ITEM EX20
EXECUTIVE
– 11 DECEMBER 2001
LIBRARY
SYSTEM REPLACEMENT
Report by
Director of Cultural Services
Introduction
- Revenue funding
was allocated in the Council’s 2001/02 Medium Term Financial Plan to
undertake the replacement of the outdated book issuing computer system
over a five-year programme from 2001/02, extending it to all libraries.
- Work has proceeded
to develop the specification for the system over the past eight months.
It is planned to complete this in the next month and then to proceed
to an invitation to tender via the European Journal in March 2002. The
finalisation of costs would then be achieved and authority to proceed
with the contract would then be sought.
- It is planned
to devote the bulk of the revenue funding available in 2001/02 to the
purchase of ICT consultancy to assist with this process and of PC’s
which will operate both for the current system (where some terminals
are now over seven years old and need replacement) and for a new system
when chosen.
Review of the Implementation
Programme
- During the course
of this year, partly as a result of the Best Value Review (BVR) investigations
currently underway, it has become increasingly evident that it would
be desirable to accelerate the above five year programme to three years,
to enable the library service to keep up with the e-government agenda
and to provide the service with a comprehensive network countywide.
The factors identified include the following:
- Oxfordshire
Community Network will deliver broadband connections to all libraries
by December 2002 for the People’s Network programme. This network
infrastructure will also be used for the library system and for the
new Management Information System. Bringing the Library System Replacement
programme forward to synchronise more closely with the roll out of
the People’s Network would allow full utilisation of the network at
an earlier date, maximising the council’s investment and enabling
the synergies between these major ICT developments to be fully realised
at an earlier date.
- Earlier implementation
would also be cost-effective in terms of project management. For example,
all the data and electrical cabling needed within each library could
be done at one time. This would reduce the level of disruption to
the public service, and would also enable staff training to be handled
as one programme.
- In order for
the library service to play its full part in the e-government programme,
all libraries need to be linked to a computer system that will allow
remote access by readers to check their accounts, renew their books
and place reservations. The existing completion date of March 2006
would not meet the government’s 2005 deadline for e-government.
- Acceleration
of the programme would also enable the library service to contribute
more effectively to the Council’s social inclusion and lifelong learning
agendas.
- It has already
been reported in this year’s Annual Library Plan that the current
timetable for the extension of a library computer system to all libraries
may preclude meeting the (mandatory) national standard for seven-day
book request satisfaction (PLS9i). However the Council is committed
to meeting DCMS standards by the end of 2003/04, subject to available
resources.
- It is becoming
increasingly evident, through staff consultation as part of the preparation
of the Annual Library Plan and through the work of the Best Value
Review of the Library Service, that the public perception of Oxfordshire’s
Library Service is adversely affected by the lack of a computer system
in the majority of libraries.
Conclusion
- Against this background
it may well be that one of the recommendations from the Best Value Review
will be to accelerate the implementation timetable. However, this would
have to be evaluated against other likely choices arising from the Best
Value Review (for example extending library opening hours and raising
book fund levels), and against the efficiency savings arising from the
review. At that stage it would be clearer what the options might be,
and whether the funding of the accelerated programme would be deemed
a financial pressure as part of the Medium Term Financial Plan, or would
be a choice against other priorities to be funded within existing resources.
Financial Consequences
- The acceleration
of the programme would lead to higher revenue payments in years two
and three (i.e. 2002/03 and 2003/04), as contributions to the renewal
fund would commence earlier with some reductions subsequently. There
could be however a financial premium of up to £156,000 over five years.
This financial modelling of the programme is still being developed,
as part of the Best Value Review.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to approve the acceleration of the implementation programme
for replacement of the book issuing computer system as described in
the report, subject to:
(a) Council
agreeing implementation of the Oxfordshire Community Network;
(b) the
Best Value Review of the Library Service confirming acceleration
of the replacement of the system as a priority;
(c) funding
being identified to meet any estimated shortfall that may arise
from acceleration of the replacement programme.
RICHARD
MUNRO
Director of
Cultural Services
Background
Papers: Nil
Contact
Officer: Andrew Coggins, County Librarian, Tel: Oxford 810212
30
November 2001
|