|
Return
to Agenda
ITEM BV9
BEST VALUE
& AUDIT COMMITTEE –
9 MARCH 2005
REPORT OF
THE AUDIT WORKING GROUP
Report by
Director for Resources
The Working Group
met on 14 January and 11 February 2005.
14
January 2005
Internal/External
Audit
- The Group received
a briefing on the differing roles and inter-relationship of Internal
and External Audit by Keith Bellew, Chief Internal Auditor and Mukhtar
Khangura and Tim Pearce, Audit Managers, KPMG LLP.
KPMG 2004/05
Audit
- KPMG updated the
Group on External Audit’s progress and plans for the statutory audit
of the 2004/05 accounts and their other work. KPMG’s appointment
was from April 2004 and they were responsible for the audit from 2004/05
accounts onwards. The Group considered member involvement and regular
briefing by KPMG including any inadequate management responses. The
interim audit and review of Internal Audit would take place in late
April/early May. Any issues would be reported via a letter or ‘mini
report’ and brought to the Group.
Project
Management
- The Group considered
a briefing note updating the position on project management as requested
at its December 2004 meeting and asked that the briefing note be circulated
to the members of Best Value & Audit Committee.
Internal
Audit’s 2003/04 Recommendations
- Members considered
the latest update on progress relating to Priority 1 recommendations
on Key Financial Systems and other ‘no assurance’ reports.
- The Strategic
Finance Manager, Leisure & Culture outlined the responses to the
report and answered questions relating to the recommendations on School
Support Finance. He commented that the section been under great pressure
but a restructuring in September 2004 was now bringing dividends. He
noted that the Internal Audit and Robson Rhodes reports had a common
theme – the writing of, and adherence to financial procedures. He outlined
the considerable progress made in implementing the Internal Audit recommendations.
Internal
Audit 2004/05 - Progress
- The Group considered
the schedule of recommendations in the 2004/05 Internal Audit report
together with activity to date in the current financial year.
11
February 2005
External Audit – Reports
to the Audit Working Group
- The Director for
Resources attended the meeting to discuss how External Audit should
report to the AWG and to discuss the qualification of the Best Value
Performance Plan (BVPP) in which there were still six PIs that were
not acceptable to KPMG. He was accepted that KPMG were right to qualify
the BVPP and Officers took this issue very seriously. Richard Shaw,
the former Chief Executive, had insisted on a report on each of the
6 PIs involved. The Chairman asked for the reports to be circulated
to himself, Members and Substitute Members. If necessary, some or all
of these PIs will be discussed at the next meeting. External Audit reports
should come routinely to this Group and/or Best Value & Audit Committee
(BV&A) as appropriate. The final drafts of reports should come to
the Group once they were broadly agreed between officers and KPMG. A
timetable to achieve this is being drafted.
Corporate Financial Procedures
- The Group received
a briefing on progress in producing corporate financial procedures.
There is a ‘root and branch’ review from Financial Regulations through
to detailed day-to-day procedures in the Directorates. The purpose was
that the Council should operate consistently across the different Directorates
and local systems and practices would be phased out. Training will be
provided.
Risk Identification
- The Group was
also updated on the techniques used to identify risks. Project management
remained an area of weakness for the Council and therefore for risk
identification. Partnerships are also a problem, as risk identification
was patchy and responsibility for risks was often vague. There should
be formal procedures to ensure consistency.
Risk Management
Progress
- The Group received
a report on progress on risk management arrangements in general. Weaknesses
still exist in some services but risk registers are now being updated
and should show improvement. It was hoped that more operational issues
would be included than previously (e.g. business continuity issues).
The Chairman asked that the Group be informed about any registers which
seemed to be inadequate or were produced late.
Freedom
of Information (FOI) Update
- There is a presumption
that the public have access to any information we hold unless there
is a specific exception, but the exceptions are only loosely defined.
A judgement must be made on each request. A decision not to release
information must be justified in writing so that the position can be
defended. The Group was advised that FOI does not need to inhibit discussion
within this Group in any way.
Internal
Audit Strategic Plan 2005/06 – 2007/08
- The Group considered
an update on the Strategic Audit Plan. It was noted that the long term
options for the procurement of internal audit services were under review.
The draft Plan used existing risk assessment methodology, prior to the
anticipated future use of the risk registers. Members wished to contribute
to the audit methodology in order to ensure that the Strategic Plan
was properly focused from 2005/06 onwards and were keen for the procurement
decision to be made so that the Plan could be finalised. The Working
Group was briefed on the procurement options which could be either in-house
partnership, external contract or local consortium.
Internal
Audit’s 2003/04 Recommendations
- The Business Manager,
Social & Health Care attended to answer questions on the ‘no assurance’
report on Fairer Charging. He noted that, of 19 recommendations, 12
had been implemented but they disagreed with one, number 3.1, as they
were moving towards less paperwork. Deadlines had been set for the outstanding
recommendations.
Internal
Audit Progress 2004/05
- Members discussed
a report on Internal Audit activity to date in the current financial
year, together with a schedule of recommendations made in 2004/05 to
date.
Matters
for Report to the Best Value & Audit Committee
- The Working Group
identified as specific items to report to the Committee:
- the updating
of the risk registers; and
- Internal Audit’s
possible changes in terms of procurement and the Internal Audit Strategic
Plan/methodology.
The
next meeting of the Working Group is scheduled for 4 April 2005.
JOHN JACKSON
Director for
Resources
Background papers: Nil
Contact Officer: Keith
Bellew (Tel: 01865 815265; e-mail: keith.bellew@oxfordshire.gov.uk)
February
2005
Return to TOP
|