|
Return
to Agenda
ITEM
EX8
EXECUTIVE
– 28 OCTOBER 2003
REGIONAL
MINERALS STRATEGY – CONSULTATION BY SOUTH EAST ENGLAND REGIONAL ASSEMBLY
Report by
Head of Sustainable Development
Introduction
- In September 2003
the South East England Regional Assembly (SEERA) published a draft Regional
Minerals Strategy (RMS) for consultation. A copy is in the Members’
Resource Centre. The consultation period ends on 3 November 2003. The
strategy will form part of regional guidance to local authorities on
how their land use, transport and waste management policies should address
regional issues. In particular, it will give guidance to mineral planning
authorities (MPAs) on policies for the future supply of minerals. This
report provides background to the RMS and makes recommendations on the
County Council’s response to the consultation.
Background
- The RMS will replace
the minerals section of the existing Regional Planning Guidance for
the South East (RPG9) and the Sub-Regional Aggregates Apportionment
(the apportionment of the regional supply requirement between counties)
that was agreed by the former SERPLAN in 1994. Its production has been
held up by the Government’s delay in finalising the new ‘National and
Regional Guidelines for Aggregates Provision in England, 2001-2016’
(the Aggregate Guidelines), which was only published in June 2003. It
covers the period to 2016, in line with RPG9 and the new Aggregates
Guidelines.
- The RMS encompasses
the whole of the area covered by SEERA and covers those minerals that
are of regional significance: brick clay, chalk, silica sand, gypsum,
fullers earth, and construction aggregates. Of these, only fullers earth
and construction aggregates are currently of significance for minerals
planning in Oxfordshire. It follows the same general approach as earlier
regional strategies produced by SEERA, and relates particularly closely
to the Regional Waste Management Strategy which is currently being finalised.
The RMS focuses firstly on measures to reduce demand for minerals, secondly
on the recycling of previously used materials, and finally on the supply
of newly extracted (primary) minerals to meet the residual regional
need.
- The RMS is of
particular significance for Oxfordshire in that it sets out a new sub-regional
apportionment of primary aggregates provision from quarries in the South
East. This gives figures for each mineral planning authority (MPA) of
the level of provision that should be made for the supply of sand and
gravel and crushed rock in their development plans.
Overall
Strategy Approach
- The RMS promotes
a ‘natural resource management’ approach to minerals planning, involving
the following ‘hierarchy of actions’:
- development
of sustainable construction practices to reduce growth in demand
for minerals;
- increased
use of recycled materials and mineral wastes as alternatives to
primary mineral extraction;
- appropriate
use of imported materials to supplement local supply;
- sufficient
planned provision for mineral extraction to meet the Region’s
share of national supply;
- effective
management of mineral extraction and processing within environmental
objectives and safeguarding of future supplies.
- The RMS stresses
that the maintenance of a healthy regional economy will require an adequate
supply of minerals to deliver the housing programme and infrastructure
projects, but that planning policy has to balance the need for minerals
with the environmental impact arising from their extraction, processing
and transport. It says MPAs should ensure provision is made for sufficient
supplies of other minerals to meet regional and, where appropriate,
national needs, but that self sufficiency of supply is unachievable
at either regional or local level.
- This approach
to minerals planning supports the approach taken in the draft Oxfordshire
Structure Plan Review.
Policies
for Sustainable Construction, Recycling and Re-use
- Policy M1 promotes
sustainable construction practices through SEERA working with partners
to promote good practice, reduce wastage and overcome constraints, with
the aim of stabilising annual consumption of primary aggregates by 2016.
In particular it says development plans should ensure development projects
use construction materials that reduce demand for primary aggregates
wherever practicable, and should promote effective environmental management
of mineral extraction and restoration and increased movement of minerals
by rail and water.
- Policy M2 says
use of secondary and recycled aggregate materials in the South East
should increase to at least 7.4 million tonnes per annum (mtpa) by 2016;
and that MPAs should make provision for recycling facilities to enable
this target to be met. Policy M3 urges Government action to adopt statutory
recycling and recovery targets for construction and demolition waste
and to promote more sustainable construction practices and recycling
projects.
- These policies
will help to secure more sustainable construction practices and increase
the use of secondary and recycled materials, thereby reducing the need
for primary aggregates extraction. However, the target figure for 2016
of 7.4 mtpa seems unambitious and could be increased. I have some more
detailed comments on these policies, which are set out in the annex
to this report.
Policy
for Primary Aggregates
- Quantitatively,
the most important minerals in the South East (and in Oxfordshire) are
construction aggregates. The Government’s new Aggregates Guidelines
set out the levels of provision expected to be made from different aggregate
sources and includes the following figures for provision over the period
2001-2016. The guideline figures for the South East, with the actual
supply figures for 2001 for comparison, are:
|
|
Total
Guidelines Provision
2001-2016
(tonnes)
|
Annual
Provision
2001-2016
(mtpa)
|
Actual
Supply 2001 (tonnes)
2.2
|
|
Land-won
sand and gravel
Land-won
crushed rock
Marine
sand and gravel
Secondary
and recycled materials
Imports
to England
Total
|
212
35
120
118
85
570
|
13.25
2.2
7.5
7.4
5.3
35.6
|
13.4
2.4
7.2
6.6
3.8
32.4
|
These
figures do not include an additional 9 million tonnes of crushed rock
imported from other regions (mostly by rail). Inter-regional imports
and exports of sand and gravel were broadly in balance.
- The guidelines
figure for land-won sand and gravel is 19.7% less than the previous
(1994) guidelines figure for the South East, reflecting a 19% reduction
in the national guidelines figure. However, the South East figure for
land-won crushed rock is 10% higher than the previous figure, reflecting
recent increased supply from this source.
- The RMS proposes
a regional land-won sand and gravel supply figure of 13.0 mtpa, slightly
less than the Government’s guideline figure. The RMS proposes that this
be apportioned initially to MPAs on the basis of average production
over the period 1995-2001. The regional land-won crushed rock figure
is proposed to be apportioned between Kent and Oxfordshire, being the
only counties with significant crushed rock resources, again on the
basis of past average production. The RMS says the apportionment is
to be reviewed following the consultation and in the light of a strategic
sustainability appraisal that is currently being undertaken.
- Policy M4 says
the supply of aggregates in the South East should be from a significant
increase in secondary and recycled materials, a reduced contribution
from primary land-won resources, and increases in landings of marine
sand and gravel and imported crushed rock. It sets out the level of
provision for land-won primary aggregates (the apportionment) that should
be made by each MPA through their development plans. The proposed apportionment
figures for Oxfordshire, with the regional provision figures for comparison,
and showing the proportion of regional provision to be met by Oxfordshire
compared with the previous (1994) position, are:
|
Aggregate
Type
|
Annual
Regional Provision (mtpa)
|
Proposed
Oxfordshire Apportionment (mtpa)
|
Proportion
of Regional Provision 2003
|
Proportion
of Regional Provision 1994
|
|
Land-won
sand and gravel
Land-won
crushed rock
|
13.0
2.2
|
1.96
1.0
|
15%
46%
|
12%
33%
|
|
Total land-won
aggregates
|
15.2
|
2.96
|
19%
|
14%
|
- In making a response
to the proposed new apportionment, the following points should be considered:
- the proposed
Oxfordshire sand and gravel apportionment is only 2% less than
the 1994 apportionment (2.0 mtpa), compared with a regional reduction
of 21% and reductions for all other MPAs of between 7% and 97%;
- the proposed
Oxfordshire crushed rock apportionment is over 50% higher than
the level of production around 1994 and as provided for in the
Minerals and Waste Local Plan 1996 (0.65 mtpa) (there was no apportionment
for crushed rock in 1994);
- the proposed
total Oxfordshire apportionment is 12% higher than the level of
provision made under the 1994 guidelines and apportionment, compared
with a regional reduction of 18% and a reduction (in most
cases substantial) in provision for all other MPAs;
- the proportion
of regional provision proposed to be made by Oxfordshire is increased
from 14% in 1994 to 19%;
- the proposed
total Oxfordshire apportionment is 9% higher than the level of
production in 2002 of 2.71 million tonnes (1.79 million tonnes
sand and gravel, 0.92 million tonnes crushed rock).
- There may be a
case for an increase in crushed rock provision from Oxfordshire, given
the higher guideline figure for the South East and the limited availability
of crushed rock resources in the region. As one of only two counties
with significant resources, Oxfordshire would inevitably play a role
in supplying crushed rock. But Oxfordshire should not at the same time
be required to make continued sand and gravel provision at almost the
same rate as previously, when resources of this material are widely
distributed across the region. I consider the very small decrease in
the sand and gravel apportionment for Oxfordshire, which has resulted
in a significant overall increase in Oxfordshire’s apportionment, to
be illogical and unsustainable.
- I consider that
a strong objection should be made to the proposed apportionment in Policy
M4, particularly to the sand and gravel apportionment, on the following
grounds:
- the proposed
apportionment is based on a backward-looking methodology, relying
on past production, and does not consider either the distribution
of future demand for aggregates in the South East or the future
supply capability of aggregate resource areas;
- use of this
methodology has produced a 12% increase in the overall apportionment
for Oxfordshire, in contrast to a regional reduction of 18% and
a reduction in the apportionment for every other MPA, despite
the following factors;
- Oxfordshire,
and in particular its main aggregate resource areas, lies at the
periphery of the South East region and is very poorly located
in relation both to the major development areas planned in the
region under the Government’s Sustainable Communities programme
(Thames Gateway, Ashford (Kent) and Milton Keynes) and to London
(the main export market for aggregates from the South East);
- under the
proximity principle, aggregates provision to supply these development
areas should be made from resources closer to them than Oxfordshire;
the aggregate resources of Oxfordshire are affected to a very
substantial extent by environmental and other constraints which
will limit the ability of the County to supply aggregates without
significant harm being caused, in particular:
(a) the
sand and gravel deposits that are not within Areas of Outstanding
Natural Beauty occur mainly within the Valley of the River Thames
and its main tributaries, where the water table is generally high
and much of the land is liable to flood; and they are also almost
all within one or more of the safeguarding zones for the nine
safeguarded airfields (8 military and 1 civil) which lie within
or affect Oxfordshire;
(b) a
significant proportion of the limestone resource of Oxfordshire
lies within an Area of Outstanding Natural Beauty;
- a new aggregates
apportionment for the Region should not be agreed until a full
sustainability appraisal has been carried out, taking into account
the expected future distribution of aggregates demand and environmental
and other constraints on aggregates supply (including aerodrome
safeguarding and the water environment) in a consistent manner
across the region.
Fullers
Earth
- Of the other minerals
covered in the RMS, only fullers earth is of significance in Oxfordshire.
However, the RMS says further consideration of this mineral in the strategy
is not currently warranted, but that this should be kept under review.
Consequently fullers earth is not covered by any policy in the RMS.
Safeguarding
- Policy M6 says
areas permitted and identified in development plans for working regionally
significant minerals and existing and proposed wharves and depots for
handling and distributing minerals should be safeguarded against other
development. The minerals specified in the policy include aggregates,
but not fullers earth.
- The inclusion
of a safeguarding policy in the RMS will provide a regional policy basis
for development plan policies that seek to avoid this sterilisation
of mineral resources which might need to be worked in the future. However,
this policy should be widened to cover all potentially significant mineral
deposits, including fullers earth. I have some more detailed comments
on safeguarding and fullers earth, which are set out in
the annex to this report.
Financial
and Staff Implications
- The RMS will set
a regional minerals policy framework for the review of the Minerals
and Waste Local Plan. Work on the Local Plan Review has commenced and
a programme has been drafted, which should be met from existing resources.
The RMS is not expected to impose any additional resource requirements.
Conclusions
- On the whole the
RMS covers those areas of minerals planning that are appropriate to
the regional level and provides a policy framework that will help the
development of minerals policy at county level. However, the proposed
aggregates apportionment places an unfair and unacceptable burden on
Oxfordshire and a strong objection should be raised. There are a number
of other issues relevant to Oxfordshire, on which comments should also
be made.
RECOMMENDATION
- The Executive
is RECOMMENDED to:
- agree
to the report forming the basis of the County Council’s response
to SEERA on the Regional Minerals Strategy Consultation Draft,
with particular reference to targets for use of primary aggregates
and for secondary and recycled materials, primary aggregates
provision (apportionment), fullers earth policy and minerals
safeguarding policy;
- in
particular, raise strong objection to the aggregates apportionment
proposed in Policy M4, on the grounds set out in paragraph 17
of the report.
CHRIS
COUSINS
Head of Sustainable
Development
Background
Papers: Nil
Contact
Officer: Peter Day, Tel: Oxford 815544
25
September 2003
Return to TOP
|