01/11/2018 - Chairman's Updates

Wicklesham Quarry – Update

 

Officers advised members of concerns regarding inadequacy of gradient levels which had been achieved on the site as part of recently completed restoration work. Committee instructed officers to write to Grundons in the strongest terms asking them to adjust and correct those levels in order to comply with previously agreed restoration plans as soon as possible. If no positive response was received then officers were advised that the committee would support them in considering the expediency of enforcement action being taken requiring the site to be restored within a potential timeframe of 3 – 6 months.