstanding
application) in the quarry. It is my view that such circumstances do
not warrant a departure from the normal green belt policies.
- In addition, there
are existing sites close by, for instance Worton Rectory Farm, Cassington
(about 6 miles to the south) and Slape Hill (4 miles to the west) which
already take in and recycle inert waste. The proposal does not therefore
accord with policy W4 (a) of the Minerals and Waste Local Plan. Also
the existing stabilisation permission runs out at the end of March 2003.
Although an application for new stabilisation operation is awaiting
determination, it is my view that all material coming into the quarry
should go to the stabilisation works. The applicants have constantly
expressed the urgency of ensuring the stabilisation works are completed
quickly because of the possible danger of collapse of the quarry walls.
Even so, extensions had to be given to phase 1 even without recycling
on the site. The diverting of any material away from these works would
further prolong the stabilisation and restoration of the quarry which
I (and the applicants) wish to see completed at the earliest opportunity.
- In conclusion,
although I have considered the application in relation to Policies W3,
W4 and W5 (in relation to waste recycling) of the Minerals and Waste
Local Plan and found some merit in the proposal with regard to these
policies, my view is that nothing has changed since the earlier refusal
of permission for a waste recycling facility in the quarry and that
no very special circumstances have been put forward to override Green
Belt policies G4 of the Oxfordshire Structure Plan and GB1 of the Cherwell
Local Plan which presume against inappropriate development of this nature
and, therefore, it also does not accord with policy W3 (e) of the Minerals
and Waste Local Plan.
Environmental
Implications
- The environmental
implications are as set out in this report.
Financial
and Staff Implications
- There are none
other than those that would arise if the applicant appealed to the Secretary
of State against any refusal of planning permission.
PLAN (download as .doc file)
RECOMMENDATION
- It is RECOMMENDED
that planning permission be refused for the installation of an inert
waste recycling facility at Shipton-on-Cherwell Quarry (Application
No. 02/02330/CM) for the following reasons:
- there
are no very special circumstances to warrant a departure from
normal Green Belt policy and as such the proposal is contrary
to Policies G4 of the Oxfordshire Structure Plan 2011 and Policy
GB1 of the Cherwell Local Plan and Policy W3 of the Oxfordshire
Minerals and Waste Local Plan; and
- the
proposal is contrary to Policy W4 of the Minerals and Waste
Local Plan as (1) no overriding need has been identified for
the proposal and (2) the site is not one where permission would
normally be permitted as it is part of a site where a land stabilisation
operation takes place and not part of a mineral extraction or
landfill site.
DAVID
YOUNG
Director of
Environmental Services
Background papers: File No: 8.1/4817/3 Inert waste recycling facility
at Shipton-on-Cherwell Quarry, Nr Kidlington held in Land Use Planning
Section of Environmental Services
Contact Officer: John Hamilton, Tel: Oxorrd 815584
3 February 2003
Return to TOP
|