ITEM EX6
Report of: Strategic Director for the Environment (Oxford City Council) and Assistant Chief Executive (Oxfordshire County Council) Title: AREA DEVELOPMENT FRAMEWORK FOR THE WEST END Ward: ALL Report author: David
Steel/Chris Impey Key Decision: Yes Lead Members: Councillor Hollingsworth (City Council) and Councillor Mitchell (County Council) Scrutiny responsibility: Environment
The Area Development Framework (ADF), recently received from David Lock Associates (DLA) provides an exciting vision for the renaissance of Oxford’s West End. Further work is required to develop the vision and begin the process of implementation, but the ADF will enable the City Council to commence work on the preparation of an Area Action Plan for the West End, and at the same time to use the City and County Councils’ West End land-holdings to help further shape and deliver the vision outlined by DLA. The number of development opportunities identified in the Second Deposit Oxford Local Plan and the ADF together with the number of pre-application enquiries being received, clearly indicate that there is a high level of interest in the West End. Work is underway on two major projects at Oxford Castle and a mixed development alongside Castle Mill Stream. The ADF will enable the two Councils to be proactive in dealing with future applications: to lead rather than to follow. Renaissance of Oxford’s West End is identified as a priority strategic objective of the County Council, will lead to substantial progress against several elements of the City Council’s Vision Statement, and will assist in meeting objectives of both City and County Councils’ Community Strategies. The West End provides an opportunity to facilitate countywide transport improvements currently under consideration in the draft Local Transport Plan (LTP2). The West End Partnership (Oxford City and Oxfordshire County Councils and SEEDA) commissioned DLA to produce an ADF for Oxford’s West End in March 2004. At the same time Ove, Arup and Partners (Arup) was commissioned to advise on the feasibility of improving railway station arrangements for Oxford including a possible relocation of the station. Following extensive research and consultation the ADF has now been received and endorsement is being sought from the partner organisations. A copy of the ADF has been given to each Member and is available too for public inspection on www.oxfordwestend.co.uk including all the supporting papers.
The ADF combines three elements:
It is hoped that all Members have had an opportunity to read the full ADF in which there is important visual information to illustrate the text. However, the central components can be summarised as follows: Design concept The West End is identified as a city quarter which itself can be subdivided into four quarters each with a distinctive character. Each quarter should be encouraged to develop around a public space and establish its connection to the adjoining Castle Mill Stream. Oxford Castle lies at the heart of the four quarters and thus provides a link to the whole area. Development principles A set of principles underlies the approach in the ADF. They are recommended as a set of tests.
Illustrative Vision An illustrative vision has been drawn up to indicate one way that the design concept could be interpreted. Based on the development principles, Turner Morrum Associates (TMA) has undertaken a block-by-block assessment of the value of the illustrative development along with the likely value of developer contributions. TMA clearly demonstrate that the development is viable but that any development fund generated will be modest in scale. The development gain will be insufficient, for example, to make a meaningful contribution to the station move/redevelopment. Development issues In preparing the ADF the consultant team considered a range of significant issues for the West End. These have played a large part in shaping the ADF and defining the strategy.
The underlying development Issues are:
Work is well under way on some of these projects but in no case is it yet complete. As an example work is nearing completion on options to relocate the railway station as identified in the Arup report. Currently the cost and benefit of moving the station suggest that capacity improvements at the current site is the best option. However, the Strategic Rail Authority has commissioned a study of the implications for the Botley Road before making their decision known in June. In summary, the ADF is an exciting piece of work that has recommended a vital future for the West End, one that while visionary is grounded in reality and suggests a way forward that can be implemented. Therefore it is suggested that DLA and the other consultants should be warmly congratulated for their work, including the efforts that they made to engage with the public and other important stakeholders.
Overall the West End renaissance will be a substantial and costly project where most of the costs will be borne by the private sector, but one where costs are contained or self-financing as far as the two Councils are concerned. For example ring-fenced income from developers should be available to fund necessary public realm and infrastructure works. It is suggested that a development fund be established to enable contributions from different developers to come together to fund major infrastructure works. The viability of the project will depend on a robust approach being taken to developer’s contributions; a proactive approach through a priority list of necessary works, some outside of the West End, is currently being drafted. A partnership budget already exists to cover elements of the necessary project management work as they unfold in 2005/06.
As the project develops and both Councils become actively involved in various capacities, consideration will need to be given at each relevant stage to ensure that each Council has the appropriate powers to act. Similarly as the project develops consideration will need to be given to the possibility of creating an appropriate separate legal vehicle to take the project forward.
The Steering Group has considered immediate staffing implications. Further work has been requested on the details, but it is considered that about two posts needed to take forward the new tasks and responsibilities can be funded from the existing West End budget for 2005/06. There will also be pressures on Planning and Transport for both Councils but such pressures should be dealt with through the normal business planning processes as they arise.
The West End Steering Group at its last meeting considered a Project list. The Steering Group want clear management of the overall programme to provide momentum and coherence to the eight strands shown below.
Background papers:
March 2005
|