Return
to Agenda
ITEM EX18
THE EXECUTIVE
- 23 JULY 2002
TRAFFIC
MANAGEMENT PROPOSALS ASSOCIATED WITH THE RELOCATION OF SS PHILIP AND JAMES
C of E FIRST SCHOOL, OXFORD
Report by
Director of Environmental Services
Introduction
- As part of the
Oxford Schools Reorganisation and to cater for the needs of local development
the First School will transfer to a Primary School on a site north of
Aristotle Lane. Planning consent for a 14 class primary school, in Navigation
Way, was granted in June 2001. The consent included conditions, as set
out in Annex 1, that
required various traffic management arrangements to be implemented before
the school could be occupied. This report outlines the informal consultation
undertaken to date on possible traffic management measures and proposes
a preferred option for formal consultation and implementation.
- The new school,
which is required to open in October 2002 will initially be limited
to accommodate a maximum of 180 children until such time as the proposed
spine road from Woodstock Road becomes available.
Development
of Proposals and Consultation with SS Philip and James
- The County Council’s
Engineering Consultant, Babtie, produced an initial design that took
into account planning conditions set out in
Annex 1,. That design provided
two rising bollards in Aristotle Lane, at its junction with Kingston
Road, to control access into Aristotle Lane during school arrival and
departure times. This option was discussed at a meeting in March 2002
with the Buildings Sub-Group of SS Philip and James Governors.
- The Group expressed
some concerns about the proposals and made suggestions that they considered
should be explored to improve the safety of children accessing Aristotle
Lane and crossing the bridge. These suggestions included an alternative
location for the rising bollards. The Governing Body’s concerns are
set out in Annex 2 together
with officer comments made at the time.
- Following that
meeting some changes were made to the initial design and another meeting
held with the Buildings Sub-Group in May 2002. Concerns were again expressed
about the safety of children (walking and cycling) mixing with motor
traffic on the bridge. Officers consider that this cannot be totally
avoided without closing the bridge, which is not possible, as it is
the only exit from a housing estate. The issue of whether the restriction
point should be in Aristotle Lane or in Kingston Road was once again
raised. Officers agreed to look at this again and if a solution could
be found to remove the possibility of vehicles trying to turn round
within the immediate vicinity of the restriction point to include this
in a subsequent informal consultation.
Options
for Consultation
- Consultation has
been undertaken on two options for restricting access into Aristotle
Lane. Option 1 provides a restriction point in Aristotle Lane, at its
junction with Kingston Road. Option 2 provides a restriction point between
Aristotle Lane and Polstead Road. These are shown in Annex 3, which
is the consultation leaflet delivered to properties in the immediate
area and directly affected by the proposals. Also shown in the leaflet
is proposed traffic calming in surrounding roads.
- The suggestion
that the restriction point be located in Kingston Road between Aristotle
Lane and Polstead Road was reviewed. The problem of parents setting
down their children at the restriction point and carrying out a three
point turn can be overcome by restricting motor vehicle access into
Kingston Road, at its junction with St. Margaret’s Road, ie a restriction
on northbound movements. The provision of this additional constraint
means that any parent that still wishes to set down their child near
to the restriction in Kingston Road will have to approach it via Polstead
Road and then turn southward, thereby removing the need to carry out
a three point turn.
Results
of Consultation
- The consultation
leaflet, Annex 3, was delivered to approximately 250 properties on 14
June. Over 200 leaflets were also distributed via SS Philip and James
School to parents. A meeting with representatives of residents’ association,
in the area, was held on 25 June.
- At the time of
writing this report 28 individuals/organisation had responded. Their
comments are summarised in Annex 4.
Copies of the original letters/e-mails have been placed in the Members’
Resource Centre.
- The majority of
those commenting preferred Option 1. However, many of those who did
prefer this option raised concerns about the safety of pedestrians and
cyclists who will be using the bridge and mixing with motor traffic.
Those concerns have now been addressed in revised proposals.
Revised
Proposals
- Revised proposals
for controlling access into Aristotle Lane and traffic management in
the surrounding roads are shown on plan Nos BPN823/F3262 and BPN823/B3200.
Copies of the plan have been placed in the Members’ Resource Centre
and will also be on display at the meeting.
- Changes that have
been incorporated include additional traffic calming in Aristotle Lane,
either side of the bridge, traffic calming in Navigation Way and provision
of a footway linking the footpath from the recreation ground to the
school site (although this will be dependent on the purchase or dedication
of land). It is also recommended that an additional School Crossing
Patrol be provided at the Kingston Road/Polstead Road junction to assist
children to cross these roads.
Other
Issues
- The school is
expected to be completed in October. The school have indicated that
they wish to occupy the new site as soon as possible.
- To ensure that
the traffic management measures are in place for the opening of the
school, it will be necessary to order the rising bollard equipment before
results of the further consultation are known. By ordering the equipment
early, before the end of July, there is a risk that the comments received
from the formal consultation will be such that the proposals are not
proceeded with. The rising bollard equipment, which is estimated at
£45,000, would then need to be stored for possible use at a future site.
Financial
and Staff Implications
- The staffing implications
can be met from existing resources. The measures are to be funded from
the Oxford School Reorganisation Programme. The cost of an additional
School Crossing Patrol can be met from existing budgetary provision.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- agree
to formal consultation being undertaken on the revised proposals
shown on plan nos BPN823/F3262 and BPN823/B3200 and to authorise
the Director of Environmental Services, in consultation with
the Executive Members for the Transport and Strategic Planning
& Waste Management and Local Member(s), to implement the
measures subject to the consideration of any representations
or objections resulting from the consultation;
- authorise
officers to order the rising bollard equipment in advance of
the formal consultation;
- agree
to the provision of an additional School Crossing Patrol.
DAVID
YOUNG
Director of
Environmental Services
Background
papers: Letter of comment on file number 12.6.320
Contact
Officer: John Cramer Tel: Oxford 815963
18
July 2002
|