Return
to Agenda
ITEM CA6
CABINET
– 15 NOVEMBER 2005
REVENUE
BUDGET & CAPITAL PROGRAMME: SERVICE AND FINANCIAL PLANNING 2006/07
– 2010/11
Report by
Chief Executive and Director for Resources
Introduction
- This report is
the second in a series informing members on the service and financial
planning process and issues for 2006/07 and the medium term. The report
sets out the latest information on the Council’s financial position.
It also provides an update on CCMT’s budget management proposals for
2006/07 and outlines areas of uncertainty. A summary Budget Fact Sheet,
the second in the series will be published alongside the report to give
an easily accessible step by step guide of the key issues as they emerge.
Executive
Summary
- The Medium Term
Financial Plan (MTFP) includes a sum available to allocate for 2006/07
of £9.2m. This is dependent upon achieving efficiencies/savings of £5.0m.
CCMT have already identified £4.3m of efficiencies as part of the budget
process leaving a shortfall of £0.7m. In addition, £0.5m of previously
agreed policy plans are no longer required which reduces the existing
commitments in the MTFP. Based on these two changes, the sum available
to allocate is currently £9.0m.
- The Directorates
have identified non-discretionary pressures against the contingency.
For all other pressures which represent policy choices, Directorates
have been asked to identify how they intend to fund these. There is
some additional one off money available to fund one off pressures which
is currently estimated to be between £1.1 and £3.5m.
- The final amount
required for balances is being reviewed and a full risk assessment undertaken.
There remains substantial uncertainty around the outcomes for Oxfordshire
of the Formula Funding Share (FSS) and grant review. The provisional
settlement will be known in early December and this will make the funding
position much clearer. There is little flexibility around the capital
programme with £1.9m available to allocate in 2008/09.
- All services are
required to produce their service and financial plans for 2006/07 (and
beyond) by the end of January 2006. The next stage of the process will
be for Scrutiny to review the budget proposals put forward by CCMT in
December.
2006/07
Net Expenditure and Funding
- The table on the
next page sets out the starting point for the 2006/07 budget per the
revised MTFP and shows the anticipated changes based on latest information.
Changes from the previous report are explained in the following paragraphs.
Previously
Agreed Policy Plans
- The 2003/04 MTFP
included potential increases in pension costs associated with the Homes
for Older People contract from 2005/06 of £0.5m. This represented the
past service deficit in respect of those staff transferring to the contract.
It has now been determined that this sum is not required. In addition,
with the proposed transfer of Firefighters pensions out of Formula Spending
Share, to be funded instead by a specific grant, the ongoing policy
plan relating to increases in pension costs based on predicted Firefighter
retirements in future years will no longer be required. This is £0.09m
in 2006/07 and £0.286m in 2007/08.
Starting
Point for 2006/07 Budget per Revised MTFP |
|
|
|
Revised
MTFP |
Latest
Position |
|
£m |
£m |
Gross
Budget 2005/06 |
777.5 |
777.5 |
Less: |
|
|
Specific
Grants 2005/06 |
123.9 |
123.9 |
Income
2005/06 |
69.6 |
69.6 |
|
|
|
Equals:
Budget Requirement 2005/06 |
584.0 |
584.0 |
|
|
|
Add
new 2006/07 items: |
|
|
(i)
Inflation |
15.3 |
15.3 |
(ii)
Previously Agreed Policy Plans |
1.0 |
0.5 |
(iii)
Other Variations Agreed in MTFP |
0.2 |
0.2 |
(iv)
Efficiencies and Savings |
-5.0 |
-4.3 |
(v)
Available to Allocate to Council Priorities |
9.2 |
9.0 |
|
|
|
Equals:
Budget Requirement 2006/07 |
604.7 |
604.7 |
|
|
|
Funded
by: |
|
|
Total
Formula Grant (assuming 3.2% increase) |
367.2 |
367.2 |
Council
Tax (including surpluses) (assuming 4.375% increase) |
237.5 |
237.5 |
|
|
|
Total
Funding 2006/07 |
604.7
|
604.7
|
|
|
|
- As part of the
2005/06 budget, £0.25m of savings relating to Telecommunications were
included as a Policy Plan. At its meeting on 20 September, the Cabinet
agreed a supplementary estimate to reinstate the savings of £0.25m.
Actual savings arising from the contract are now expected to be £0.112m
in a full year. As a consequence of this, there is a shortfall in the
base budget of £0.138m.
- These changes
reduce the commitments arising from previously agreed policy plans from
£1.0m to £0.5m in 2006/07 and from £2.7m to £2.4m in 2007/08.
Efficiencies
and Savings (and the Efficiency Savings Strategy)
- Work on the procurement
element of the efficiency savings strategy has identified potential
savings next year of £0.3m. The Procurement Team is working with Directorates
to achieve other efficiencies which should come on line in 2006/07.
However these are only in the exploratory stage and it is too early
to include any potential savings in future years budgets.
- Some potential
has also been identified for increasing income by £0.4m. This includes
increasing fees and charges income by 3%, which is 1% above the MTFP
assumptions.
- CCMT have agreed
that the balance of savings required should be allocated out to Heads
of Service on a pro-rata basis. £4.4m equates to 1.72% saving for each
service. As last year, services were expected to focus initially on
the scope for making further efficiency savings on top of those achieved
this year.
- Services have
provisionally identified how they intend to meet these targets although
further work needs to be undertaken to verify their achievability. An
initial response indicates efficiencies of £3.6m, which when added to
the procurement and income generation savings totals £4.3m, compared
with £5.0m target.
Savings
Targets – Provisional Intentions of Services
|
£m
|
|
|
Procurement
|
0.3
|
Income
Generation
|
0.4
|
|
|
Learning
& Culture
|
0.5
|
Social
& Health Care
|
2.2
|
Environment
& Economy
|
0.8
|
Community
Safety
|
0.0
|
Resources
|
0.1
|
|
|
TOTAL
|
4.3
|
Sum Available
to Allocate to Council Priorities
- The Medium Term
Financial Plan (MTFP) includes a sum available to allocate to Council
Priorities of £9.2m, which is the amount of funding available within
the constraints of a 4.375% Council Tax after taking into account items
already agreed (inflation, on-going policy plans and other approved
variations). This sum is however dependent on achieving £5.0m of efficiencies
and savings as set out in the MTFP. It should be noted that the sums
already agreed can be reviewed as part of the budget process to ensure
they are still relevant and required.
- The table above
shows that currently savings identified total £4.3m, which falls short
of the sum required by £0.7m. This shortfall is partly compensated for
by £0.5m of previously agreed policy plans which are no longer required,
reducing the existing commitments in the MTFP. As a result of this,
the sum available to allocate is revised down by the net difference
from £9.2m to £9.0m.
- Potential calls
against this sum relating to pressures have already been identified
and these are currently being reviewed. As the sum available to allocate
is not sufficient to cover the potential pressures and other priorities
for funding, CCMT and Heads of Service are to undertake further work.
This includes:
- CCMT to agree
a list of pressures deemed non-discretionary which will be funded
from the sum available to allocate
- Heads of Service
to ensure that savings have been identified to match each pressure
- Heads of Service
to prioritise each pressure and saving
- Heads of Service
to set out for each of the pressures and savings identified, the scope
and consequences of not providing funding, or removing funding in
terms of outputs and outcomes
- This work will
be carried out over the next few weeks and a detailed schedule of pressures
and choices as to how these could be funded will be available for Scrutiny
Committees to consider in December.
Additional
One-off Funding in 2006/07
- There is expected
to be some unbudgeted one-off funding available for 2006/07, from the
following sources:
- additional interest
income expected from higher balances
- expectations
around PSA reward grant
- the Local Authority
Business Growth Incentive (LABGI) Scheme
- collection fund
surpluses (above that assumed in the MTFP)
- It is too early
to be able to quantify exactly how much additional funding will be available,
but it is expected to be between £1.1m and £3.5m. The Head of Finance
& Procurement has advised that this one-off funding should be used
to finance one-off pressures, or where there is a clear course of action
to deal with on-going pressures post 2006/07.
Integrating
Service and Financial Planning
- Stage 2 of the
process for integrating service and financial planning has now been
completed. This part of the process was for services to define the services
that are delivered currently in terms of outputs and outcomes (not inputs).
This establishes current service levels, which ties in with the basic
service structure of the County Council defined at Stage 1 of the process.
- Consideration
is now being given to a proposed format for developing new service plans.
It is intended that they will reflect the work already done on defining
outputs and outcomes and will include:
- Key outcomes
which we aim to achieve
- How we will
measure success, including key milestones
- Outputs or milestones
by which we will judge progress towards intended outcomes including
key performance indicators and analysis of risk
- Service budgets
- The development
of the service plans forms stage 3 of the service and financial planning
process and is scheduled for completion by the end of January 2006.
2005/06
Financial Monitoring
- The latest projected
position for financial monitoring is set out in the table below.
|
2005/06
latest projected variation
(-
indicates under spend)
|
|
£m
|
Learning
& Culture
|
1.267
|
Social
& Health Care
|
0.738
|
Environment
& Economy
|
-0.258
|
Community
Safety
|
0.400
|
Resources
& Chief Executive’s Office
|
-0.074
|
|
|
TOTAL
|
3.180
|
- The major areas
of overspend relate to Home to School Transport and Premature Retirement
Compensation in Learning & Culture, Children and Families and Learning
Disabilities in Social & Health Care, the Youth Offending Service
in Community Safety and Supporting People. Environment & Economy
have redirected underspends of £0.716m and unexpected income of £0.241m
in Transport against alternative priorities and this should help alleviate
pressures which would otherwise impact in 2006/07.
- Where there are
overspends which are liable to continue in future years, these should
have been identified as part of the budget process. Likewise any underspends
which are likely to continue should also be reviewed.
Beyond
2006/07
- The MTFP includes
a sum to allocate in 2007/08 of £15.1m. This is based on a 5% increase
in formula grant arising from the 2004 Spending Review. Included in
this was an expected increase in Schools FSS of 6.8%. Based on this
assumption, and what is already included in the MTFP for increases in
schools block spending, it is anticipated that £8.6m of the £15.1m will
need to be passed onto Schools via the Dedicated Schools Grant (DSG)
reducing the available contingency to £6.5m. The sums to allocate in
2008/09 and 2009/10 are £6.5m and £6.9m respectively based on 3% growth
across all services. At this stage it is also assumed that the increase
in funding for 2010/11 will be 3%. The £5.0m efficiency target continues
up to 2008/09 only and a decision will need to be taken around whether
this should continue after that.
- Some pressures
for future years have already been identified and were detailed in the
previous report. These include increases in Landfill Tax after 2008/09,
and possible revenue effects of the Homes for Older People contract
in 2007/08.
- In addition, the
Government’s measure of inflation, the Consumer Price Index (CPI) rose
to 2.5% in September. The MTFP assumes annual increases of 2.0% for
inflation on all non-pay items, which may not now be considered sufficient.
The MTFP also includes increases of 2.5% each year for pay inflation,
given increases in recent years for all Council workers have been up
to 3%, and Directorates have been absorbing the shortfall in funding
since 2004/05, the amount set aside in future years should be reconsidered.
- The table below
shows the latest position in respect of the sum still available to allocate
for years after 2006/07.
|
2007/08
|
2008/09
|
2009/10
|
|
£m
|
£m
|
£m
|
Sum
available to allocate per revised MTFP
|
15.1
|
6.5
|
6.9
|
Less:
|
|
|
|
DSG
Increase
|
8.6
|
|
|
Landfill
Tax
|
|
|
0.8
|
Homes
for Older People
|
1.6
|
|
|
Additional
0.5% Inflation - Pay
|
0.8
|
0.8
|
0.8
|
Additional
0.5% Inflation – Non pay
|
0.6
|
0.6
|
0.6
|
|
|
|
|
Current
sum available to allocate
|
3.5
|
5.1
|
4.7
|
Balances
and Reserves
- The Financial
Monitoring Report elsewhere on the agenda identifies that forecast balances
at 30 September are £12.442m, with further potential calls of £0.650m
relating to the anticipated overspend on Supporting People, which is
intended to be returned to balances in 2006/07. Balances also include
£2.0m from interest on cash balances up to half of which may need to
be returned to the Capital Programme to maintain its value.
- The projected
net expenditure for 2006/07 based on a 4.375% Council Tax increase is
£604.7m. The Financial Strategy for the Council states that we should
aim to maintain balances at 2% of our net budget. This is the estimated
total required to cover known and anticipated risks and to allow for
unforeseen circumstances. A full risk assessment to establish the prudent
minimum level for balances is being revisited as part of the budget
process. To achieve balances of 2% (if that is still deemed to be the
correct level following the risk review) would require minimum balances
of £12.1m. A further £4.1m contribution is already allowed for in the
MTFP, depending on the outcome of the risk assessment it is possible
that not all of the £4.1m contribution to balances will be needed.
- As the grant settlement
is expected to be tight in 2006/07, there is a growing interest at the
Treasury and ODPM about the use of reserves. A full analysis of projected
reserves for 2006/07 is being undertaken currently and will be reported
in the next Service & Financial Planning Report to Cabinet on 20
December.
Total
Formula Grant Forecast
- The MTFP total
formula grant forecast for 2006/07 is £367.2m. Of this, an estimated
£285.9m will be DSG, this assumes a 6.8% increase (the government have
promised at least 6%). This potentially leaves £81.3m as the residual
grant figure. If the DSG is higher, the residual grant will be smaller.
- Our forecast assumes
that the benefits of the extra resources announced for the 2005/06 Settlement,
(estimated at that stage to be worth around £6.2m for Oxfordshire) would
not continue and that having deducted this we would then receive a 5%
increase in grant.
- Uncertainty about
the grant forecast continues, for various reasons, including:
- Continuation of
extra resources announced for 2005/06
- The FSS formula
and grant review
- The uncertain
effects of grant floors
- The introduction
of DSG
- Draft amending
reports
- The FSS Formula
and grant review includes over 40 options for changing the system. Very
recently, revised versions of three of the options that have significant
effects on Personal Social Services (PSS) have been announced. Including
these three very recent changes, the 19 best options for change in the
review would now increase our grant by £3.349m, whereas the 20 worst
options would lead to a loss of £31.953m. Thus there is a continuing
high risk of large grant losses as a result of the review.
- Grant floors would
probably delay the effects of the worst FSS and options. However, large
losses would worsen our grant position, in the years after 2006/07.
Grant floors might, in our most favourable forecasts, guarantee that
our residual grant in 2006/07 would be no less than the notional amount
for 2005/06 (of £88.234m). This would obviously be much more favourable
than the £81.3m that we are currently assuming. This wide range illustrates
the continuing uncertainty about the grant consultation announcement
that is now expected in December.
- In the longer
term, the introduction of DSG seemed likely to leave the Council slightly
worse off, perhaps by £1.3m. Schools in contrast, could be £0.8m better
off. However the consultation suggests that the government might include
grant changes and grant floors that protect the Council against at least
some and possibly all of the effect of introducing DSG, at least in
2006/07.
- Draft amending
reports have recently been issued for 2004/05 and 2005/06. These show
minor changes in both years to give a £0.043m increase in grant relating
to 2004/05 and a £0.089m reduction in grant relating to 2005/06.The
net amount (a grant loss of £0.046m) will be deducted from our grant
payments during 2006/07.
Capital
Programme
- In February 2005
the Council agreed a three-year capital programme covering 2005/06 to
2007/08, which allocated all the available resources at that time.
- In February 2006
the Council will need to agree an updated three-year programme adding
2008/09 as the new year three. The Directorates have been asked to bring
forward capital proposals for consideration against the resources available
for 2008/09. These proposals will be brought forward in a future report
to Cabinet, with a recommendation from the Capital Steering Group as
to which schemes should be supported for inclusion in the three-year
programme to be agreed by Council.
- The Council has
in the past agreed a number of criteria for the capital programme. These
include that Learning & Culture can bring forward a schools programme
in balance with the resources available, Transport can bring forward
a programme which allocates resources approved in the Local Transport
Plan, and that the Council would utilise all credit allocations given
by Government departments. Credit approvals given by Government departments
attract grant through the revenue support grant mechanism. The costs
of new borrowing to fund the capital programme are therefore broadly
matched by additional Government grant.
- The capital programme
is currently forecast to be in surplus by £22.6m at the end of 2005/06.
This surplus will be mostly used up over the years 2008/09 as planned
in the agreed capital programme, leaving a residual balance of £0.9m.
- In addition it
is anticipated that the Council will receive a further £1m of credit
allocation for 2008/09 in relation to fire and social services.
- This leaves £1.9m
of resources available to fund new capital proposals in 2008/09. A the
programme is in surplus up to 2008/09 there is an option to bring forward
any projects considered urgent into years earlier than 2008/09.
- It may be prudent
not to allocate all available capital resources fully at this stage,
so that there would be a contingency available for any urgent capital
issues that arise over the next three years. It may be appropriate at
the stage to plan for only £1m of new capital projects, proposals for
which will be brought forward from the Capital Steering group.
Prudential
Borrowing
- Prudential Borrowing
is available in addition to government supported borrowing through credit
allocations. The Council has to show that any additional borrowing taken
under Prudential Borrowing is prudent and affordable. This is monitored
by Council approving a series of Prudential Indicators each year.
- The Council has
a policy to use Prudential Borrowing, but only where there are savings
that meet the additional borrowing costs incurred. (Otherwise the revenue
consequences of the borrowing would need to be positively justified
as a policy change as an addition to the revenue budget.) To date the
main commitment under Prudential Borrowing is tackling backlog maintenance
in the Council’s buildings for which £25m has been allocated over six
years. Further projects may come forward in the future requiring Prudential
Borrowing and these will be brought to Cabinet for approval as they
arise.
RECOMMENDATIONS
- The Cabinet
is RECOMMENDED to :
- note
the report;
- refer
the identified budget pressures in the respective service areas,
and the choices as to how these could be funded, to the Scrutiny
Committees for consideration and advice, on the basis of schedules
to be drawn up and presented to the committees by the Head of
Finance & Procurement with the relevant service officers,
following consultation with the appropriate Cabinet Members.
JOANNA
SIMONS
Chief Executive
JOHN JACKSON
Director for
Resources
Background
Papers: Nil
Contact
Officers:
Sue Scane, Head of Finance & Procurement Tel. 01865 816399
Paul Edwards,
Corporate Performance Manager Tel. 01865 815307
Lorna Baxter,
Strategic Financial Planning Manager Tel. 01865 816087
Mike Petty, Strategic Finance Manager Tel. 01865 815422
November
2005
Return to TOP
|