|
Return
to Agenda
ITEM EX11
EXECUTIVE
– 10 DECEMBER 2002
SCHOOLS
PFI CREDITS
Report by
Acting Chief Education Officer
Introduction
- PFI credits issued
by the DfES will amount to over 25% of total capital support available
to schools in 2004/05. LEAs will be required to submit, by the beginning
of January 2003, an expression of interest to the DfES on prospective
school PFI schemes that would meet the appropriate prioritisation criteria.
It is expected that over £1 billion will be available in this round
of bidding following the recent Public Sector finance review. It is
likely, however, that demand will once again exceed the amount of funding
available.
- This report is
being circulated to the Learning & Culture Scrutiny Committee for
its meeting on 3 December. Any comments on the part of the Committee
will be reported at the meeting.
Background
to PFI
- In 1999/2000 there
were 14 successful bids with an average value of £31 million. This has
grown to a position in 2003/04 where there are 21 successful bids, with
an expected average value of £44 million. An increasing number of these
schemes involve groups of schools. The overall impact is to provide
significant numbers of new buildings very quickly, providing fully serviced
schools for, typically, 25 years. Contractors are paid a unitary charge
over that period of time and the capital cost of this are provided through
credit approvals which are additional to the usual authority entitlement.
At the end of the contract period the buildings are usually handed back
to the LEA and the expectation is that they will be in excellent condition.
- PFI provides:-
- The opportunity
for large scale investment
- Budgets to maintain
high standards
- Reinvestment
in assets over contract period
- The ability
for schools to focus managerial time on educational attainment
- The more likely
delivery of the project on time and cost with appropriate transfer
of risk to the provider
- 0-10% savings
over traditional procurement
However,
there are issues in the following areas:
- Restricts financial
flexibility for the LEA and the school
- Governors concern
over LMS and how the school budget will be affected
- Quality of design
has been variable in the past
- Complex procurement
process
- Staff resources
and need for a skilled team
- Procurement
costs
- In financial terms
PFI provides the benefit of PFI credits from the Government and there
is no requirement to pay anything to the contractor until buildings
are fully operational, but there will be revenue costs through the procurement
process in accessing appropriate staff and expert legal and financial
advice. If an expression of interest proves to be successful and a more
detailed scheme is developed and agreed then the County Council will
need to acknowledge that additional funds over and above the PFI credits
may be required.
Criteria
for PFI credits
- Outline Option
Appraisals need to be carried out in order to establish which schemes
would be most suitable for PFI and also meet the criteria as set out
by the DfES. These focus on the following:-
- How the project
will transform educational attainment and address wider DfES priorities
(40% of the marks). There is a new focus on transforming secondary
education, dealing with schools of concern, supporting the 14-19 agenda,
workforce reform, inclusion, community schools and better ICT infrastructure.
- How the project
will transform the school estate (40% of the marks). LEAs are
required to indicate the equivalent capital spend that would be used
to overcome sufficiency, condition and suitability problems within
schools – each element carrying equal weighting.
- How the project
will address wider Government priorities (10% of the marks). Proposals
that seek to tackle wider Government priorities will score higher
marks. This could include addressing social inclusion and non-school
elements such as libraries, health and sport.
- Project delivery
and PFI development (10% of the marks).
- Indications are
that the DfES employ a marking scheme out of 20. Clearly on such a marking
scheme 1 point or ½ a point has made a difference between schemes being
accepted or not. Therefore it is very important to try and address all
the issues raised in the criteria.
Proposals
for PFI bid
- There is a logic
in a bid which encompasses one part of the County given the relative
inexperience that the authority has in this form of procurement, but
this must be balanced with the fact that a project must be large enough
to make a difference and be attractive to contractors. Given the change
in the criteria that were announced on 30th September, there
is a possibility of looking at a bolder more wide ranging grouped schools
bid that aims at transforming secondary education in a number of places.
- Certain areas
of the County have situations which may lend themselves to a PFI bid
and a number of schools have been proposed. These include the County
towns ear-marked for growth (Banbury, Bicester, Didcot, Witney) and
also Sonning Common and Wantage.
- The methodology
that needs to be applied is to carry out outline option appraisals on
different schemes to see whether they would meet the DfES criteria,
time scales for signing a contract, and whether a PFI scheme is likely
to produce the outcomes that are required and where funding through
traditional means is not available or insufficient and does not provide
such good value for money. Outline option appraisals have been carried
out on several schemes and costings have been looked at on a whole life
basis in comparison to other alternative methods of funding.
Banbury
- A scheme could
encompass the redevelopment of schools in Banbury and provides real
opportunity to improve the school estate and raise standards from a
relatively low base. It is likely that a bid that includes Banbury School
will contribute most to an expression of interest. The school is currently
categorised as having serious weaknesses and the buildings themselves
have significant problems and are scattered around a large site. The
prospect of a capital receipt for the existing Stanbridge Hall site
would assist in the value for money test. The assessed condition needs
of the school are high. A scheme here would make significant impact.
An option appraisal would demonstrate that Drayton School would not
meet the criteria in school buildings terms, but a development plan
needs to be agreed so that other sources of funding possibly freed up
by a development of Banbury School could be directed to more limited
work at Drayton School in the medium term. It is proposed to include,
under basic need, a bid for a new 7 class primary school in the centre
of Banbury, which given site issues and distribution of housing may
be difficult to procure through traditional means.
Bicester
- Proposals are
currently being explored with regard to a possible 3rd secondary
school in Bicester. The expectation is that this might be an 11-16 school
with 6th form provision being focused at Bicester Community
College. Although Bicester Community College could accommodate all the
growth in the current Local Plan it would not be able to do so beyond
that period and therefore it is prudent to look at a new secondary school.
However, planning issues are not well developed and the inclusion of
a new school of sufficient size is not possible within the time scales
necessary for a bid this time round. Bicester Community College has
had extensive new work and new buildings recently. Cooper School is
full and has no capacity for further growth. Both its condition needs
and suitability problems are significant. It currently features as the
2nd worst school on the current suitability assessment(AMP).
It might expect some limited funding though the NDS Modernisation Fund
in the next 2-3 years. However, given the development of new provision
within the town and the high identified need at Cooper School, there
is a strong case for including the school in a PFI project, in order
to secure its long term future and enable it to make progress in raising
standards.
Didcot
- There is a requirement
for an additional 3,200 houses on the west of Didcot and a further 1,200
elsewhere in the town. The Didcot Girls’ School site is below the size
required for a school of its size and St Birinus is constrained on its
current site, despite off-site sports fields. Excluding these developments
numbers on roll at both schools are planned to rise to over 1,600 by
2008. It is clear that a 3rd secondary school is required,
a strategy agreed by the County Council 3 years ago. It is proposed
to secure 3 schools each with a permanent capacity of 1,450. 600 pupils
would be generated from the west Didcot site for which developer contributions
would be sought. This, however, still produces a significant shortfall
both in terms of cost of buildings and land acquisition to provide for
the new school. In addition to this growth, Didcot Girls’ School has
600 temporary places and St Birinus 300. The Girls’ School has significant
condition needs. This also raises the whole issue of the need to bring
the other schools up to a similar standard to the new school, with 1,450
permanent places. Any new school could be built in a phased way, but
gives the opportunity to incorporate features which would score highly
in a bid. It provides an opportunity to build a new school in co-operation
with the Church of England Diocese to compensate for lost Church of
England places in Oxford City (subject to formal consultation), and
to open it with its own specialism, possibly Business and Enterprise,
given its potential location in respect of the Milton Business Park.
It would be anticipated that the joint 6th form arrangements
would continue and other resources such as community facilities could
be incorporated which provides a value for money benefit. The option
appraisal process would suggest that remodelling and refurbishing of
St Birinus and Didcot Girls’ School, along with the provision of the
3rd new secondary school, could be effectively procured through
PFI. It is also proposed to include Greenmere School which serves the
most deprived area of Didcot and its site is adjacent to St Birinus.
By including Greenmere this opens up the opportunity to develop this
and the St Birinus site more flexibly and to produce a more cost effective
primary school building to serve the community.
Sonning
Common (Chiltern Edge School)
- There is some
poor accommodation at the school and 180 temporary places. There is
no forecast growth at the school and it does not score highly on deprivation
or inclusion issues. Although the new guidelines support popular schools
not able to access other funds it is not untypical of a number of other
schools across the authority. Option appraisal would demonstrate that
it does not add to a proposed PFI bid at this stage.
Wantage
(King Alfred’s)
- Members will be
aware of reports outlining the Governors’ desire to promote a new secondary
school, probably on a site between Wantage and Grove, as part of the
proposed redevelopment within the Vale of White Horse Local Plan. The
school has currently around 25% surplus spaces, though it could be argued
that a higher proportion of surplus places is required as the school
operates on three sites. Members will be aware of the arguments relating
to the financial and achievement issues in respect of the operation
of a split site school. There are a number of other options to developing
the school, including consolidation within Wantage. Provision of a new
school would score highly on ‘other Government objectives’ and demonstrates
good value for money through possible capital receipts generated from
the sale of the existing sites. It is not possible to proceed with an
agreed scheme until the planning issues are resolved and they are not
far enough advanced to enable this school to be included within this
round of bidding.
Witney
Secondary Schools
- It is anticipated
that the Basic Need required within the West Oxford Local Plan to 2011
for Witney can be accommodated on the existing two school sites. Given
significant work at both schools in recent years, it is likely that
funding for this growth could be catered for from within Annual Capital
Guidelines allocations and developer contributions.
Conclusion
- Following option
appraisals of a variety of schools, it is felt that a strong bid could
be submitted on the basis that, having carried out a successful reorganisation
within Oxford City, it is sensible for the Education Department to seek
to make a significant difference in the other Country towns and that
an expression of interest be submitted which encompasses a 3rd
new secondary school at Didcot and the redevelopment of the existing
two schools, the Cooper School in Bicester and Banbury School. A new
primary school in the centre of Banbury will also be promoted and Greenmere
School will be drawn into the redevelopment of the St Birinus site.
- Other resources
through developer contributions and capital receipts are not sufficient
to enable objectives to be met through traditional means but will contribute
to demonstrating value for money and provide additional funds towards
the schemes and potentially enhance them further. An estimate on the
total level of PFI credits being requested and additional financial
information will be provided at the meeting. Should an expression
of interest by the Council be supported by the DfES, then consideration
and approval of detailed proposals will be required at a future date.
Supplement
RECOMMENDATION
- The Executive
is RECOMMENDED, subject to consideration of any views on the part of
the Learning & Culture Scrutiny Committee, to approve the submission
of an expression of interest for schools’ PFI credits to the DfES by
3 January 2003, to include a new aided secondary school in Didcot (subject
to formal consultation); remodelling/re-furbishing of St Birinus, Didcot
Girls, Greenmere School, Banbury School and The Cooper School; and a
new primary school in Banbury.
ROY
SMITH
Acting
Chief Education Officer
Background
Papers: Nil
Contact
Officer: Michael Mill, Education Officer-Premises Development
Tel: 01865 428161
November
2002
Return to TOP
|