|
Return
to Agenda
ITEM EX22
EXECUTIVE
– 19 MARCH 2002
A422 BANBURY,
HENNEF WAY DUALLING
Report
by Director of Environmental Services
Introduction
- This report seeks
the approval of the Executive to enter into a Works Agreement with Railtrack
relating to the new bridge required for the construction of Hennef Way
Dualling. The Works Agreement exposes the County Council to future liabilities
relating to upgrading of the railway line, but Railtrack insists on
a Works Agreement before it will agree to sell the land it owns that
is needed for the construction of the road. Agreement has been reached
on the acquisition of all the remaining land and this is the final step
required before the contract can be awarded.
Background
- The full dualling
of Hennef Way from M40 to A423 Southam Road has been an approved Major
Capital Programme Scheme since the mid 90’s. In June 2001 the former
Environmental Committee approved a Project Appraisal No H159/1. This
gave spending approvals of £5.776M at May 2001 prices. The scheme is
included in the 2001/02 capital programme. Every effort has been made
to achieve the earliest possible start date and tenders were invited
in November 2001. Tenders have now been received and the lowest price
bid can be funded from the allocated budget.
Railtrack Negotiations
- All land required
for the scheme has been secured with the exception of land in the ownership
of Railtrack plc, which is necessary for the new railway bridge construction.
Railtrack have tied the release of this land to the signing of a "works
agreement"
- In order to carry
out works on or over a railway, Railtrack require Outside Parties to
enter into a works agreement. Railtrack maintain that their document
is a nationally agreed one and we have some evidence to substantiate
this.
- The most financially
onerous clauses in the Agreement are reproduced in Annex
1 . This gives
Railtrack the right to require the Council to alter the bridge at any
time in the future at the Council’s cost to suit Railtrack’s development
of the railway line.
- Railtrack are
not prepared to negotiate on the clause and the original 1983 Agreement,
relating to the present bridge on Hennef Way, also reproduced in Annex
1 includes effectively the same liability. In order to mitigate this
liability, officers have sought Railtrack’s agreement to the provision
of a clause requiring Railtrack to give reasonable notice to the Council
to enable the Council to make a bid for Government funding through the
Local Transport Plan. The outcome of this initiative will be reported
orally at the meeting.
Director’s Comments
- The need for "works
agreements" with Railtrack is common practice and it is understandable
that Railtrack seeks to protect its future interests in the event that
a major upgrading of the line is proposed. The County Council would
seek similar agreements if a new railway were being proposed, crossing
a road that may need to be improved.
- In practice it
would be several years before any major rail upgrading could come forward
and there would be the opportunity of bidding for additional Local Transport
Plan funding to cover the cost of any future liabilities. I would expect
the Department of Transport, Local Government & the Regions to be
sympathetic to this type of case, especially if flagged well in advance.
It is common practice for the Strategic Rail Authority to publish their
programme of line upgrades well in advance.
- There is no real
alternative to accepting Railtrack’s requirements if the dualling of
Hennef way is to go ahead and I recommend that the County Council enter
into a "works agreement" that includes the clauses 24.1, 24.2
and 24.3 as set out in Annex 1. The Strategic Rail Authority recently
published plans for a gauge upgrade from Southampton to Birmingham by
2005. There are four structures which are affected by this upgrade.
Current indications are that the bridge at Hennef Way is not one of
them. We are seeking confirmation of this and the latest position will
be reported orally at the meeting.
Financial and Staff Implications
- Using the lowest
tender bid and the other costs, which are now known, a check has been
made against the Project Appraisal budget figure and the projected scheme
cost can be met from the scheme budget. No further spending authority
is therefore required at this time. However the potential liability,
if Railtrack invokes clauses 24.1,2&3 of the "works agreement"
remains unpredictable.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to authorise the completion of a "Works Agreement"
with Railtrack plc that includes clauses 24.1, 24.2 and 24.3 as set
out in Annex 1, subsequent to written confirmation that the Hennef Way
bridge is not affected by the upgrading proposals by Strategic Rail
Authority.
DAVID
YOUNG
Director of
Environmental Services
Background
papers: Nil
Contact
Officer: Colin Baird Tel: Oxford 815536
March
2002
Return to TOP
|