|
Return
to Agenda
ITEM EX14
EXECUTIVE
– 6 FEBRUARY 2002
CARTERTON
AND WITNEY TO OXFORD PUBLIC TRANSPORT LINKS
Report by
Director of Environmental Services
Introduction
- The main purpose
of this report is to provide the Executive with details of a recent
study looking at the feasibility of reinstating a passenger rail line
from West Oxfordshire to Oxford. It also takes the opportunity to update
the Executive on the latest situation with the A40 bus lane project,
including details of the Government's response to the County Council's
bid for funding.
Background to the Rail
Study
- In July 2001,
the County Council and West Oxfordshire District Council jointly commissioned
independent consultants to undertake an outline study looking into the
feasibility of reopening the disused railway line between Brize Norton
and Yarnton. The study followed an earlier resolution of the Public
Transport Sub Committee, at the end of 2000, and was conducted by Mott
MacDonald, a firm with a background in rail and public transport work.
- The purpose of
the study was to identify any significant physical constraints along
the route and the capital costs and environmental implications associated
with restoration of heavy rail and light rail options. Subsequently
it was agreed that options involving the extension of the County Council's
Oxford GTE (guided bus) scheme should also be included. It should be
noted that this study was very much the first stage in the process in
that it was limited to outline feasibility. This meant that the potential
options were not developed in any detail and that the study did not
investigate the more detailed cost and benefit issues. A copy of the
consultants' report has been placed in the Members' Resource Centre.
The consultants have also offered to present the conclusions of their
study to a joint meeting of County and District Members. The District
Council has offered to host the presentation at its offices in Witney.
Route Constraints
- The railway line
originally ran from the Cotswold Line junction at Yarnton, past Cassington,
Eynsham and South Leigh to Witney and from there along the south side
of the Brize Norton air base and on to Fairford in Gloucestershire.
The consultants have undertaken a review of the Yarnton to Brize Norton
route and have found several sections where the old alignment is now
no longer available. The main obstacles to reinstatement of the old
line are described in Annex 1. There are a number of sections of the
route where property development or road construction over the last
thirty years means that a modified alignment would be needed. The most
significant problems, particularly for a heavy rail route, are to be
found in the area between Witney and Ducklington (see
Annex 1).
Identification of Options
- The consultants
have identified three broad options and a number of sub options which
are described in detail in their report. A brief description of the
options and their possible route alignments is provided in
Annex 2. The routes are also shown on the attached
plan. The feasibility of a heavy rail route has been assessed and the
consultants have concluded that reinstatement, predominantly along the
line of the old route, would not be viable. The reason for this is the
problem of getting a heavy rail route across the A40 Witney bypass (which
did not exist when the old railway line was still running) and in to
Witney where an industrial estate is now built on the site of the old
station. Similarly, there are huge engineering challenges and environmental
costs associated with realigning the heavy rail route via a parkway
station on the south side of the A40 Witney bypass near Ducklington
(see Annex 2). These involve taking the line across a lake and the probable
demolition of an hotel.
Light Rail/Tram Or Guided
Bus?
- The difficulties
in taking a traditional heavy rail route into or close to Witney, have
led the consultants to look at a number of alternative light rail/guided
bus options which have the flexibility of on-street running. In addition,
engineering design specifications for light rail/guided bus are less
onerous (and implementation less costly) than heavy rail. In developing
these options, the consultants have advised that if a new link to West
Oxfordshire is to be progressed, it should be compatible with whatever
system is developed to run the proposed Oxford GTE services between
the Peartree and Redbridge park and ride sites. Clearly, it would not
make sense to develop two separate systems that required passengers
to interchange between each. There are also cost savings in combining
the proposed Oxford system with a route out to West Oxfordshire.
- The consultants
have pointed to the pros and cons of the light rail and guided bus approaches.
They argue that light rail vehicles have high capacity and in image
terms are less like a bus, meaning that it may be easier to persuade
motorists to switch mode. The consultants also point to the opportunities
(subject to HMRI approval) for light rail vehicles to share heavy rail
track on the approaches into Oxford. This could overcome some of the
problems that are likely to arise with the Oxford GTE project which
requires the construction of a separate guideway for buses alongside
the rail lines.
- The benefits of
the guided bus approach are that it offers much greater flexibility
in that the vehicles can leave the guideways and operate on street as
conventional buses. The establishment of a guided bus network is less
costly than the light rail equivalent. The vehicles may also be considerably
cheaper, depending on whether they are simple conversions of conventional
buses or very high specification vehicles.
Cost of Options
- The consultants
have produced broad estimates of the costs of implementing the range
of options identified in their report (and summarised in Annex 2). The
heavy rail option is estimated to cost £107m. The GTE (guided bus) option
is estimated to cost around £45m for the infrastructure required between
Witney and Oxford. An additional £6m is estimated for the necessary
high specification rolling stock (less if the vehicles used are conventional
buses with minor modifications). A further £23m is required for the
proposed Oxford GTE link from Peartree to Redbridge (which until now
has been progressed as a stand-alone project).
- The Light Rail
option is estimated to cost around £54m for the Witney to Oxford infrastructure
with a further £12m for the rolling stock. The costs of a light rail
system for Oxford (as an alternative to the proposed Oxford GTE system),
are estimated to be £13m. This element is cheaper than the GTE equivalent
because it relies upon light rail vehicles being able to use heavy rail
track rather than the construction of guideways (although GTE has other
advantages and there are doubts about the practicality of track sharing
– see below).
- In total, therefore,
the GTE option (£74m combined cost including Oxford system) is marginally
cheaper than the light rail option (£79m). Both options are cheaper
than the most basic heavy rail option (avoiding Witney), however, the
task of raising the necessary funding for either of the preferred options
will clearly be considerable.
Officer Comments
- It seems clear,
even within the limited scope of an outline feasibility study, that
there are very significant obstacles to the reintroduction of a heavy
rail line, particularly along the section between Witney and Ducklington.
On this basis, officers support the consultants’ conclusion that a heavy
rail link would not be viable. The conclusion that light rail and guided
bus options are worthy of more detailed study is also supported. Officers
feel that the consultants may have underplayed the difficulties of trying
to introduce on-street running of light rail vehicles within Witney.
There would inevitably be implications for general traffic and the practicality
of achieving this would need to be explored in much greater detail.
Similarly, the joint use of light rail and heavy rail rolling stock
on the same track (as the consultants have suggested for the Oxford
end of the route) is an approach where the safety and capacity implications
would need to be fully resolved. Both the guided bus and light rail
options have implications for heavy rail capacity on the main line through
Oxford which will need to be considered alongside the aspirations of
the TOCs (Train Operating Companies).
- The pros and cons
of light rail, as opposed to GTE (Guided Bus) have been considered in
the past in the early stages of the development of the Oxford GTE proposal.
The image/capacity benefits of light rail compared with the flexibility
of guided bus are issues that will need to be further considered within
the context of more detailed study of West Oxfordshire to Oxford travel
demands. It makes sense for any link to West Oxfordshire to be compatible
with the system chosen for Oxford. One important point to bear in mind
is that the consultants have been cautious about whether the population
of West Oxfordshire and the related passenger demand, will be great
enough to meet the costs of either a light rail or guided bus system.
Further study will show whether the additional demand arising from the
expected 25% growth in population of Witney and Carterton over the next
decade, will be sufficient to make the economic case for a new link.
Procedures/Implementation
Timescale
- It should be emphasised
that the procedures that need to be followed for this type of scheme
mean that it will take a minimum of seven years, and typically at least
a decade, before the facility is in place. The main stages in the process
are set out in the consultants’ report. A crucial part of the process
will be the need to secure significant Government grant through a major
public transport scheme LTP bid. Government grant will only be forthcoming
if it can be clearly demonstrated that the benefits, in terms of annual
passenger revenues, reduced journey times and modal transfer, are sufficient
to off-set the considerable costs. The consultants have pointed out
that their outline feasibility study was not sufficiently detailed to
be able to take a view on whether the potential patronage levels and
other benefits are likely to be large enough for either the light rail
or guided bus options to pass the economic tests.
Update on the Proposed
A40 Bus Lane
- A bid for a grant
towards the cost of implementing the proposed £9.6m bus lane scheme
was submitted to Government last July. The Government’s response to
the bid was set out in the Local Transport Settlement, received in December.
The Government did not approve funding for the bus lane scheme but requested
that the bid should be re-submitted again this July. This was the same
response as that received a year ago. The basis for the Government’s
reluctance to approve the scheme appears to be lack of confidence in
the appraisal material produced to support the bid. In particular, there
is concern about the patronage projections that have been produced to
underpin the economic case for the scheme. Even though our consultants,
Babtie, argue that these projections are conservative, the Government’s
economists would prefer to see evidence from similar schemes elsewhere
to substantiate the forecasts. The problem for the scheme is that it
would be the first of its kind so no such supporting information is
available. A meeting with GOSE officials is to be held early in the
New Year to discuss the additional appraisal information required for
a submission in July this year.
- This delay to
progress on the bus lane scheme provides the opportunity to step back
and review options for the A40 corridor, particularly in light of the
rail study conclusions. The patronage base that would be required for
the bus lane scheme would also be needed to support a segregated guided
bus or light rail scheme from West Oxfordshire. In this sense the schemes
would be in competition for funding. The advantage of the bus lane scheme
is the fact that it could be implemented more quickly and at far less
cost. A segregated guided bus or light rail scheme would offer the significant
advantage of providing a comprehensive traffic-free route for both the
outward and return journey. However, the implementation timescale for
a guided bus or light rail option would be considerable and there is
a risk that the economic case for either will not be strong enough to
secure the necessary funding.
Next Steps
- One way forward,
bearing in mind the different implementation timescales for the bus
lane scheme and the guided bus/light rail scheme, might be to modify
the bus lane scheme so that it can link into a segregated guided bus
or light rail route at a later stage. The section of the A40 over which
an on-line bus lane or guideway can be provided before going off-line,
to utilise sections of the old railway line, will need to be assessed.
This work could form part of a wider review of options for the A40 corridor.
- It is proposed
that the review should also include looking at the possibility of a
new highway link, from the A40 to the A34, as part of the package of
measures. This scheme is identified in the County Council’s Structure
Plan and could provide motorists heading for the A44, A34, M40 and beyond
with a link that avoids the congested A40 Wolvercote Roundabout. The
costs and benefits of this scheme as part of a wider package would need
to be fully assessed.
- It is suggested
that officers should undertake this broad review of the options for
improving transport links and report back to the Executive later in
the year. Following the review, the Executive will need to decide whether
a bid for the existing or modified A40 bus lane scheme should be submitted
this summer and whether consultants should be commissioned to develop
more detailed alternative or compatible proposals for the A40 corridor.
The consultants could be required to undertake their work on further
proposals in time for the results to be incorporated in the July 2003
Annual Progress Report.
Financial and Staff
Implications
- This report has
identified the significant costs involved in developing a guided bus
or light rail link from West Oxfordshire. A very robust case would be
needed to secure the necessary Government grant. The task of raising
the required funding is made more difficult by the fact that developer
contributions associated with the substantial housing growth in Carterton
and Witney over the next decade are largely already committed.
- The costs of undertaking
a more detailed study to support a bid to Government are significant.
It may be that the most cost-effective way of commissioning the work
would be through the Council’s transport planning term consultants who
are shortly to be appointed to conduct the Transport Networks Review.
The A40 corridor review could be made their first priority. Additional
work on the appraisal material needed to support a revised package of
measures would, however, require additional consultancy fees during
2002/03 if a modified submission is to be made in July 2003.
- More detailed
work on the light rail and guided bus schemes (and an A40/A34 link road)
involving more precise identification of the alignment for these routes
could have blight implications. This could potentially result in claims
under the Land Compensation Act.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- endorse
the findings of the consultants’ report that the reinstatement
of a heavy rail link along the disused rail line between Brize
Norton and Yarnton would not be viable but that options involving
either a GTE (Guided Bus) or Light Rail system are worthy of
more detailed study;
- welcome
the consultants’ offer of a joint presentation of the study
findings to interested County and District Members at the District
Council offices in Witney and ask officers to make the arrangements;
- ask
officers, in light of the Government’s response to the bid for
the proposed A40 bus lane, to undertake a broad review of the
short and longer term options for improving transport links
between West Oxfordshire and Oxford, including the possible
incorporation of the guided bus or light rail proposals identified
by the consultants and to report back with preliminary recommendations
within four months; and
- continue
with preparation of the A40 bus lane scheme to provide the opportunity
of a resubmission to the DTLR in July 2002 for the current or
modified scheme, dependent on the outcome of the further review.
DAVID YOUNG
Director of
Environmental Services
Background Papers:
Mott MacDonald report
Contact Officers:
Mark Jarman telephone: 01865 815094
January 2002
Return
to TOP s |