|
Return
to Agenda
ITEM AU8
AUDIT COMMITTEE
– 28 JULY 2006
INTERNAL
AUDIT QUARTERLY REPORT
Report by
Head of Finance & Procurement
- This report provides
a summary of the progress of Internal Audit in delivering the 2006/07
Internal Audit Plan, and the current performance against the indicators
agreed by the Audit Committee in November 2005. This report covers the
period 1 April 2006 – 30 June 2006.
Progress
Against the Audit Plan
- Appendix 1
(download as .xls file) to this
report lists all the assignments for 2006/07 and the quarters they are
currently planned to be undertaken. The table attached as appendix
2 to this report, analyses the number of audit
assignments by Directorate and then by quarter. In total, including
two additional audits identified in quarter 1, there are 104 audit assignments
to be completed, of which there are 15 where the work is planned to
be undertaken throughout the year, for example Payroll and Creditors,
or in more than one quarter, for example Risk Management.
- The quarterly
plans are agreed with the Directors and Senior Managers, however it
is inevitable that circumstance will arise that require changing the
timetable. To minimise the impact of any changes on the completion of
the audit plan, the planned activity for quarter 4 is currently lower
than other quarters. These tables will be updated each quarter to reflect
the changes for reporting to the Audit Committee.
- In quarter 1 there
were originally 17 assignments planned, with a further 7 of the cross
cutting assignments having planned activity in this quarter. Two new
assignments have been added to quarter 1 (See ‘Variation to the Plan’
later in this report).
- Of the 26 audits
planned, work has commenced on 20 of the audits. Six audits have been
deferred to later quarters:
- Payroll – Completing
05/06 work in this area so not appropriate to start 06/07 work
- Recruitment
and Selection – completing 05/06 work in this area so not appropriate
to start 06/07 work
- Children Social
Care Budget – A review of this service is currently being undertaken
by the Directorate. The audit activity will be deferred to later in
the year and used to evaluate progress on implementing changes for
that review.
- Client Self
Assessment – this project has not yet commenced in the Directorate
- Project Link
– the project is not yet at the business processing stage, therefore
internal audit involvement is minimal.
- E Procurement
– the project is not yet at the stage where internal audit need to
be involved.
- No audits have
yet been completed, but exit meetings have been completed for seven
of the audits, and draft reports are expected to be issued shortly.
- In addition to
the planned activity, the majority of the outstanding work has now been
completed from 2005/06. A contingency of 30 days was allocated for this
work, and this has been exceeded by 8 days.
Resources
- Three permanent
members of staff all started during quarter 1 and in addition a temporary
Senior Auditor also started. The team also welcomed back an Audit Manager
who returned from maternity leave.
- The two remaining
vacancies are going out to advert on Friday 21 July, and will be advertised
for four weeks. Interviews will be planned for the beginning of September.
- The procurement
of external services will be undertaken during quarter 2, and reported
to the AWG and the Audit Committee in September.
- One member of
staff has had significant sick absence during the quarter which is now
impacting on performance and is requiring a review of the allocation
of planned resource, which is likely to result in changes to the quarter
2 programme.
Performance
Monitoring
- The current performance
against the agreed indicators can be summarised as follows:
Elapsed
time between start of the audit (opening meeting) and Exit Meeting.
- The target is
no more than three times the allocated audit days. This has been achieved
for the audits where the exit meeting has been completed, and is on
target for the other audits where exit meetings have been planned.
Elapsed
Time for completion of audit work (exit meeting) to issue of draft report.
- The target of
15 days has not been achieved for the schools audits as a result of
staff sickness. There is also a minor delay as we are finalising the
changes to audit opinions that are presented in the reports. This is
not expected to be an ongoing issue.
Elapsed
Time between issue of Draft report and issue of Final Report
- No draft reports
have been issued, however it is anticipated that the delay to the school
audits being issued will result in this target not being achieved as
we are approaching the end of term, so schools will not respond until
September. This is not expected to be an issue for other audits as the
Auditors have agreed report turnaround times with the relevant staff.
%
of Internal Audit Planned Activity delivered against that planned to
be achieved for the period.
- The specific quarter
1 plan (not including the cross cutting audits) represents 21% of the
total activity, and currently 19% has been started. This difference
represents two audits. Whilst there is some slippage, this was expected
as two additional audits have been introduced in the quarter. There
has also been a significant resource change in this quarter, including
four new staff, so there has been a learning curve for these staff that
has resulted in some delays occurring, but it is not expected to be
an on going issue.
Hours
charged to audits compared to budgets
- In addition to
the overrun on the completion of the 2005/06 work, four current assignments
have gone over the allocated budget. In total 21 additional days have
been spent. However, this is mainly due to new staff familiarising themselves
with the Council and our processes, so the majority of the overruns
can be attributed to training and development. There is one audit where
additional resource had to be allocated as in addition to the routine
audit, concerns had been raised so a special investigation was also
undertaken. Where this is not the case, increased supervision has been
put in place to improve performance.
- At this stage
is not appropriate to report on the other indicators, as no reports
have yet been issued.
Variations
to the Audit Plan
- There are two
variations to the original Internal Audit Plan that require the approval
of the Audit Committee. These are additions to the plan each with a
budget of 10 days being met from the contingency built into the original
plan. Both variations have been agreed by the Head of Finance and Procurement.
The rationale for the variations are as follows:
|
Directorate
|
Audit
Activity
|
Rationale
|
|
E&E
|
Registration
Service Income Systems
|
The Head
of the Registration Service requested Internal Audit review the
adequacy of controls in their income systems, as she is concerned
the current information she is getting does not provide her with
the assurance she requires. The service collects approximately
£1Million a year.
The audit
will review the adequacy and effectiveness of the controls in
the income systems in particular focussing of the mitigation of
risks relating to fraud, inaccurate recording in the accounts
and robustness of management information.
|
|
SCS
|
Payments
to Order of St. John
|
A special
investigation has been requested by the Head of Finance &
Procurement to review the processes for processing payments to
the Order of St John, following the raising and subsequent cancellation
of a substantial debtor invoice that was incorrect. In addition
to reviewing the processes, the audit will also undertake verification
testing on a sample of transactions in 2005/06 and 2006/07 to
consider accuracy and appriateness.
|
Special
Investigation
- There are currently
nine special investigations being undertaken, two of which are carried
forward from 2005/06. Of these five relate to possible fraud, the others
relate to weakness in internal control. There has been a significant
increase in the number of incidents being reported, which is encouraging
as staff are raising concerns and detecting issues. Whilst internal
audit are not directly involved in investigating all these cases, we
do maintain an overview, and will be considering the internal control
issues resulting from each investigation.
- There is no indication
that any of the cases represent significant fraud, or material loss
to the Council, but they are minor opportunistic incidents. The Council
does however take these matters very seriously and by investigating
all cases is demonstrating a zero tolerance to fraud.
- Once the investigations
have been concluded, any internal control issues identified will be
reported to the Audit Working Group.
Other
Issues
- One of the key
areas of weakness in compliance with the CIPFA Code of Practice was
that the reporting lines of the Head of Internal Audit and in particular
the right to report independently was not explicit. This has now been
addressed, and a protocol has been agreed and signed by Senior Officers.
At the same time the Terms of Reference for Internal Audit have been
reviewed and updated to reflect changes in personnel and to the staffing
structure. These are attached to the protocol as annex 1. Both documents
have been attached as appendix 3 (download
as .pdf file) to this report, to be noted by the Audit Committee
and for the Terms of Reference to be approved.
Conclusion
- Satisfactory progress
is being made against the 2006/07 plan, and there are no major issues
or concerns to report at this stage.
RECOMMENDATIONS
- The Committee
is RECOMMENDED to:
- note
the report;
- approve
the variations to the Internal Audit Plan;
- note
the Head of Internal Audit Protocol; and
- approve
the Internal Audit Terms of Reference.
SUE
SCANE
Head of Finance
& Procurement
Background
Papers: None
Contact
Officer: Ian Dyson, Assistant Head of Finance (Audit), Tel: (01865)
815440
July
2006
Return
to TOP
|