|
Return
to Agenda
|
Division(s):
Banbury Grimsbury
|
ITEM EX16
EXECUTIVE
– 14 OCTOBER 2003
NEW PRIMARY
SCHOOL, CATTLE MARKET, BANBURY – LAND ACQUISITION
Report by
Director for Learning & Culture
Introduction
- This report seeks
the Executive’s approval to proceed with the acquisition of land for
the purposes of a new primary school project in Banbury. The project
comprises the building of a new 7-class primary school including Foundation
Stage facilities on and adjacent to the former Cattle Market site in
Banbury, east of the town centre.
School
Development
- The Cherwell Local
Plan identifies in excess of 1,000 new dwellings (up to 2011) to be
provided on brown field sites in the central and eastern parts of Banbury.
This figure includes between 320 and 390 units at the Cattle Market.
Most other proposed dwellings are situated within the catchment areas
of three existing primary schools in Banbury: St Leonard's, St Mary’s
and Dashwood. All three schools have little spare capacity.
- A detailed option
appraisal has been undertaken which examined different ways in which
the additional pupils might be accommodated, including the further expansion
of St Leonard’s Primary School and/or St. Mary’s Primary School, and
the closure of Dashwood School and amalgamation with a new school. The
further expansion of St. Leonard’s School is considered undesirable
given the current size of the school and the shortfalls in its core
accommodation e.g. small hall. St Mary’s School has a limited site and
would require the purchase of additional land. The closure of Dashwood
School and the building of a larger school on the Cattle Market site
would require considerable funds additional to those which would be
generated from the sale of the Dashwood School site. The option appraisal
concluded that the most cost effective solution would be to provide
a new 7-class school at/by the Cattle Market site with expansion and
improvement at Harriers Ground School if necessary.
Land Acquisition
- On the basis of
the standards in the Oxfordshire Primary School Brief a total site area
of 1.306 hectares would be required for the new school. In view of the
significant costs of providing the school and uncertainty about eventual
pupil numbers (see Financial Implications below), it is necessary to
take a cautious approach to its planning and development. As the first
requirement is for the Council to secure sufficient site area to build
the school, it is proposed that the financial contribution from the
developers of the Cattle Market site under the planning agreement (£1.7m)
be provided as land. This equates to 0.728 hectares. An "agreement in
principle" has already been reached with the Cattle Market site developers
as to the provision of this land.
- The balance of
the land required for the school is also proposed be found partly from
within the Cattle Market development area but outside the scope of the
planning agreement. It is proposed that this should be leased from the
developers with a 3-year option to buy. Again this has been agreed in
principle with the developers. However this will not be sufficient on
its own to provide all the land required for the new school. Accordingly
Cherwell District Council has been approached about the feasibility
of releasing an area of land in its ownership adjacent to the development
area. The District Council has indicated that it would be willing to
sell this land to the County Council, on a market value basis.
- This will provide
more time for a final decision to be made on the school. If it is eventually
decided not to proceed with the school development, or to pursue another
option, the land acquired could be sold and any lease terminated. However,
a decision on the acquisition of the land is required now because of
the outstanding planning application and planning agreement for the
Cattle Market site development.
Financial
Implications
- The current estimated
cost of the school buildings (including the improvement at Harriers
Ground) is £3.65m. The total cost of land acquisition is likely to be
of the order of a further £3m. It has become increasingly difficult
to calculate the number of pupils generated from the proposed developments
in the area, and although it is intended that developer contributions
will be sought from each of the developments towards permanent school
accommodation, there is likely to be a larger number of 1 or 2 bedroom
properties than previously anticipated - which will have a knock-on
effect in terms of developer contributions. There is, therefore, some
uncertainty about whether the costs falling on the County Council could
be wholly repaid through developer contributions.
- Accordingly the
purchase and transfer agreements under negotiation will ensure that
the Council’s costs in acquiring land at this stage could be recouped
at a later date through re-sale (or sale back) if not required for the
school development. However, to ensure certainty over site availability,
it will be necessary to pay for the District Council land over the coming
months. This has been agreed at £300,000 and is the total being committed
at this stage other than some fee costs.
- It should be noted
that apart from further design work, no other work will be undertaken
on this project until an agreement with the developer for the land acquisition
is firm and further assessment of pupil generation is undertaken.
RECOMMENDATION
- The Executive
is RECOMMENDED to authorise the acquisition of the land for the proposed
school on the basis set out in the report.
KEITH
BARTLEY
Director for Learning & Culture
Background
papers: Nil
Contact
Officer: Michael Mill, Education Officer, Tel: (01865) 428161
September 2003
Return to TOP
|