Return to Agenda

Division(s): Ploughley

ITEM PN8

PLANNING & REGULATION COMMITTEE – 17 OCTOBER 2005

PROGRESS REPORT ON MATTERS AT FOXLEY FIELDS FARM QUARRY AND LANDFILL SITE, FINMERE

Report by Head of Sustainable Development

Introduction

  1. At the 5 September 2005 meeting this Committee resolved to ask for another progress report on planning matters relating to this site. The full resolution (Minute 45/05) is as follows:

    1. note the report;
    2. instruct officers to write a strongly worded letter to Premier Aggregates expressing the Planning & Regulation Committee’s concern at the lack of progress on agreed remedial measures together with a Planning Contravention Notice as a precursor to enforcement action if progress was not rapidly made;
    3. ask officers to submit a progress report to the 17 October meeting setting out the options available to enforce the planning consent issued on 12 July 2005 and the conditions attached to it in the event of unsatisfactory progress on the agreed remedial measures.

  1. The resolution refers, amongst other things, specifically to the need for recommendations on the options available to enforce the planning consent issued on 12 July (00/01480/CM) and also the conditions attached in the event of unsatisfactory progress on the agreed remedial measures and requires a strongly worded letter to be sent to Premier Aggregates and a Planning Contravention Notice (PCN). These were sent in September.
  2. Background

  3. Premier Aggregates are continuing the import and disposal of waste at the site. At the time of writing this report tipping is taking place on the flanks of cell 6 below the approved levels (see plan) (download as .doc file). Premier have nearly completed the preparation of cell 8 and estimate that filling with imported waste could begin by the date of this Committee. The preparation of cell 9, immediately adjacent to cell 8, is proceeding with an estimate of the end of October before it can be used to receive the top 5 metres of the over-tipped waste from cells 1 to 6.
  4. It was reported at the last Committee that red silt had been deposited on the top of the site in clear view of the village. This silt appears to be above the approved levels. Premier Aggregates say it is to be used for day-to-day cover of the waste once over-tipped material begins to be re-deposited in cell 9.
  5. Progress on activities contrary to the July 2005 planning permission

  6. Our monitoring officer visited the site on 7 September and noted breaches of condition and the agreement and brought these to the attention of Premier Aggregates.
  7. Apart from the acknowledged over-tipping of the site the following breaches and actions made, or intended to be made, are listed below (the following conditions are set out in full in annex 1 (download as .doc file)):-

    • Condition 16 (Noise from reversing bleepers)

Premier Aggregates confirm that from mid September all mobile plant operating on the site were fitted with white noise bleepers so that the condition can be complied with.

    • Condition 18 (Measuring wind speed – to ensure no dust nuisance from the stripping of soils in high winds)

Premier Aggregates say that an order for a data logger, to record the results of the anemometer, has been made and is expected to arrive in the first week in October.

    • Condition 20 (Scheme for tree protection)

A scheme for tree protection has not been submitted in the month allowed following the issue of the planning permission. Premier Aggregates promise one will be submitted prior to this Committee.

  1. The agreement requires the recording of the source of waste (to enable catchment area requirements to be met). Premier say a new weighbridge system is on order but, in any event, a plan showing the local area with post codes marked on will be put up in the office. Data for all loads will be recorded with their postcode. They will also record whether the postcode areas are within or without the catchment area.
  2. A check will be made of the site shortly before Committee in order to verify these improvements and the results reported to the meeting.
  3. Options for Enforcement Action

  4. If checks confirm that satisfactory actions have been taken in relation to conditions 16, 18 and 20 then no enforcement action is required. If these actions have not been undertaken then the service of Breach of Condition Notices (BCNs) would be the most sensible action. BCNs would require compliance within three weeks of service.
  5. If no action has been taken on recording where waste is coming from in order to comply with the legal agreement then the remedy is to seek a prosecution.
  6. The only acknowledged breach where action by Premier Aggregates to remedy it cannot reasonably be taken before this Committee is the over-tipping above approved levels permitted in July 2005. A stop notice could be served to prevent any more deposit above this level, and only waste deposited above this level, but on the basis that cells 8 and 9 will be ready to accommodate imported and over-tipped waste at some time in October this year it is unlikely that waste, other than material needed for day-to-day cover to comply with licensing regulations will be deposited.
  7. Enforcement Action could be taken to require all the over-tipped waste to be removed above the approved levels: it would not stop waste being deposited in accordance with the July 2005 permission. In my view, it would be expedient to serve an Enforcement Notice because of the continued adverse visual impact of the over-tipped site on Finmere and because the over-tipped mound is an alien and unacceptable feature in the landscape. The Notice would have to specify what actions were required to take place giving a time within which they should be completed. The action could also include a requirement for restoration in accordance with the July 2005 permission.
  8. Premier Aggregates say that they intend to apply for planning permission to retain most of the over-tipped material in place. They also have the right to appeal the enforcement notice. Any such application would have to be determined on its merits against Development Plan policies taking into account any material considerations. If the application was refused the applicant would have the right of appeal. Despite the possibility of an application, serving an enforcement notice now, in my view, offers the best means by which to ensure that tipping of waste is brought back to reasonable levels. Nevertheless, Members should be aware that serving an enforcement notice does not guarantee a swift or satisfactory conclusion because of the appeal process.
  9. Conclusion

  10. It may be necessary to enforce planning conditions 16, 18 and 20 in the event that compliance with them has not been achieved by the date of this meeting. Prosecution may be necessary to seek compliance with the agreement so that the origins of waste imports are known.
  11. In addition, it may be expedient to serve an enforcement notice requiring the removal of all the over-tipped waste and restoration of that part of the site to run concurrently with the processing of any planning application made to keep the waste in situ.
  12. RECOMMENDATION

  13. It is RECOMMENDED that:

(a) unless conditions 16, 18 and 20 of planning permission 00/01840/CM are complied with by the date of this Committee then Breach of Condition Notices be issued to seek compliance;

(b) unless arrangements are in place for recording the geographical location of any imported load of waste then arrangements for prosecuting Premier Aggregates be made; and

(c) enforcement action be taken to secure the removal of all the waste tipped above the restoration levels approved under permission 00/01480/CM and the restoration of site in accordance with conditions of that permission.

CHRIS COUSINS
Head of Sustainable Development

Contact Officer: John Duncalfe Tel: Oxford 815356

Background papers:
File 8.1/6232/1 ‘Foxley Fields Farm, Revised Restoration and Inert Materials Recycling Facility’ held in the Planning Implementation Group, Environment & Economy, Speedwell House, Speedwell Street, Oxford OX1 1NE

October 2005

Return to TOP