|
Return
to Agenda
ITEM EX13
EXECUTIVE
– 15 OCTOBER 2002
TRANSPORT
CAPITAL PROGRAMME 2002/03 TO 2005/06
Joint Report
by Director of Environmental Services and Director of Business Support
Introduction
- On 17 April 2002,
the Executive approved the transport capital programme for 2002/03 to
2004/05 and asked to be updated on the progress on the programme in
October 2002. This report updates the 2002/03 programme and also seeks
approval, in principle, to a revised allocation for the programme under
the six main budget headings, as set out the Local Transport Plan (LTP),
for the period 2003/04 to 2005/06 to assist with the forward planning
of the programme.
- As last year,
the final approval to the detailed 2003/04 transport capital programme
is not anticipated to be made until April 2003 after the Executive has
considered the Single Capital Pot (SCP) capital allocation and the County
Council has approved the Capital Programme. However, it is important
if preparation work is to be undertaken on schemes to be implemented
in 2003 and beyond, that ‘in principle’ approval is given to the main
budget headings at this stage so that resources are directed at developing
the schemes most likely to form the programmes for 2003/04 and later
years.
Background
- On 19 February
2002 the Executive approved a provisional SCP allocation for the period
2002/03 to 2005/06 from which the detailed programmes for 2002/03 to
2004/05 were developed and subsequently approved in April 2002 (Annex
1).
- The forecast outturn
and other changes to the 2002/03 programme, together with other events,
now make it appropriate to amend this provisional SCP allocation. It
should be noted that the provisional SCP allocation was based on the
Government’s indicative allocations that were advised when the LTP settlement
was received in December 2000, updated to take account of the additional
£750,000 for 2002/03 included in the transport element of the SCP announced
in December 2001.
- Although the Government
specifically required that local authorities did not include bids for
additional schemes in the Annual Progress Report, submitted in July
2002, there is reason to hope that the transport element of the SCP
to be announced in December 2002 will be higher than the indicative
allocation of £15.921m that has been assumed to date. There will also
be a discretionary element of the SCP but none of this has been assumed
to be available to support the transport capital programme.
- In considering
the proposals for a revised provisional SCP allocation, the Executive
should note that the transport capital programme is also supported by
5 other sources of funding:
- Developer Contributions
- Surpluses from
the On-Street Parking (OSPS) Account
- Contributions
from other authorities
- £1.5m repayment
from the revenue budget due in 2004/05 and in 2005/06
- Ringfenced special
grant for the Home Zones challenge scheme in Saxton Road Abingdon.
(£350k).
Developer
Funding
- The total amount
of developer contributions held by the County Council for transport
schemes at the start of the financial year was just over £23m with a
further £13m that has been secured by legal agreements but not yet received.
Approximately £11m of these contributions is committed to the ITS programmes
and the major road schemes in Banbury, Bicester and Didcot.
- The remaining
£12m of the developer funding available is planned to be used to fund
the Cogges Link improvement in Witney and provide further support to
the ITS programmes. The actual amount of developer contributions that
will be available in 2003/04 and later years is dependent on the terms
of the agreements, the schemes selected for implementation and the pace
of development. The City Council also hold approximately £3.8m of development
contributions which it is anticipated will be allocated to support the
future OTS programme.
On-Street
Parking Surplus
- The surplus on
the OSPS account at 1 April 2002 was approximately £3.3m. Approximately
£2.7m is committed to the Water Eaton and Thornhill P&R sites, with
the remainder being used to refinance some of the Sustainable Transport
projects carried forward from 2001/02 that were not funded from the
SCP last year. The surplus on the OSPS account (approximately £1m per
annum) is available to support elements of the transport programme,
subject to meeting the conditions that relate to Section 55 funding.
It is anticipated that the management costs of the new P&R sites
and further P&R enhancement schemes will be funded from this source.
Progress
on the 2002/03 Programme
- A key factor in
trying to assess the forecast out-turn for the 2002/03 programme is
the feasibility of incurring the expenditure within the financial year.
The SCP is only valid for one year and payments have actually got to
be made if the expenditure is to count against the SCP allocation. This
means that work has to be completed by about mid February if the invoices
are to be passed and payments made within the financial year.
- The detailed summary
of progress on the schemes being progressed as part of the 2002/03 programme
is set out in a document (Update on the 2002/03 Transport Capital Programme)
which has been placed in the Members’ Resource Centre. Contact names
are included so that members can seek any additional information on
individual schemes. The forecast out-turn figures have been assessed,
based on the best estimates currently available from client managers,
Babtie and Isis Accord. These indicate that there is a forecast underspend
on this year’s SCP of £1.8m. The £1.8m will be required to complete
works on the 2002/03 programme that will not be charged to the 2002/03
SCP. If action is not taken there is a risk that this part of the SCP
would no longer be available to the County Council.
- There are various
courses of action available to the County Council to resolve this problem.
The advantage of carrying out an October review of the current year’s
programme is that there is still time to reallocate funding into the
structural maintenance budget where less preparation work is required
and additional expenditure can more easily be incurred. It is therefore
proposed that a sum of £750,000 is transferred into the 2002/03 capital
maintenance budget and next year’s structural maintenance budget reduced
by a similar amount to fund the expenditure on the current year’s integrated
transport programmes that has to be carried forward to next year. This
is in line with the Executive’s previous policy of seeking to bring
forward essential maintenance work to improve the road network. A scheme
on the A4130 in Didcot has already been identified from next year’s
programme that can be brought forward with the advantage that it can
be carried out at the same time as a developer funded cycleway scheme.
- In some jointly
funded schemes it would be possible to incur more SCP expenditure this
year than planned and defer expenditure of either developer contributions
or OSPS funds until 2003/04. This has the advantage that a decision
does not have to be made until nearer the year end when the likely outturn
position is clearer. Hennef Way is currently under construction and
it is planned to spend £1m of SCP and £1.927m of developer contributions
during 2002/03. At this stage it would be possible to increase the SCP
allocation by £1.05m to £2.05m with a consequent reduction in next year’s
SCP requirement from £1.668 to £618k. The £1.05m would then be available
to fund those integrated transport schemes that require carry-forward
funding. Depending on the final outturn figures it would be possible
to adjust this figure to ensure that there is no underspend of the transport
SCP allocation this year.
Other
factors affecting the 2003/04 to 2005/06 Transport Capital Programme
- The provisional
programme for 2003/04 to 2005/06 shown in Annex
1 includes a sum of £3.9m for
Marcham Bypass. Due to inflation, design changes and increased estimates
of land costs and compensation, the cost of this scheme is now over
the £5m threshold set by the Government for Major Schemes. This means
that Marcham Bypass will have to be subject to a bid to the Government
for specific funding. It is considered that a good case can be made
for Marcham Bypass but progress will be dependent on a bid being successful.
On the positive side it does mean that Marcham Bypass cannot now be
funded from the SCP allocation and therefore £3.9m will be available
to be allocated to other projects.
- Projects that
may require additional funding are elements of the Carterton, Witney
to Oxford Transport Links Strategy that is the subject of a later report
on the agenda of this meeting. This report recommends that phase 1 of
this strategy is not progressed as a major scheme bid in order that
more rapid progress can be made on improvements to Wolvercote Roundabout
and a new link road joining the A40 to the A44/A34. Some funding will
be required in the 3 years from 2003/04 to 2005/06 but it will be included
in the provisional allocations for major schemes (for County purposes
these are defined as over £0.5m), integrated transport strategies (e.g.
for Wolvercote Roundabout as part of the OTS programme) and Sustainable
Transport.
- A study is currently
being carried out on the A40 Green Road Roundabout. If low to medium
cost solutions are recommended then these will need to be included in
a future OTS programme. Due to the need for extensive consultation and
complex design issues, it is unlikely that significant expenditure could
take place during 2003/04. Any major scheme proposals are likely to
take some years to develop and probably could not be programmed until
2005/06 at the earliest. The capital programme will need to be reviewed
if a major scheme is to proceed prior to the next LTP submission. Smaller
scale improvements could be included in the 2004/05 programme.
- The recent Executive
decision to fund the 2003/04 preparation work on GTE out of the SCP
will require an additional £800k to be allocated to the major schemes
budget heading.
- The contractual
difficulties with the Cornmarket Scheme in Oxford have exposed the County
Council to a financial risk in the order of £600k. Action has already
been taken to offset this risk by charging all of the 2000/01 and 2001/02
expenditure, including the cost of the abortive work, to previous Supplementary
Credit Approvals. Every effort will be made to secure reimbursement
of abortive costs by way of the contracts’ dispute procedures. The cost
of future work in Cornmarket will be largely covered by the City Council’s
contribution. Any funding recovered by the County Council through the
disputes procedures will be available to support future capital programmes.
It is not possible at this time to predict when this money might become
available but £600k has been notionally included in the 2005/06 budget
as being the most pessimistic date.
- The current programme
for Cogges Link, Witney means that it is unlikely that the programmed
£1m contribution will be required until 2004/05, as it will be essential
to spend developer contributions first to meet the requirements of Section
106 Agreements.
- The budget for
the extension of the Thornhill P&R site includes a developer contribution
of £135k from the City Council. One of the key objectives of the Thornhill
extension was to provide additional parking for staff and visitors accessing
the Churchill and Nuffield hospitals. Tenders have been invited for
bus services to link Thornhill to the hospital sites. Unfortunately
there are not sufficient developer contributions currently available
to fund this service but, subject to the agreement of the City Council,
it would be possible to use £135k of the forecast underspend to fund
the Thornhill P&R extension and so release this developer contribution
to support the bus service.
- If this course
of action is acceptable to both Councils it will mean that there would
be a shortfall in the carry forward funding required to complete this
year’s integrated transport programmes. This can either be funded from
next year’s SCP or potentially from the OSPS which, subject to the conditions
relating to Section 55 funds being met, could be used to support the
OTS programme next year. It is suggested that a final decision on how
this shortfall should be funded be deferred until the level of the overall
SCP allocation is known.
Revised
Provisional Programmes proposed for 2003/04 to 2005/06
- The key criteria
used to develop the revised provisional programme are:
- The structural
maintenance budget (including repayments from revenue) should be increased
over the remaining 3 years of the 5 year programme from a total of
£13.604m included in the existing provisional allocation, to £22m.
This requires general reductions in other budget areas but these will
be offset to some extent by additional OSPS and developer contributions
that become available.
- The revenue
contributions of £1.5m in 2004/05 and 2005/06 will be allocated to
the structural maintenance heading, reducing the required capital
allocation in these years to £6.0m.
- The casualty
reduction budget increases over the three years in view of the national
and local targets for casualty reduction.
- The Community
Safety budget for 2003/04 takes into account the results of the Scheme
Assessments completed to date and the potential need to jointly fund
the M40 J6 Lewknor Improvement scheme. Increases are proposed in future
years to reflect the growing demand for safety schemes.
- The Sustainable
Transport budget is the most difficult to predict with any accuracy.
There are growing demands on the BWTS programme as more schools make
strong applications and cycling schemes are generally becoming more
expensive as schemes develop following public consultations. The County
Council’s aspirations for GTE, rail improvements, Premium Routes and
Real Time Passenger Information would impose severe demands on the
next 3 years’ capital programme if they were all to be realised. In
practice it is unlikely that they will all be deliverable within the
next 3 years and many will form part of the next Local transport Plan
bid in 2005. The £8m SCP proposed for 2003/4 to 2005/06 will have
to be supported by developer contributions and OSPS if this challenging
public transport programme is to be delivered.
- The proposed revised
provisional programmes are set out in Annex
2. These provisional programmes have been
developed taking into account the Draft Budget Strategy considered at
the last Executive and the need to meet the targets set out in the LTP
and the PSA. It is emphasised that these are for forward planning purposes
only and it will need to be reviewed early next year in the light of
the actual SCP allocation and the Council’s decision on the whole capital
programme. Cost estimates and programmed dates are also subject to change
as feasibility and design work is progressed.
Financial
and Staff Implications
- The financial
implications are as set out in the report. Assessment, promotion and
design of schemes in the programme will be undertaken by a combination
of existing staff, Halcrow, the County Council’s term consultant for
transport planning, and Babtie, the County Council’s term consultant
for engineering design. The growing transport capital programme increases
the demands on client and project management and on the resources required
for transport planning and engineering design consultancy support. This
can be partly funded form the capital programme but only at the expense
of the overall size of the programme.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:-
- approve
the revised provisional transport SCP allocation for 2003/04
to 2005/06, as set out in Annex
2, for forward planning purposes;
- authorise
the Director of Environmental Services, in consultation with
the Director of Business Support to increase the 2002/03 SCP
allocation for Hennef Way, with a corresponding reduction in
the 2003/04 SCP allocation to Hennef Way, to ensure that the
£18.613m SCP allocation for 2002/03 is fully utilised;
- approve
the transfer of a total of £750,000 from the forecast underspend
on the 2002/03 Sustainable Transport, Community Safety (Transport)
and Casualty Reduction budgets to the Structural Maintenance
budget and make an equivalent reduction in the proposed provisional
Structural Maintenance allocation set out in Annex 2 for 2003/04,
to enable the 2002/03 schemes carried forward to 2003/04 for
implementation to be funded; and
- approve
the use of an additional £135k of SCP underspend in 2002/03
for the funding of the Thornhill Park and Ride Extension to
release the allocated developer contribution of £135k, subject
to the agreement of the City Council, to support proposed contracted
bus services from Thornhill Park and Ride to the Churchill and
Nuffield Hospitals.
DAVID
YOUNG
Director of Environmental Services
CHRIS GRAY
Director of Business
Support
Background
papers: Nil
Contact
Officer: Eddie Luck - Tel: 01865 815845
October
2002
Return to TOP
|