Return to Agenda

Return to BV9

Return to Annex 2

Division(s): All

ITEM BV9 - ANNEX 2 - APPENDIX 2

BEST VALUE COMMITTEE – 23 JUNE 2004

VALUE FOR MONEY – BEST VALUE REVIEW PROGRAMME

Reengineering the Recruitment Process

Scoping Report

Project plan

Action

Timescale

Outcome

Business case for pilot established

April 2004

Achieved

Sponsor and working party established

May 2004

Achieved

Workshop 1

To explain theory and to plan field work

June 8th

 

Field work

To gather and analyse information about the process

June 9th -July 9th

 

Workshops 2, 3 & 4

To compare information from Directorate to Directorate and to design a common process where practical to do so.

To identify how MIS can be employed to help the process.

To identify efficiency savings.

July 12th, 19th and 26th

 

Steering group meetings including project sponsor, recruitment lead and project lead.

A further 2 meetings to be arranged

June 18th

 

Scoping paper to Best Value Committee

June 23rd

 

Secure member involvement

June-July 2004

 

Resources and costs

Each directorate will be asked to dedicate a minimum of 1 member of staff, and ideally 2 (to be negotiated) to work on the exercise for 10 working days over 1 month plus be available for 4 additional workshops.

Staff working on SAP and On line job applications will be asked to join the workshops being held in late May and June.

Activity

Cost (£)

 

Training and set up

Workshop 1

500

 

Fieldwork

Materials

Staff backfill

 

100

8000

 

Analysis

Workshops 2,3,4

 

2100

 

Admin

2000

 

Contingency

2,300

 

Total

15,000

 

Assumptions

(i) Things that have been taken for granted

(ii) Any dependencies on other projects

  • Staff will be available to undertake the project (this to be helped by providing backfill) and they are able to commit the time needed
  • That the SAP module and on-line job application packages are not "set in stone" and by working together, the most useful format for these can be developed.(interdependency of projects).
  • That staff working on MIS/on line job applications will be available to work on the implementation of the action plans
  • That the work to procure new advertising contracts links to the BPR findings (interdependency of projects).
  • Key information about the basics of the process are available.

Issues and Risks

Problems that are foreseen

 

  • During the exercise, staff will feel very pressured and find the time spent on the project (and away from their desks) as frustrating. This issue will be discussed when setting up the teams.
  • The SAP upgrade will erode the time available from the MIS team
  • The information needed will not be available and there will not be the time or resource to collect it
  • The SAP module will not be flexible enough to best fit new practice.
  • Delays in undertaking BPR will mean that the SAP module and the online application work will be developed past the point where BPR can be of help. Timing is critical.
  • Getting the right external support to address issues we have not encountered before.

 

Return to TOP