|
Return
to Agenda
ITEM EX20
EXECUTIVE
– 10 DECEMBER 2002
GTE FOR
OXFORDSHIRE
Report
by Director of Environmental Services
Introduction
- On 1 October 2002,
the Executive gave in principle approval to funding GTE work through
to the end of the "Project Authorisation" phase in 2005/06, and as part
of this agreed a significant increase in capital funding for the GTE
Project for 2003/04, with £800,000 identified for the scheme. This figure
is subject to confirmation following the Government’s Single Capital
Pot (SCP) allocation for the County and the division of this funding
between budgets.
- The GTE Project
is being run by a "Special Purpose Company" comprising 15 public and
private sector partners, which own shares in the company and have directors
on its board. These include the County Council, which is represented
by Councillor Bill Bradshaw, who chairs the Company. At the time the
GTE Project Company was set up, the Council placed the Company in the
"bodies useful to the Council’s work" category, and it currently has
"non-strategic" outside body status.
- Given the significant
increases in County Council funding, it was agreed that further consideration
needed to be given to the mechanism by which this funding is spent and
the control procedures required to achieve this. I undertook to report
back to the Executive on these matters and this is the principal subject
of this report. The report also considers the need to change the status
of the Company given the recent developments that have taken place.
Background
- County Council
funding previously allocated to GTE has been transferred to the Project
Company in the form of a conditional grant, the condition being that
the funding is spent on the GTE project, specifically the delivery of
work outputs and targets clearly identified and agreed (for example
the undertaking of the current Project Definition work programme).
- The Project Company
was set up in a particular way, such that the combined participation
of the local authorities involved (the City Council are also shareholders
and have a director on the board) is less than 20% of both the total
shareholding in the company and the total number of directors on the
board. The reason for this is that exceeding this 20% figure would mean
that local authorities would be deemed to have influence or control
over the Company, which would mean the Company would effectively be
viewed as an extension of the local authorities’ activity and, for example,
expenditure of the Company would count as that of the local authorities
involved.
- It is considered
advantageous to maintain both the Company running the GTE Project, and
the set up of the Company as described above, for a number of reasons:
- It allows the
Company to operate independently of the County Council (for example
appointment of consultants is not required to be undertaken via a
tendering process);
- It provides
a mechanism for private sector partners to join the Company and contribute
funds to GTE – some £300,000 of private sector cash and work in kind
has been contributed to the Company so far;
- It would maintain
the genuine public-private sector partnership approach to GTE, which
is advantageous in terms of drawing in private sector expertise, involving
key local stakeholders in the development of GTE, and demonstrating
an approach consistent with Government policy which has been successful
elsewhere (for example, the recently-approved tram system in Nottingham
was promoted along similar lines).
Proposals
- Three means of
achieving greater County Council involvement in the project are proposed,
covering the project’s status, day-to-day officer and member input and
the management of the proposed additional funding.
- Firstly, it is
proposed that Council be recommended to agree that GTE should be given
"strategic" outside body status. This is on the basis of:
- the significant
additional (and ongoing) County Council funding agreed in principle
for the project;
- the increased
strategic importance of GTE, given for example the recently agreed
strategy for the A40 corridor (which includes the GTE project as an
essential element) and the close interrelationship between GTE and
the development of the railway through Oxford (in particular the proposed
relocation of Oxford Station);
- the increased
likelihood of funding to implement GTE being bid for as a Major Scheme
in the next Local Transport Plan.
Should
this change of status be agreed, the appointments to the GTE board will
be within the gift of the Executive. If not, the appropriate recommendations
will need to be made to Democracy & Organisation Committee,
following
consultation with the appropriate Executive Member and Scrutiny Chair(s)/Deputy
Chair(s).
- It is felt that
the second objective would be achieved by the appointment of an additional
County Council representative to the GTE Company board. This would still
allow the combined local authority representation to be within the 20%
threshold identified above. Given the executive arrangements now in
place, it is logical that the Executive Member for Transport be nominated
as the additional member.
- Since Councillor
Bradshaw was appointed (June 1999), Councillor John Dennis was appointed
as his alternate to the board. Although this appointment was never formally
terminated, it is considered to have come to an end at the County Council
election in June 2001 (even though Councillor Dennis has since been
re-elected to the Council.)
- The issue of an
alternate raises the question that, if two County Councillors were to
sit on the board of the Project Company, whether each would require
an alternate. On balance, given the frequency of board Meetings and
member involvement in the Company’s activities, it is felt that one
alternate (who could substitute for either County Council board member)
would be sufficient. Again, considering the Executive arrangements now
in place, it would be logical for the Executive Member for Strategic
Planning and Waste Management to be nominated as the County Council’s
alternate Director.
- Both the appointment
of an additional County Council Director and a new alternate Director
would need to be endorsed by the board of the Project Company, which
next meets on 20 January. I have no reason to believe that these appointments
would not be accepted by the board; indeed they are likely to be welcomed
as a reflection of the County Council’s increased commitment to the
project.
- At officer level,
responsibility for the GTE Project has recently transferred to the Sustainable
Transport (Special Projects) Group within Environmental Services, as
proposed in the report to 1 October Executive. This will allow the project
to be managed alongside complementary proposals such as the County’s
recently approved strategy for the A40 (which is partially predicated
on GTE being delivered) and the Premium Routes study. Additional resources
have been approved for this Group to strengthen the officer input to
the project.
- Turning to the
financial arrangements, it is proposed that funding agreed to the project
be allocated to the Project Company in the form of a conditional grant,
as previously. However, in order for the allocation and expenditure
of this funding to be more closely monitored, the following is proposed:
- that the allocation
for 2003/04, currently £800,000, is granted in up to four stages,
with an initial allocation to be made in April 2003 (following approval
of the capital programme in March) and further allocations on (for
example) a quarterly basis, as required and agreed;
- that each allocation
is more closely tied to specific project milestones and deliverables,
to be agreed with the County Council directors on the board;
- that an annual
report is submitted to the Executive, detailing how the funds have
been spent in the previous financial year and outlining the funding
required for the forthcoming financial year, for consideration as
part of the annual capital programme.
Conclusions
- Three means are
proposed to secure greater County Council involvement in the management
and development of the GTE Project:
- A change of
status of the County Council’s designation of GTE, from a non-strategic
to a strategic outside body. This will need to be agreed by Full Council.
- The appointment
of the Executive Member for Transport as an additional County Council
Director on the GTE board, together with the appointment of the Executive
Member for Strategic Planning & Waste Management as an alternate
Director for either board member. These can be agreed by the Executive
subject to (i) above and would be subject to the approval of the GTE
board;
- Introducing
more stringent control and monitoring of how County Council funding
granted to the Project Company is spent, to be agreed with the County
Council Directors on the board and reported back to the board on an
annual basis.
Environmental
Implications
- There are no significant
implications arising from this report.
Financial
and Staff Implications
- The principal
implications for the project were identified in the report to 1 October
meeting of the Executive. There are no further significant implications
arising.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- RECOMMEND
the Council to agree the inclusion of GTE for Oxfordshire in
the list of strategic outside bodies for the purpose of Section
H of the Constitution;
- subject
to (a) above, approve the appointment of the Executive Member
for Transport as an additional County Council Director on the
GTE board, together with the appointment of the Executive Member
for Strategic Planning & Waste Management as an alternate
Director for either County Council board member;
- subject
to the finalisation of the Capital Programme for 2003/04, agree
that the funding provisionally allocated to the project for
2003/04 be conditionally granted to the Project Company in up
to four stages, with the amounts and conditions for each stage
to be agreed by the County Council Directors on the board in
consultation with the Director for Environment & Economy.
DAVID
YOUNG
Director of
Environmental Services
Background papers: Nil
Contact
Officer: John Disley Tel: Oxford 810460
November
2002
Return to TOP
|