Return
to Agenda
ITEM PN5
PLANNING AND REGULATION COMMITTEE
- 13 JANUARY 2003
NON-COMPLIANCE WITH CONDITION
2 OF PLANNING PERMISSION (CHD/12412/2-CM) FOR THE 'INFILLING OF THE
EXISTING HOLE WITH SOIL AND HARDCORE FOR AGRICULTURAL USE' AT HACKPEN
HILL, CHILDREY (Ref: CHD/12412/3-CM)
Report by Director of Environmental
Services
Introduction
- Ben Smith &
Sons (Wantage) Limited have applied for permission not to comply with
Condition 2 of the last planning permission for the infilling of an
existing hole with soil and hardcore for agricultural use at Hackpen
Hill, Childrey.
- Condition 2 limited
the use of the site until 30 September 2002. The application is to extend
the use of the site through to 30 September 2004.
Site Description and History
- The site is located
to the south east of the B4001, south of Childrey (grid reference SU
354 854), and is within the North Wessex Downs Area of Outstanding Natural
Beauty. It is reasonably isolated from any residential properties, the
closest being Sincombe Farm, 400m away.
- At present there
is a hole (measuring approx. 250m x 35m) where chalk was previously
quarried. This is a relatively small landfill site, which has been partially
infilled and is currently overgrown. Planning permission was granted
in 1992 and again in 1996 for the infilling of the site to similar levels
to the surrounding countryside and to restore the land to agricultural
use. However, the applicant has not managed to complete infilling.
Application Details
- It is proposed
that the operation would continue to operate under the conditions of
the 1996 permission. This allows the site to be filled with inert wastes
brought to the site by lorry. The existing permission limits lorry movements
to and from the site to 10 per day.
- Finished contour
levels would be the same as those previously approved, and would tie
in with the surrounding fields. The land would be returned to agricultural
use for wheat and barley production.
Consultations and Representations
- See Annex
1.
- One letter of objection has been received.
Comments of the Director of Environmental
Services
- Section 54a of
the Town and Country Planning Act 1990 states that decisions should
be made in accordance with the Development Plan unless material considerations
indicate otherwise. The relevant plan policies are set out in Annex
2.
Impact on Area of Outstanding Natural Beauty
- The main consequence
of extending the permission on this site is that the site, which is
within an AONB and close to two footpaths, would not be restored for
an additional two years. At present the disused quarry pit and access
road are unattractive, and detract from the landscape value of the area.
Allowing an additional two years would allow the original levels of
the site to be restored and returned to agriculture, improving its landscape
value in the longer term, thus complying with OSP policy EN1 and EN4.
Refusing the application would result in the site being restored at
levels similar to those on site at present. This would mean that there
would be a permanent indentation left in the landscape, and the agricultural
potential of the site would also be diminished. It is therefore preferable
that the site is infilled. However, as the site currently detracts from
the surrounding landscape infilling and restoration of the site should
be completed as soon as possible. It has been made clear to the applicant
that should permission be granted that the permission would only be
for 2 years and the development should be completed within this period.
Other Environmental
Effects
- There are no additional
environmental effects associated with this application that were not
considered with the original application. The number of lorry movements
to and from the site is low (max 10/day) and residential properties
are located far enough away from the site that they would not be significantly
affected. The application, therefore accords with OMWLP policy W7.
Footpaths
- It has been noted
that hay bales have been left next to the footpath. The landowner has
agreed to ensure these are removed. Should material be left next to
or on the footpath in the future enforcement action can be taken if
necessary.
Compliance with Waste Licence
- One of the reasons
for the Ramblers’ Association concern was that conditions associated
with the waste licence have not been complied with. The Environment
Agency visit the site to check compliance with the waste licence. They
have not found any breaches of conditions in the last few months. They
are checking to see if there have been previous breaches.
Infilling
of the Site
- The final reason
for the objection was that ‘local authorities are being urged strongly
not to use landfill’. With a small site like this land filling is
an appropriate method to allow for the restoration of the land to levels
similar to those of surrounding fields (this is reflected in Government
Guidance MPG7 – Restoration of Mineral Workings). At present the site,
along with the land around it, is not farmed as the location of the
hole makes it uneconomic to do so. The site has, and would be, infilled
with inerts, so there are no issues of pollution of the surrounding
environment. As the site is an old mineral working the proposal is in
accordance with OSP policy WD5.
Summary
- In summary the
application would allow for the continuation of the tipping at Hackpen
Hill Quarry for an additional 2 years. This would allow the site to
be restored to levels similar to that of the surrounding countryside,
enhancing both its landscape and agricultural potential. There would
be no additional environmental effects above those considered in the
original application.
Environmental Implications
- These are outlined
in the report.
Financial and Staff Implications
- There are no financial
or staff implications other than those that would arise if the applicant
appealed to the Secretary of State against any refusal of planning permission.
RECOMMENDATION
- It is RECOMMENDED:
- to approve
the application to amend condition 2 of Permission No CHD/12412/2-CM
as follows:
"The
deposit of waste hereby permitted shall cease on or before 30
September 2004 and the site shall be restored in accordance
with the approved details and conditions of this permission
within a further period of 6 months or such longer period as
the Local Planning Authority may approve in writing.
Reason:
To minimise the duration of disturbance from the tipping operation."
- that the
following conditions be added/amended to update the permission:
"Aftercare
of the restored site shall take place for a period of up to
5 years in accordance with an aftercare scheme to be submitted
to and approved in writing by the Local Planning Authority.
Such a scheme shall be submitted before 30 March 2004 and shall
specify the steps proposed to be carried out during the aftercare
period and make provision for an annual site meeting to discuss
and agree steps necessary on the restored land.
Reason:
To bring the land to the standard required for agricultural
use.
The
development hereby permitted shall be carried out solely in
accordance with the approved submitted details and plans and
those of planning permission CHD/12412/2-CM except as modified
by these conditions and unless otherwise agreed by the Local
Planning Authority in writing.
Reason:
For the avoidance of doubt and to ensure that the development
is carried out in accordance with approved plans and details"
- that all
other existing conditions on Permission No. CHD/12412/2-CM should
remain in force with regard to development on the site.
DAVID YOUNG
Director of
Environmental Services
Background
Papers: File reference 8.4/3585/2 – Hackpen Hill Quarry, Childrey,
in Land Use section, Environmental Services, Speedwell House. Representations
made on this application are on this file.
Contact Officer:
Kate Dahm, Tel: 01865 815272.
December 2002
Return
to TOP
|