|
Return
to Agenda
ITEM EX20
EXECUTIVE
– 22 JANUARY 2002
PROPERTY
CONSULTANCY SERVICES
Report by
Director of Environmental Services
- At their meeting
on 11 October 2001 the Operations Sub-Committee received a report titled
Property Consultancy Services - Review of WSA's Service 2000/01 and
Future Provision of Services (OPS 16). Members of the Executive are
recommended to read the full report but a summary follows.
Summary of
the Report to Operations Sub-Committee
- The Report gave
details of the annual review of services provided by WS Atkins (WSA)
in 2000/01. There were concerns about some areas of the service but
it was acknowledged that WSA had responded well to the very large workload
arising from the re-organisation of City schools and overall the service
provided was satisfactory.
- The current contract
with WSA will come to an end in March 2003 although the County Council
has the right to extend the contract for a further period. It was recommended
that there should be a Best Value Review for Property Services before
a new contract for any significant period is let. The review should
reassess the services which are likely to be needed in the future, and
how they should be packaged and procured. This should include examination
of the work done by County Council client staff as well as by the consultants.
It would not be possible to undertake a Best Value Review and allow
sufficient time for the work which would then be required to arrange
for a new contract or contracts to be let by the date at termination
of the current contract - 31 March 2003. To allow adequate time it was
recommended that the current contract with WSA be extended until the
end of March 2005. This would also enable all of the works on the City
Schools Reorganisation to be completed before the re-letting and avoid
the significant extra workload involved in re-tendering during those
works.
- Members of the
Operations Sub-Committee expressed dissatisfaction with the current
level of service and resolved to:
- recommend the
Executive in consultation with Scrutiny to set up an urgent assessment
of the services provided by WSA;
- extend the current
contract with WSA until 31 March 2004.
Review of
Services
- The Annual Review
goes into considerable detail in assessing the service using monitoring
information. Copies of the detailed reports which made up the review
undertaken in 2001 have been placed in the Members' Resouce Centre.
My strong advice would be that rather than concentrate on an assessment
of the services provided by WSA, a thorough review should be undertaken
to re-examine the property consultancy services required by the County
Council and how they should be provided. There should be consideration
of the client role, the split of functions between Environmental Services
and service departments and the services required to be provided externally
and how they should be packaged and procured.
- It will also be
necessary to consider the consultancy services which will be required
under the partnering contracts arising from the Government’s "Rethinking
Construction" initiative (this will be a recommendation of the
Best Value Review for Construction). This goes well beyond assessing
the service provided by WSA and, in my view would be most appropriately
addressed by a Best Value Review. Almost certainly the review would
involve independent expert advice.
Extension
of the Current Contract
- If a thorough
review of the property services required by the County Council is to
be undertaken then my advice would be that a period of twelve months
should be allowed for the review to be undertaken and for any recommendations
and action plan to be agreed with members. The process from that point
for entering into new contracts would take eighteen months allowing
for a six-month lead-in period for any new contractor following appointment.
The earliest that a new contract could commence would therefore be the
beginning of July 2004. Extension of the current contract with WSA until
March 2004, as agreed by the Operations Sub-Committee, therefore gives
a timetable which would be extremely difficult to achieve from the outset
and would not allow for any slippage or unforeseen delays.
- Extension until
March 2005 would allow adequate time with an allowance for any delays
in a Best Value Review and in the processes for preparing new contract
documentation, consultation, advertising, selection of contractors,
completion of legal documentation and lead-in period. My strong advice
is to allow adequate time and not to start with what is probably an
unachievable timescale for reviewing a service and letting a contract
or contracts which will involve very substantial expenditure for the
County Council and have a significant impact on all services as well
as potentially causing disruption to the City Schools Reorganisation.
Conclusion
- I remain of the
view therefore that, as recommended to the Operations Committee:
- a Best Value
Review of Property Consultancy Services should be included in the
Best Value Review Programme for 2002/03; and
(b) the
current contract with WSA should be extended until 31 March 2005.
- It would however
also be appropriate to review the performance monitoring arrangements
under the current contract before the contract is re-let.
RECOMMENDATION
- The Executive
is RECOMMENDED to consider the recommendation of the Operations Sub-Committee
having regard to the Director of Environmental Services’ advice set
out in the report.
DAVID
YOUNG
Director of
Environmental Services
Background
Papers: Nil
Contact
Officer: Neil Monaghan, Tel Oxford 815712
January
2002
Return
to TOP
|