MARKET SQUARE/WESSEX WAY, BICESTER - TRAFFIC MEASURES TO FOLLOW THE SKIMMINGDISH LANE IMPROVEMENT

Summary of the Consultation Presented to the Steering Group

The main issues arising and the group(s) which raised them, were as follows:

Issue:

Raised by:

Market Square is looking tired and some upgrading of the environment, including re-surfacing, seating, lighting, litter bins and bike stands is required. Some change is needed.

All groups.

Pedestrian safety should be improved and the crossing points shown in all options are in the right locations.

All groups.

Concern at the loss of parking in options 2, 3 and 4, particularly short term parking, with no provision for any replacement provision.

General public, Market Square businesses and the Chamber of Commerce.

Concern at the need for vehicular access to properties on the north side of Market Square and Market Hill throughout the day for collection and deliveries

Market Square businesses and the Chamber of Commerce.

Concern at the number of heavy goods vehicles, including those making deliveries and those passing through, using Market Square.

General public.

Concern at the prospect of the extension of Wessex Way, despite residents of Wessex Way acknowledging that they had been aware of the proposals when they purchased their flats.

Wessex Way and other affected residents.

More interest in improving the environment of Market Hill than in providing additional bus stops and taxi ranks here.

General public.

Key Events

April 2003 Submission of Planning Application.

June 2003 Planning Decision.

Implement interim safety improvements in the current operation of the Square.

October 2003 Start consultation on Operational Orders for the Market Square.

July 2004 Land Acquired from Developer.

Possible Public Inquiry (if required) into Operational Traffic Orders

October 2004 Earliest Approval of Traffic Regulation Orders.

March 2005 Wessex Way tenders issued.

July 2005 Wessex Way starts on site.

October 2005 Resolution of Public Inquiry on the Traffic Regulation Order.

Cherwell District Council Urban Design Works contract tenders issued.

March 2006 Wessex Way open to traffic.

April 2006 Start Highway Amendments to south side of the Square.