|
Return
to Agenda
ITEM EX6C
EXECUTIVE
22 JANUARY 2002
CAPITAL
PROGRAMME 2001/02 TO 2003/04
Report by
Director for Business Support & County Treasurer
and Director of
Environmental Services
Capital Settlement
2002/03
- The County Councils’
capital allocation for 2002/03 comes under the new Single Capital Pot
arrangements. We have received a Basic Credit Approval (BCA) of £28.987m
for 2002/03. The BCA is calculated from individual Service Annual Capital
Guidelines (ACG) and a discretionary element of BCA as follows:
| |
£’000
|
|
Education
|
8,666 |
|
Transport
|
18,613 |
| Social
Services |
550 |
| Other
Services |
577 |
| Total
Annual Capital Guidelines |
28,406 |
| Less
Receipts Taken Into Account |
-738 |
| Discretionary
BCA |
27,668 |
| Basic
Credit Approval |
1,319 |
| |
28,987 |
| |
|
| |
|
- In theory the
Single Capital Pot allows the County Council greater freedom to spend
capital resources on its own priorities. There is an anticipation from
government that there will be improved outcomes and better services
arising from the introduction of the Single Capital Pot as follows:
- More autonomy
and accountability and greater responsibilities for local authorities
in making their decisions;
- Better planning,
by giving greater predictability in funding levels and allowing more
flexibility;
- Better corporate
and strategic working and more effective tackling of cross cutting
issues; and
- Better use and
management of assets.
- However the Transport
Settlement letter indicated that there is an expectation that authorities
spend sufficient funds on transport to enable them to work towards,
and ultimately meet, the objectives and targets contained within their
LTPs. This will be monitored through the Transport Annual Progress Reports.
- The level of capital
support for 2002/03 is similar to 2001/02. What is new is a discretionary
element of the BCA which can be spent as we see fit. The discretionary
sum represents an allocation of 5% of the total available capital resources
within the Single Capital Pot. The allocation is based on evaluation
under the new central government assessment system of the Council’s
Capital Strategy and Asset Management Plan, plus assessments of service
areas. Our Capital Strategy and Asset Management Plan were both assessed
as satisfactory, the categories being "good", "satisfactory"
or "poor". Our service area assessments were as follows (the
categories being "well above average", "above average",
"average", "below average", and "well below
average"):
Service
Area Assessment
Education Average
Social
Services Above Average
Transport Above
Average
Overall
Performance Above Average
- A number of comments
were made on the relevant strengths and weaknesses across the Capital
Strategy and Asset Management Plan and these will be taken into account
when submitting our revised Capital Strategy and Asset Management Plans
to the Government in July 2002. We will bring forward drafts to the
Executive for approval in due course.
Financial Position
- The financial
summary shows a surplus of funding for the capital programme in 2001/02
(£4.8m), a deficit of £0.7m in 2002/03 and a surplus of £8.7m after
2002/03. However no schemes have been added to the programme to reflect
the new annual capital guidelines received for 2002/03, other than a
single line added to the Environmental Programme to reflect the net
effect of the Transport Settlement. The Director of Environmental Services
will be proposing a detailed allocation of the settlement in due course,
and the analysis will be included in the next capital programme update.
Summaries 1 - 3 (download as .rtf
file)
Financing of Capital Programme (download
as .rtf file)
- The overall financial
position for each service block is analysed below:
|
|
|
|
|
|
|
|
|
|
2001/02
|
2002/03
|
After
2002/03
|
Total
|
|
|
|
£m
|
£m
|
£m
|
£m
|
|
|
|
|
|
|
|
|
|
Education
|
6.7
|
-3.8
|
7.4
|
10.3
|
|
|
Transport
|
0.9
|
-1.9
|
-1.1
|
-2.1
|
|
|
Social
Services
|
-2.8
|
1.1
|
4.2
|
2.5
|
|
|
Environmental,
Protective and Cultural Services (EPCS)
|
|
|
|
|
|
|
-0.3
|
-0.4
|
-0.4
|
-1.1
|
|
|
|
|
|
|
|
|
|
Sub
Total
|
4.5
|
-5.0
|
10.1
|
9.6
|
|
|
|
|
|
|
|
|
|
Capitalisation
of Revenue
|
|
1.0
|
0.5
|
1.5
|
|
|
Discretionary
BCA unallocated
|
|
1.3
|
|
1.3
|
|
|
Potential
Slippage
|
|
2.0
|
-2.0
|
0.0
|
|
|
Other
Adjustments
|
0.3
|
|
0.1
|
0.4
|
|
|
Surplus
/ Deficit (-)
|
4.8
|
-0.7
|
8.7
|
12.8
|
- In addition we
have received Supplementary Credit Approval for 6th Forms
basic need of £641,000 in 2002/03, £916,000 in 2003/04 and £275,000
in 2004/05. Additional grant has also been approved for New Deal for
Schools and devolved capital. These items will be added to the next
capital programme when details have been worked out.
- In the commentary
below and the draft Capital Programme, the programme areas of the former
committees have been retained. The divisions will be reviewed for the
future in line with the Revenue Budget arrangements.
Education
- The Education
Committee has a surplus of £2.9m at the end of 2002/03 rising to £10.3m
by 2004/05. This surplus mainly reflects the new credit approvals received
for 2002/03 (£2.6m) and the commitment to further credit approvals of
£3.7m in 2003/04 and £1.1m in 2004/05.
- However, included
within the resources available to fund the Education programme (download
as .rtf file) in 2002/03 is a contribution of £3m in respect of
Wallingford School from the trustees who owned part of the land sold
in 2000/01. Although there was an understanding that the Trustee’s share
of the capital receipt would be used to contribute to the cost of the
works on the Lower School site the receipt has not yet been paid over
and there are still discussions being held on the interest in the Lower
School site to be transferred to the Trustees in consideration for the
£3m. If the payment is not made in 2002/03 then the Education programme
would be in deficit at the end of that year by some £0.1m, returning
to a surplus of £7.3m by 2004/05.
- Under existing
rules the Education Service can plan on the basis of having a programme
balanced with resources available. This allows them to bring forward
projects totaling £10.3m for inclusion in the programme from 2002/03,
of which no more than £2.9m should arise in 2002/03. However if the
Wallingford Contribution is not received the Programme will only have
£7.3m available for new projects and could not commit schemes until
2003/04.
- The Education
credit approvals are based on bids made to the Department for Education
& Skills and reflect basic need (i.e. roofs over heads) as a result
of rising pupil numbers. The Education department is planning on the
basis of developing new schemes for an April 2003 start. This will incur
fees in 2002/03 but these should be contained within the overall programme.
In 2002/03 only schemes with specific grant will come through into the
programme. This covers the position if the Wallingford contribution
is not obtained.
Social Services
- The Social Services
programme (download as .rtf file)
shows an overall surplus of £2.5m by 2003/04. However there is a funding
shortfall of £2.8m in 2001/02 falling to £1.7m by the end of 2002/03
before returning to surplus. The programme includes the anticipated
sales and purchases arising from the Homes for Older People transfer.
The impact of the transfer on capital and revenue is attached to the
Strategic Overview Report.
- Social Services
are allowed to plan on the basis of a programme balanced to their available
resources. Technically they can add new projects to the value of £2.5m
into their programme after 2002/03.
- The Homes for
Older People (HOP) transfer will require a switch of resources between
revenue and capital as part of the financing in the early years is through
capital receipts and lease premiums. The Council will have to capitalize
revenue payments in 2002/03, totaling £2.4m, and £2.1m in 2003/04. This
will also affect the receipts taken into account adjustment in the BCA
for 2003/04 and this has been allowed for in the overall resources available
to the programme.
Environment
- The Environmental
programme has been updated to include the effect of the new credit approvals
received under the Local Transport Settlement (LTS). A single line has
been included in the expenditure tables at this stage to reflect the
net resources to be allocated. Of the £18.6m settlement some £1.4m has
been reserved for the Banbury Hennef Way Dualling Stage 1 project. The
Transport Settlement is based on bids made by the Council. Of the £18.6m
received there is an indicative figure of £8.013m for local road maintenance,
although this allocation is not ring-fenced. The Environmental programme
is allowed to spend all the resources allocated through the LTS. The
Director of Environmental Services will be bringing forward proposals
for allocating these resources in due course and these will be included
in the next capital programme update.
- The Environmental
programme (download as .rtf file)
shows a deficit of £2.1m which has arisen from approvals given in previous
years for fees on developer funded schemes and preparation pool schemes
for which no funding is available. There may be a requirement to approve
additional fees money for these purposes in future years but no additional
money is sought at the moment. Allocations in earlier years have ranged
from £0.5m to £0.75m.
Public Protection
- There have been
no additions to the Public Protection capital programme.(download
as .rtf file)
Cultural Services
- There have been
no additions to the Cultural Services capital programme (download
as .rtf file)
Operations
- The Operations
Sub-Committee capital programme includes a scheme for improvements to
County Hall in 2002/03 totaling £0.4m for which a project appraisal
is attached to this report for approval (Annex 2).
(Strategy & Resources capital programme (download
as .rft file))
Broadband Network
- The County Council
agreed to the installation of a Broadband network at its meeting on
11 December. A budget provision of £1.5m has been approved from 2002/03
to meet part of the costs associated with providing the network.
- This leaves unfunded
costs of £821,000 in 2001/02 and £918,000 in 2002/03. The costs for
2002/03 assumed a receipt of £250,000 E-Government funding from the
Government. This figure has now been reduced to £200,000 increasing
the deficit in 2002/03 to £968,000. The report on the Broadband Network
identified potential income sources to meet part of the unfunded costs.
Negotiations are ongoing to secure contributions, but none have been
agreed to date.
- It is proposed
to charge the 2001/02 capital costs outstanding to the Capital Programme
(£697,000). The 2002/03 costs could be offset by external income.
Capital / Revenue Flexibility
- Whilst the earlier
part of the report sets out the traditional way in which the Council
would allocate its capital resources for 2002/03, the Executive may
wish to consider an alternative strategy, which would create some flexibility
in the revenue budget. It can be seen that there is very limited flexibility
in the capital programme to introduce schemes for 2002/03 as there is
only £4.1m of unallocated resources. This does not allow for the possible
loss of the Wallingford School contribution of £3m and £0.7m has been
proposed to be used for Broadband Capital Costs. The 2002/03 programme
also includes an assumption that £2m of natural slippage will occur
in 2002/03. This could leave the programme with just £0.4m surplus in
2002/03.
- There is also
need to capitalize some revenue payments to facilitate use of the capital
receipts from the HOPS transfer.
- In 2001/02 it
is anticipated that there is some £5m of expenditure within the revenue
budget that is capable of being capitalized, being structural maintenance
of roads and buildings and vehicle purchase. Similar amounts are likely
to be available in 2002/03.
- In 2001/02 it
would be possible to capitalize some £2m of structural road maintenance
and charge it to the Transport Supplementary Credit Approval received.
This can be done as there is likely to be £2m slippage on spending the
full Transport SCA in 2001/02. This releases £2m from revenue which
could be carried forward to help fund the budget in 2002/03.
- In 2002/03 it
is proposed that the Council charges £1.0m of revenue expenditure of
a capital nature against credit approvals to release a further £1.0m
of revenue monies to help fund the budget in 2002/03. This is the maximum
that can realistically be released whilst enabling the delivery of a
realistic transport capital programme.
- This can be achieved
in the short term. In the long term the Council has to demonstrate that
it can deliver its Local Transport Plan through the Annual Progress
Review in order to achieve favourable Transport Settlements.
- The Director of
Environmental Services has raised no objection to the capital/revenue
switch but on the basis that the Council replaces the lost transport
capital monies from revenue in future years. This point has also been
made by the Environment Scrutiny Committee (see further below). This
concern could be met by allocating £1.0m a year from the revenue budget
to support the Capital Programme from 2003/04 to 2005/06.
- Part of the £5m
revenue expenditure remaining (£2.4m in 2002/03) will be needed to facilitate
the use of HOPs capital receipts to meet the payment streams arising
in the early years from the HOPS transfer.
Other Options
- The Executive
may wish to consider alternative options to allocating capital resources.
Any changes in policy would need to be incorporated within the Council’s
Capital Strategy to be submitted to the Government by the end of July
2002.
Capital Programme and
Asset Management Steering Group (CPAMSG)
- The steering group
met to consider the highest priority bids from service departments with
a view to advising the Executive on the priority projects to be met
from any available funding. Their views will be reported at the meeting.
Priming / Private Finance
Initiative
- The Leader of
the Council has requested a report on the potential for the Council
to undertake a Priming exercise and to identify potential areas for
a Private Finance Initiative project. Consultants have been asked to
advise on this and their report is due back towards the end of March.
A report will be taken to the Executive in April to present the consultants’
advice and to give recommendations on any schemes which are considered
potentially suitable and eligible for PFI and on options for the Council
for using the value of its assets to secure funding for new investments.
Oxford City Schools
Reorganisation
- A detailed analysis
of the City Schools Reorganisation is included as part of the Education
capital programme. The cashflow position is analysed below:
|
Year
|
Shortfall(-)
/Surplus
|
Cumulative
Shortfall(-) /Surplus
|
|
|
|
|
|
|
|
|
|
|
2000/01
|
(984)
|
(984)
|
|
2001/02
|
(3,989)
|
(4,973)
|
|
2002/03
|
(1,096)
|
(6,069)
|
|
2003/04
|
7,154
|
1,085
|
|
2004/05
|
(1,085)
|
0
|
- The cashflow position
has improved in 2001/02 and 2002/03 due to a small element of slippage
on the programme. Proposals to fund the cashflow shortfall are included
in Annex 1.(download as .rtf file).
Project Appraisals
- The following
project appraisals are submitted to the Executive for approval:
OP48 County
Hall Improvements (attached, Annex 2) (download
as .rtf file)
ED580 West
Oxford School (see Exempt part of the Agenda)
- The Executive
are recommended to approve the appraisal for County Hall Improvements
funded from the discretionary element of the single capital pot. The
West Oxford School Project is proposed to be funded from anticipated
supplementary credit approval, Wallingford contribution or reprioritisation
of the Education Capital Programme.
Prudential Guidelines
- The Government
is to introduce a new system of prudential guidelines to replace the
current capital finance system. Implementation is anticipated to be
from April 2004. Details of the system are included in the White Paper
– Strong Local Leadership – Quality Public Services dated December 2001.
The key features are the abolition of credit approvals, authorities
being able to borrow without government approval, more flexibility for
the Council’s Capital Programme and a system of prudential limits to
avoid Council’s debt going out of control, backed by reserve powers
for the Government to set a ceiling on the growth of a Council’s borrowing.
Government support for capital investment will continue but the form
has not been decided. The main benefits of the new system are as follows:
- Authorities
will be free to borrow for investment without Government consent,
provided they can afford to service the debt.
- That means more
spending on locally important projects – e.g. promoting better quality
of life.
- Authorities
will be more accountable and responsible.
- Local people
will have a greater say in decisions.
- Authorities
spending will be less tied in to rigid annual bidding rounds.
- The system will
be simpler to operate and easier for officers, councillors and the
public to understand.
- The new freedoms
will be balanced by sensible safeguards .
Recommendations from
Committees
- The Strategy &
Resources Committee in October 2001 deferred consideration of a bid
from the Operations Sub-Committee to allocate further funding to the
Energy Conservation Capital Budget from 2002/03 to allow the programme
of Energy Conservation works to continue at its current level. This
recommendation was considered by the CPAMSG, who have identified it
as a high priority project to be included in the 2002/03 capital programme.
- The Environment
Scrutiny Committee acknowledge the need to make use of flexibility between
revenue and capital funding as outlined in the Draft Budget Strategy
but advise the Executive that if any capital funds are diverted from
the transport block to assist with the revenue budget pressures in 2002/03,
these will need to be repaid to the transport capital programme within
the term of the Local Transport Plan if the objectives of the Plan are
to be met and highway safety will not be compromised.
Determinations to be
made by Local Authorities under part 4 of the Local Government and Housing
Act 1989
- Under Section
45 of the Local Government and Housing Act 1989 each Local Authority
must determine for each financial year before the commencement of the
year in question:
- Their overall
borrowing limit;
- Their short
term borrowing limit;
- A limit on the
proportion of interest which is payable at variable rates.
Overall Borrowing Limit
- This is interpreted
to mean the total borrowing from both external and internal sources
for capital financing purposes and the upper limit for revenue financing
purposes. Capital investment is partly financed by borrowing through
the consolidated loans fund, where debt outstanding at 31 March 2002
is estimated to be £197m, made up as follows:
| External
Borrowing (fixed rate) |
£167m |
| Internal
Borrowing (variable rate) |
£30m |
| |
£197m |
- In addition the
Council is anticipating receiving credit approval for the 2002/03 Capital
Programme (which automatically carries with it borrowing approval) of
up to £30m.
- The maximum permitted
borrowing for revenue purposes in 2002/03 is estimated at £67m based
on the relevant population figure for Oxfordshire. The total overall
borrowing limit proposed for 2002/03 is therefore £294m (£197m + £30m
+ £67m).
Short Term Borrowing
Limit
- This limit is
to encompass all borrowing that may not be of a long term nature at
any particular time. It is therefore suggested this should be the total
limit as determined under paragraph 46 less the present long term loans
from the Public Works Loan Board and the money market (external borrowing
in paragraph 44). On the basis of the present estimates this would give
the figure of £127m (i.e. £294m less £167m).
Proportion of Interest
Payable at Variable Rates
- In the case of
the County Council, this figure should be the same as the Short Term
Borrowing Limit i.e. £127m.
Conclusions
- The Capital Programme
has a surplus of £4.1m at the end of 2002/03 although this will be reduced
by the proposal to fund the Broadband costs (£697,000) in 2001/02 and
may be further reduced if the contribution of £3m from Trustees in Wallingford
is not received. There is therefore little headroom for introducing
new schemes into the capital programme in 2002/03.
- The impact of
this is that Education may not be able to introduce new schemes into
the programme in 2002/03 even though they have received some £2.8m towards
new basic need priorities. There is not much flexibility for dealing
with urgent priority bids from departments, particularly Annual Programmes.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- approve
the Project Appraisal at Annex 1 to the report;
- consider
the recommendations from the Capital Programme and Asset Management
Steering Group (to be reported at the meeting) and determine
which projects should be included in the Capital Programme;
- agree
that it is appropriate to meet the Capital costs of Broadband
in 2001/02 (£697,000) from the capital programme;
- subject
to the above, to approve the Draft Capital Programme and refer
it to Council for approval;
- RECOMMEND
Council to:
- approve an
overall borrowing limit of £294m for 2002/03;
- approve an
overall borrowing limit for short term borrowing of £127m for 2002/03;
and
- approve the
maximum amount of borrowing with interest payable at variable rates
as £127m for 2002/03.
CHRIS
GRAY
Director for Business Support & County Treasurer
DAVID
YOUNG
Director of Environmental Services
Background Papers Nil
Contact Officer - Mike Petty Tel.( 01865) 815622
January
2002
Return
to TOP
|