Return
to Agenda
ITEM CM7
COMMUNITY SAFETY SCRUTINY COMMITTEE - 1 DECEMBER 2008
FIRE SERVICE COMMAND AND CONTROL ROOM – THE
FiReControl AND FireLink PROJECTS
Report by Assistant Chief Fire Officer Colin Thomas (Oxfordshire’s Senior User
for the FiReControl and FireLink Projects and Joint Regional Project Board
Member)
Purpose/Background
· Regular update for
Community Safety Scrutiny Committee. This is now based on the Highlight Report
which we produce for the Joint Project Board
Project Summary
· General assessment – we
still await confirmation of the installation dates for FireLink Phase B (the
latest tentative date for the start is 30 Mar 09 – any further delay will cause
problems as it will then clash with our planned programme for the Early Station
End Equipment installation). At the same time, we have been told that there
will shortly be an announcement from the FiReControl project concerning delay;
although, as we are later in the programme, we are unsure how much this will
impact on our planned cutover date of Jan 09.
· Our own work in the Fire
& Rescue Service (FRS) to prepare for FireLink Phase B continues with the
contractor’s vehicle surveys completed in Oct 08. Detailed resource and
logistics plans are in place and merely await a firm start date. For FiReControl,
the enabling work to ensure our fire stations are ready for the Early Station
End Equipment (ESEE) is well underway and should be completed within the time
and cost estimates. The Data Conversion and Migration Toolkit (DCMT1) has now
passed its technical assurance tests and we expect to receive it in Mar 09.
In the meantime, we are pressing ahead with the work to prepare our Gazetteer
data for conversion.
· The detailed Highlight
Report is below:
Progress
(last month)
Coordinator to describe how they are proactively delivering
FiReControl (referencing TRN plan activities where appropriate).
This can be the regional progress report (if one is already being
produced) and should include issues that have been resolved at the FRS level.
- F04330 – Gazetteer Data migration. We have
received the IA report and attended a CLG workshop to analyse the
results. Action Sheet raised to initiate preparatory work on Gazetteer
prior to installation of DCMT1 – now expected Jan/Feb 09.
- F03180 – ESEE enabling work continues (4
stations out of 24 completed). Now have electrician and assistant
working full-time on project – completion planned Apr 09. This is
planned to be followed by EADS ESEE installation starting May 09
(dependant upon timing of FireLink Ph B)
- F08090 – Change to national call sign system.
Project on track to deliver change to national call signs on 31 Mar
09. Vivista have quoted for work on mobilising system. Plan to let
contract for work in Nov 08.
- F09130 – Incident Reporting System (IRS). Oxfordshire
successfully implemented the IRS on 1 Oct 08. Initial impressions are
that it is working well. A survey to gain an estimate of the impact of
using the system on our costs will be carried out at the end of the
first quarter of operation (Jan 09).
- Project Support Assistant now in post to
support both FireLink and FiReControl project teams.
- Service Delivery attended a SE WoW workshop
first week of Oct (predominantly to harmonise PDAs) and subsequent
workshop starting on 20 Oct on SOPs.
- PM visited Kent to discuss their assurance
process and use lessons to improve Oxfordshire work.
- FireLink Ph B surveys undertaken in week 20 -24
Oct. Timing for Ph B installation remains fluid.
- PM, Data Manager and WoW secondee (to start in
Dec 08) attended Data and Tech seminars in SE RCC on 28/29 Oct.
|
Problems
(Key points for discussion, Issues, Risks)
This should include
all areas where the FRS cannot resolve an issue without regional team or
national input.
It should also include the RED
issues in the DART reports at the FRS level that need national input to
deliver.
1. FiReControl Delay – DCMT1 is unlikely
to be installed until Feb/Mar 09 – this is for Gazetteer only. This
represents a delay of over 1 year compared to the original plan yet there has
been no change to cut-over dates and represents significant time compression
– impossible to tell at present when the lack of time will become critical.
With little hard information on the data migration task (or DCMT2 and future
software uploads for other data groups) this is fast becoming an issue. All
DCMT1 serials are RED on DART. We are expecting an announcement soon from
the national project team acknowledging a slip in the project timetable.
2. FireLink –Firelink Phase A
has yet to be closed out due to a number of issues relating to resilience,
this has a knock on effect which is continuing the
uncertainty over FireLink Ph B is making resource planning difficult since
the same scarce resources are required for both projects and avoiding
potential over-tasking is a problem with such fluid timescales.
a. We
still require basic questions on cost on operational use to be answered by
the project to allow us to decide on the number and disposition of the new
equipment to be finalised.
b. There
are still some small equipment design issues to be overcome before finalised
equipment can be installed |
Plans (next month)
Coordinator plans to help delivery next month.
This section should become, to large extent, the progress section at next
months meeting
- Continue
with ESEE enabling work
- Start
work to harmonise current Gazetteer with NLPG prior to installation of
DCMT1
- Continue
with call sign change implementation
- Initiate
work to improve assurance process within FRS
- Progressing
work to conduct internal business process review of ‘In Scope in FRS’
and ‘Out of Scope’ processes.
- Revise
communication plan
- PM
to attend OCC management of change workshop
- Continue
planning for FireLink Ph B, putting resources in place to support the
movement of vehicles, testing and user training.
|
Meetings held with EADS or
CLG
- None for
FiReControl
|
Communications activities
1. First formal indication of
project rescheduling passed to all Control personnel and elected members by
memo from ACO.
2. Project information on the
Intranet completely revised and renewed
3. Report on project progress given
to OCC Community Safety Scrutiny Committee.
4. Routine monthly Joint
Implementation Group meeting held
|
Risks
(Scored as High or Very
High on the FRS Risk Register, or new risks that the Coordinator has
identified)
RISK |
DESCRIPTION |
Delay |
Project slippage
jeopardizes FRS ability to maintain Control Room staffing and technology |
Unable to resource Data
Migration |
Inability to meet scale
of task (or effect of timescale compression) leads to delay, increased
errors and impacts on cut-over dates |
Inadequate retention of
control Room staff |
Inability to retain
control room staff compromises ability to maintain service standards |
Lack of staff
transferring to RCC |
Staff not transferring to
RCC leads to insufficient RCC staff, lack of expertise and threatens
ability of RCC to deliver agreed service. Increased threat of redundancy
and associated cost to FRS |
|
TRN
= training
IA = Intelligent
Addressing – A company whose name is shortened to IA
WoW workshop = Ways of
Working (this used to be called Convergence – the process of harmonizing
procedures across FRSs)
SOP
= Standard Operating Procedure
PM = Project
Manager
DART = Delivery and
Reporting Tool (a CLG reporting system for the FiReControl project)
NLPG
= National Land and Property Gazatteer
ACO = Assistant
Chief Fire Officer
COLIN THOMAS
Assistant
Chief Fire Officer - FiReControl & Firelink Senior User
Tel: (01865)
855206
Return to TOP