|
Return
to Agenda
ITEM AU9
AUDIT COMMITTEE
- 26 JULY 2006
FINANCIAL
MANAGEMENT IMPLEMENTATION PLAN 2 – QUARTERLY MONITORING REPORT
Report by
Head of Finance & Procurement
- The initial Financial
Management Implementation Plan was a set of actions designed to improve
financial management within Oxfordshire County Council. The Council
requested Robson Rhodes to complete a follow up review eighteen months
later. We have used the recommendations made by Robson Rhodes in this
follow up review as a basis for the second Financial Management Implementation
Plan. The revised plan identifies actions in nine priority areas and
one best practice area.
- Reliable financial
information on SAP
- Integrate finance,
performance and risk
- Remove control
weaknesses
- Policies and
procedures
- Internal audit
arrangements
- Performance
management of cost centre managers and budget holders
- Improve budget
management and financial reporting
- Financial training
- Appropriate
structures
- Schemes of delegation
(Robson Rhodes identified further improvements only required for best
practice. However the advent of e-procurement has necessitated a more
comprehensive revision than that envisaged by Robson Rhodes.)
- The status summary
will be updated every quarter and progress in achievement of key priority
actions reported to the Strategic Finance Group and the Audit Working
Group as well as this Committee.
- The table at annex
1 (download as .doc file)
summarises the current position on key actions and provides an assessment
of whether they are on schedule for achieving their objectives. Some
actions already have established projects and reporting channels whilst
other actions are being developed as a result of the follow up review.
Overview
- Project Link is
scheduled to be completed in July 2007. Some concerns have been raised
that this date may not be realistic for a number of reasons:
- The new project
manager will not be in post full time until 21 August and the project
officer role is still unfilled;
- The Social and
Community Services Directorate has a large number of ongoing projects
competing for staff time and attention. Although it has identified
pressure points for staff resulting from major directorate projects
there is not yet a plan to resolve the issues it has identified.
The
Project Progress report (13 June) identified that lack of project
team resources and limited availability of specialist consulting time
in August and September were likely to delay timely start and completion
of project tasks. Completion of phase 1 workshops by 17 August is
feasible but the outgoing project manager considers that further workshops
will need to be held to obtain all the inputs that are required. The
Project Progress report has also identified that the project plan
is too ambitious.
Project
Link was reported on separately to the Audit Working Group.
- The project manager
for the integration of non-SAP systems with SAP has drawn up a high
level plan for the project but this is already slipping and has not
yet been revised to reflect a realistic timetable. The plan for the
completion of all integration projects is expected to take about two
years. £500,000 is budgeted for non SAP systems integration during 2006/07
and further spend is anticipated for the following year. The project
team attribute the delay to bottlenecks caused by reliance on key staff
members in directorates who are involved in requests for information
from more than one corporate project in addition to normal business
activities. The delay in integration of non SAP systems is of concern
because, not only does it delay availability of timely and accurate
information on SAP, but also because it may impact on other council
initiatives such as Shared Services and Financial Management for Budget
Holders.
- The e-procurement
project is scheduled to go live in November 2006 in conjunction with
the accounts payable element of the Shared Services plan. The project
team have some concerns about the capacity of Directorates to provide
them with information and responses on a timely basis particularly in
view of demands from other projects. Delays in implementing the Procure
to Pay project may adversely affect the achievement of cost savings
envisaged by the business case for Shared Services.
- The project to
update policies and procedures has been delayed due to a delay in recruitment
of a Policies and Procedures Manager, although the appointment has now
been made. It is proposed to delay the completion of the briefings until
January 2007.
- Key achievements
since the last quarterly report in April include:
- An external
provider for project management training has been selected. All directorates
are due to report on their projects to the Corporate Change Manager
by 31 July. Those failing to do so will have to provide explanations
to the Audit Committee.
- The Statement
on Internal Control and the process for producing it have been approved.
- Manager appraisals
using the new Management competencies have been undertaken throughout
the Council.
- 122 budget holders
have completed the Financial Management Competencies training from
its beginning to 27 June 2006. 63% of budget holders trained have
since accessed SAP. The analysis of SAP usage will be used to target
support to budget holders. Further staff, for example, finance managers,
have also attended the training and a Head of Service Budget Summary
report has been developed.
- The next quarter’s
work will focus on:
- Actions to address
delays in the integration of non SAP systems and the Link project.
- Progress on
Integration of Financial Management and Risk
- The extent to
which Financial Management Competencies have become embedded in the
population of staff trained.
- Established projects
will continue to work through the project plan and report progress via
established corporate governance arrangements.
RECOMMENDATION:
- The Committee
is RECOMMENDED to note progress to date and give any feedback on the
quarterly monitoring report to the Head of Finance & Procurement
so that this can be incorporated in the work being undertaken on the
Financial Management Implementation Plan 2.
SUE
SCANE
Head of Finance
& Procurement
Background
papers:
Contact
Officers: Georgina Paton, Corporate and Professional Standards Manager,
Resources Directorate Tel. 01865 816357
July
2006
Return
to TOP
|