ITEM EX7
EXECUTIVE -
5MARCH 2002
DETAILED PROJECT
APPRAISAL NO. ED582
NAME OF SCHEME: Harwell
Primary School – Early Years Unit
Start Year: 2002/03
BASIS OF ESTIMATE: WS
Atkins estimate based on current sketch scheme
- DESCRIPTION
OF PROJECT
Members
will be aware of the proposal to close Harwell Nursery School with provision
in the area transferring to Harwell and Chilton Primary Schools. The
scheme at Harwell allows for new reception, cloakroom, office, resource
area and Early Years’ unit and storeroom and a new Key Stage 1 storeroom.
The Early Years’ unit will also include new external store, entrance
and cloak area with the Head’s office being converted to a disabled
WC. There will be the inclusion of external canopies, 120 sq metres
of new garden area with associated fencing and gates and new hard play
of 360 sq metres. A number of existing doors and windows are also to
be replaced.
- JUSTIFICATION
AND ASSESSMENT OF NEED
An assessment has been done
of the need for Early Years’ provision in the area given the closure
of Harwell Nursery and revenue funding has been provided through Early
Years to fund this project so that appropriate provision is in place
when the nursery school closes.
- OTHER OPTIONS
There are no other options
given that the closure of Harwell Nursery School and the above strategy
was agreed by the former Education Committee.
- FINANCIAL IMPLICATIONS
- Capital
The estimated total cost
of the scheme, inclusive of fees, is £238,000.
£186,416 will be found
from Early Years’ Revenue Funding as identified within the Minor
Works section of the Capital Programme. In addition a contribution
of £26,908 will be provided by the school and the balance of £24,676
will be met from the NDS Condition budget (£20k 02/03; £5k 03/04)
for the replacement of windows and doors.
- Revenue
Revenue costs will be
found from the school’s Fair Funding formula.
- ENVIRONMENTAL IMPLICATIONS
These will be met in accordance
with the planning permission for the site. It is intended that the
design within the existing building will lead to cost savings through
better environmental construction.
Resource Appraisal (download as .rtf
file)
ROY SMITH
Acting Chief Education Officer
CHRIS GRAY
Director of Business Support & County
Treasurer
DAVID YOUNG
Director of Environmental Services
Contact Officer: Michael
Mill, Senior Education Officer Tel (01865) 428161
February 2002