ITEM EX10
EXECUTIVE
- 22 JANUARY 2002
THE REVIEW
OF FINANCIAL MANAGEMENT IN SOCIAL SERVICES
Report by
Director of Social Services and Director of Business Support
Introduction
- The Executive,
at its meeting on 27 November, requested a report on proposals to improve
financial and management control processes within Social Services and
to include the advice of CareConsult. The Executive Summary and specific
action plans recommended by CareConsult are attached. This report summarises
their findings and proposes a way forward to ensure the recommendations
are implemented where appropriate.
The FINE Project
- CareConsult were
commissioned to undertake a project, subsequently called the FINE (Finance
in a New Environment) project, taking an in-depth view of the current
financial management arrangements for the Social Services Department,
and the development of viable recommendations to strengthen the financial
management to rectify the identified areas of weakness.
- A Project Team
consisting of mainly third tier managers worked closely with CareConsult
on assembling the evidence, identifying the weaknesses and making recommendations
on how improvements could be made. The project was divided into three
distinct areas: processes, information and people. The officers involved
were selected for their detailed knowledge of these areas with the addition
of representatives of the operational managers.
- During the project,
interviews were conducted widely throughout the department to firstly
identify departmental perceptions of financial management. Evidence
was then gathered to ascertain whether the perceptions were based on
fact. Visits were then undertaken with other authorities to compare
practice. Finally the project team took part in two workshops to sift
the evidence, identify best practice and put together action plans to
implement best practice in Oxfordshire.
Current Financial
Management and Key Findings Processes
- The budget setting
is top-down and incremental from the previous year’s budget. The process
is not linked to activity. Given that service activity is in a large
part driven by client need and measured by Government performance indicators,
a budget that is not linked to activity is not a realistic translation
in financial terms of the service that needs to be delivered. Nor is
the budget tied to other plans such as the Social Care plan.
- Service management
below second tier is not significantly involved in the budget setting
process. Lack of involvement discourages a sense of "ownership"
of the budget leading to inconsistent budget management.
- In terms of budget
monitoring, practice ranges from good to substantially inadequate. In
some cases the data provided to managers is good and action is taken
on the data. In others data is absent and no action is taken. There
is room for improvement in consistently managing costs through more
robust financial projections and a greater focus by budget managers
on projected overspends. This would allow more timely action to control
spending.
Information
- The IT systems
are dated, relatively inflexible and not user friendly. The systems
are stand-alone and the department suffers from a poorly co-ordinated
IS strategy. Although there are improvements in train through the MIS
project and the SWIFT programme, this will not address all the financial
information needs of the department. There is an absence of resources
for full SWIFT implementation. The responsibility for delivering services
is widely distributed geographically, but the budget managers in the
field have too few PCs to enable them to manage their own resources
and budgets.
- The consequence
of the above are significant manual manipulation of data and reporting
which is both time consuming and prone to error. The delays due to manual
intervention also means information is not timely. Budget managers do
not consistently receive and monitor activity cost driver information
to enable early corrective action. A low level of PCs among service
staff makes it difficult to input transaction data or monitor their
performance locally.
People
- The department
has a generally "professional social services" culture, in
which management and financial skills are generally considered as being
of secondary importance to social work know-how by most service managers
at all levels. The consequences are financial management procedures
which are not linked to activity or outcome; an us and them attitude
between finance and service managers leading to limited information
sharing; and budget management is not rigorously emphasised in the performance
management of the service.
- Structurally there
are few direct reporting links between finance, income and assessments
or performance management below Assistant Director level. Furthermore,
finance is completely separate from strategic planning. The structure
exacerbates the disconnect between finance on the one hand and service
planning and operations on the other.
- Training of budget
managers was last undertaken six years ago. This lack of training results
in both an absence of budget management skills by service staff and
an implied message that budget management is not important. There is
no specific financial training available to finance staff. This precludes
the development of the finance function towards more value added work.
- The current scheme
of delegation was written in 1997/98 and it is planned to revise it.
It is a comprehensive overarching document but there is little explicit
detail. The details are held separately by designated officers, which
makes it difficult to readily refer to appropriate policies and/or identify
inconsistencies.
Comparison
with Other Organisations
- Four County Social
Services departments and two London Boroughs were selected for comparison,
to identify good practice elsewhere. They were selected on the basis
that each of these organisations appeared to have either demonstrated
robust budget management performance and/or had successfully addressed
past problems in this area. Information on processes, information and
people was gathered in interviews lasting up to two hours.
Recommendations
from the Project
- An analysis of
the key findings within OCC Social Services department, best practice
identified in other organisations, and the individual experience of
the FINE project team members, have led to a number of recommendations
to meet the objectives set for the project and substantially strengthen
the financial management arrangements within the department.
- The recommendations
consist of a number of principles agreed at the workshop which were
converted into objectives along with an action plan designed to deliver
the objective. These are all detailed in the papers attached to this
report. The recommended objectives are:
- Processes:
- To improve the
process for compiling the Revenue Budget for 2002/2003 by introducing
in certain key areas a "bottom up" approach, with a view
to extending this approach to all budgets in 2003/2004. This will
also ensure that the decisions of the Executive and Members are based
on a better understanding of what budgets will purchase in terms of
care packages.
- To bring in
a system for routinely monitoring the budget on a monthly cycle.
- To clearly define
who has responsibility for managing each budget and taking appropriate
corrective action where necessary.
- Information:
- In the short
term, to automate downloads from Trojan and LAFIS to Excel, and
- to make the
best use of non-financial cost driver information currently available.
- In the longer
term to ensure that all data required for the service, including business
management, is entered once and appears instantly within the information
needs of the department. This may be information about individuals,
client groups or other aggregations and may be required to be shared
with partner organisations.
- People:
- Re-align Organisational
Structure
- Formalise &
approve all divisional finance officers as directly responsible to
a senior officer in the finance function with secondary responsibility
to a service manager.
- Short-term:
split staff below DFO’s into groups providing financial advice and
support and a group providing financial administration, e.g. processing
invoices etc.
- Long-term: move
financial administration into service.
- Align budget
structure and owners to Social Services organisational structure and
decision making points.
- Improve co-ordination
between Strategic Planning, Finance, Income & Assessment, and
Performance.
- Group the Resources
Division and the Strategic Planning and Resources Division together
under a Business Support Unit with strengthened co-ordination as mentioned
above.
- Ensure service
managers’ Job Descriptions include budget responsibilities as part
of performance management responsibilities.
- Strengthen focus
on budget management within performance management.
- Institute active
finance training programmes for finance staff and for cost centre
managers.
Vision for
the Future
- The target environment
for financial management in the Social Services department is one where
the budget is allocated to operational staff in line with their service
objectives; where managers throughout the organisation are appraised
against their performance, defined as the delivery of their objectives
in line with their agreed resource allocation; and where the staff,
Divisional Management Teams and the Senior Management Team all monitor
and review objectives, activity and expenditure on a regular basis.
- To support staff
in the delivery of this budgets need to be realistic and deliverable.
Managers need to be trained and appraised on competencies that include
financial and performance management. Staff are supported by efficient
and effective information systems whereby data is input once only and
all required information is instantly available to the budget holder.
Staff are also supported by a decision support team who provide assistance
on costings and activity predictions.
Implementation
and Financial Implications
- The report points
out that action plans are useful only to the extent that they are implemented.
In recognition of this some progress has already been made in delivering
some of the action plans. Progress has not been as fast as hoped because
of the need to absorb most of the work to date within existing resources.
With the exception of the Local Information Plan (see below),
the additional resources required to deliver the plans, whilst being
significant, are nevertheless manageable. Having said that in total
the plans do represent a substantial programme of work which needs to
be prioritised and managed properly.
- Each action plans
contains details of the resources required to deliver the action required.
These resources have been identified in terms of staff days. In the
vast majority of cases existing staff could carry out the work. It is
doubtful whether this can be absorbed within existing workloads in all
cases and attempting to do so will delay implementation, possibly indefinitely.
There is an inbuilt assumption that most ongoing work, e.g. by finance
staff in providing additional advice and assistance with budget monitoring,
will be absorbed within time released by the automation of some processes
and the restructuring of the finance function.
- The total requirement
has been summarised by CareConsult since the report was produced. In
total approximately 220 staff days are required to implement the recommendations.
If it is assumed that additional resources are required for all these
days, either for staff to undertake the action plan or back fill for
staff that do, the cost is estimated at £75,000. This is a maximum requirement
because some work could be absorbed.
- In addition to
this resources will be needed to project manage the action plans, to
ensure delivery, and to organise the additional resources. CareConsult
recommend an external project manager part time for about six months
to undertake this task. Based on their recommendation of one day a week,
this would cost a further £16,000. In practice, the external project
manager could also carry out some of the detailed work to deliver some
of the action plans. The maximum resources required, as recommended
by the consultants, totals therefore £91,000. Much of this is one off
to get systems and processes in place. However, about £25,000 may be
needed on an ongoing basis for training.
- This excludes
any resources needed to improve the information systems within the department.
The consultant’s view is that improvements can be made in financial
management in the short term using existing systems and the report’s
recommendations are geared to delivering such improvements. However,
this does not address the resource requirements as a consequence of
the department’s Local Information Plan and the need to deliver on the
Government’s E-Government and Information for Social Care agenda.
Local Information
Plan (LIP)
- The third objective
under Information in paragraph 18 above relates to the wider information
needs of the department. The LIP strategy already provided a framework
for the delivery of this objective and draws together the key implementation
milestones for SWIFT and MIS. The LIP should therefore be developed
and form the basis of the detailed implementation plan for meeting this
objective, encompassing the wider aims and objectives of a departmental
IT/IS strategy within the corporate context.
- To date only very
limited resources have been identified to address the Plan. Funding
of £207k has been agreed by the Department of Health and the draft Medium
Term Financial Plan contains a "bid" of £500k under unavoidable
pressures. There is an issue over how much the Plan will cost to deliver
depending upon how sophisticated a system is required and also how much
of the necessary infrastructure will be provided corporately, e.g. through
the development of the Oxfordshire Community Network. Preliminary indications
are that for a lower specification system, £6.5m of capital is required
with ongoing revenue costs of £2.4m. This does not take into account
any corporate provision which may reduce the costs.
- Included within
the report on the Medium Term Financial Plan to the Executive is a paper
concerned with raising performance through e-government. The paper recognises
the need to address the shortfall in investment on IT within service
budgets. It is proposed to report to the Executive in April on a firm
business plan for IT, taking into account service needs and any available
revenue and capital funding sources. At that stage the Social Services
LIP can be considered within an overall strategic plan for the authority.
- The Council is
currently implementing a new Management Information System (MIS). The
Social Services department is also considering implementing the Costed
Packages of Care facility on SWIFT. Officers have been involved in identifying
what technically is required from the systems. However, there is concern
that there is a need to widen the issue and involve the operational
staff in identifying in practical terms their information requirements
to assist them to manage the business. This needs to be co-ordinated
in some way. A bid has been made for resources from sums set aside within
the MIS project to assist departments in carrying out this exercise
in relation to that project. It is important that the outcome from both
these projects and the FINE project are linked. The opportunity could
be taken to identify one project manager to implement FINE and link
in the department’s requirements for these other projects.
The View of
the Social Services Senior Management Team
- The department’s
Senior Management Team has considered the outcome and findings from
the review. In general terms the report is welcomed as a valuable piece
of work and the Team endorses the recommendations contained within the
report. The Team agrees with the general thrust of the report. However,
the Team believes that each issue highlighted within the report, whilst
being a fair reflection of practice in some parts of the department,
is not necessarily representative of the whole department. Having said
that the Team agrees that improvement is required in all the areas identified
if improvements in financial management are to be made.
Other Related
Issues
- An additional
Assistant County Treasurer has been seconded to the Social Services
Department for about nine months to assist in the review of financial
management within the department and to assist with the control of the
budget in the current year and the formulation of the budget for 2002/03.
This period of secondment will be coming to an end within the next couple
of months. Decisions need to be taken on what changes need to be made
to the financial support for the department following the secondment.
- There are inter-related
reviews currently outstanding that need to be considered at the same
time. There is the review of the Management Structure within the Social
Services Department (recently deferred pending the outcome of the above
FINE report) and the wider review of the Education, Social Services
and Cultural Services Departments.
- The two Assistant
County Treasurers currently in the Social Services Department, will
be advising the Chief Executive, the Director for Business Support and
the Director of Social Services on their views about the arrangements
for financial management within the department. This will cover both
the short term, until the above action plan has been fully implemented,
and in the longer term. This advice can then be taken into account in
the wider debate.
The Way Forward
- There is no doubting
the importance of implementing the recommendations in the CareConsult
report. It is also important that additional resources are identified
to both implement the action plans and to project manage them. It is
also necessary for the senior officers within the Council to take a
personal interest in ensuring progress is made. It is proposed therefore
that the Chief Executive commissions a sub-group of the County Council
Management Team to monitor progress. This team would agree the arrangements
for project management with the Director of Social Services and the
Director for Business Support. The issue of the Local Information Plan
also needs to be addressed by this sub-group.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- endorse
the CareConsult report (download
as .rtf file);
- agree
the recommendations contained within the report;
- identify
the resources to implement the recommendations within the Council’s
budget for 2002/03; and
- ask
the Chief Executive to commission a sub-group of the County
Council Management Team to monitor progress on implementing
the recommendations.
MARY
ROBERTSON
Director of
Social Services
CHRIS
GRAY
Director for Business
Support
Background
Papers: CareConsult report: "Finance In a New Environment"
Contact
Officer: Paul Gerrish Assistant County Treasurer Tel 01865
815370
14
January 2002
Return
to TOP |