|
Return
to Agenda
ITEM EX24
EXECUTIVE
– 19 MARCH 2002
COTSWOLD
LINE RAIL STUDY
Report
by Director of Environmental Services
Introduction
- The County Council
is a member of the Cotswold and Malverns Transport Partnership which
was formed five years ago with the aim of developing the Cotswold railway
line between Oxford, Worcester and Hereford. In Oxfordshire all Cotswold
Line trains serve Oxford, Charlbury and Kingham; most serve Hanborough,
but only a very limited service is provided for the halts at Combe,
Finstock, Ascott-under-Wychwood and Shipton.
- In 1999 the Partnership
commissioned the Oscar Faber consultancy to look at how the Cotswold
Line should be developed. A report detailing the outcome of this study
was submitted to the former Public Transport Sub-Committee in November
1999.
- A further report
commissioned from Halcrow Fox identified a £50 million ‘first stage’
development. However the Strategic Rail Authority (SRA) in discussion
with the Partnership indicated that this still fell outside the criteria
for Rail Passenger Partnership (RPP) funding.
Potential Progress towards
Enhancement of the Network
- The Partnership
has continued to meet in order to try to identify a series of smaller
RPP bids which would give the biggest benefits (maximum capacity achieved
for minimum infrastructure enhancement). These were shown to be the
doubling of track from Norton Junction (near Worcester) to Pershore
plus additional signalling between Malvern Link and Great Malvern. Although
the location of these improvements lies totally outside Oxfordshire,
they would provide significant benefits to Oxfordshire residents with
a more robust and frequent timetable (hourly off-peak). The aim of this
project would be to show a return on capital expenditure both in terms
of increasing capacity on the line and improving reliability.
- Officers of the
Partnership have held two recent meetings with the SRA at which it gave
a positive reception to this latest idea. It has also indicated that
funding is now available from the new Rail Performance Fund (RPF), which
has funding of £40 million per annum over a ten-year period, but that,
in order to stand the best chance of success with a bid, an application
should be received for 2002/03 determination. This would need to be
submitted by the Partnership by July 2002. In subsequent years, there
is likely to be much more competition for funding, hence the urgency
for this submission.
- The information
provided by the consultants provides a useful starting base but suffers
from being already somewhat out-of-date. In order to formulate a submission
to the standard required by the SRA, further development cost work needs
to be undertaken in terms of level of detail and financial information,
with a full review of construction costs. This detailed work is likely
to require an expenditure of £250,000-£400,000, of which an overall
share of £130,000 is being proposed to be funded by the relevant local
authorities, the major contribution to which will need to come from
the County Councils. The remaining funding would come from the SRA.
It has been emphasised that the SRA would not contemplate giving 100%
funding and that it would want to see a meaningful financial commitment
from local authorities before it would support the project. In order
to achieve the recommended submission date of July of this year, a degree
of urgency for this work is required.
- The Local Transport
Plan (LTP) spells out (page 81) that the Council supports the
further development of the Cotswold Line and will continue to work through
the Partnership with the aim of improving the services offered by the
line.
Financial Implications
- Should the Partnership’s
bid to the RSA be successful, the track enhancement and signalling work
is likely to be carried out in the 2005/06 financial year, and this
will involve a major call on the Council’s capital funding. The amount
of the capital contribution which this Council will be called on to
contribute towards the overall project which could cost between £15-£50m
(depending on the nature of the project which is finally agreed) cannot
at this stage be quantified.
- Normally this
matter would be dealt with as part of the Capital Programme Review which
the Executive will be considering in April. The urgency to complete
the submission to the SRA by July 2002 means however that we need to
be able to confirm to the Partnership our contribution to the development
costs by 31 March 2002. For this reason, a decision on this cannot wait
until the main review in April but needs to be taken forthwith. Oxfordshire
County Council’s share of the £130,000 has not been clarified at the
time of writing but will not exceed £30,000, and this can be met from
the existing provision for consultants’ fees. Nevertheless the Council,
in agreeing to pay its contribution towards the development costs of
this capital project, will be raising the expectation of entering into
a long-term commitment to co-funding the project itself, as set out
in paragraph 8 above, in advance of any other decisions on the capital
programme. The size of this contribution and its timing would need to
be the subject of a future report to the Executive. As is the case with
the development cost funding, the SRA, if it accepts the Partnership
submission, will expect the members of the Partnership to fund a meaningful
financial contribution towards the costs of the project.
Staff Implications
- Work on the development
costs and the submission to the SRA will be carried out by consultants
on behalf of the Partnership. Staff already attend meetings of the Partnership
and in future the County Council’s day-to-day work on the Cotswold Line
will be undertaken by its new Rail Development Officer who commences
employment in April.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- agree
to fund a contribution of up to £30,000 to the Cotswold and
Malverns Transport Partnership in the 2002-03 financial year
for development costs in preparing a submission to the Strategic
Rail Authority for the upgrading of the Cotswold Line; and
- note
the expectation of a significant Capital contribution by the
County Council towards the future upgrading of the Cotswold
Line, should the submission by the Cotswold and Malverns Partnership
to the Strategic Rail Authority be successful, subject to further
detailed report on the likely costs and financing implications
in the context of the benefits to Oxfordshire.
DAVID
YOUNG
Director of
Environmental Services
Background
papers: Partnership meeting notes and correspondence on
Environmental Services files PT 9412 and 9412/1.
Contact
Officer: Alan Pope Tel: Oxford 815585
March
2002
Return to TOP
|