The works under the Engineering and Construction Short Contract have commenced. The Parent Company guarantees the performance of such works.
Decision Maker: Director of Environment & Highways
Decision published: 09/06/2026
Effective from: 02/06/2026
Decision:
To seal and
complete the Parent Company Guarantee between (1) OCC and (2) John
Graham Holdings Limited relating to the Stage One NEC4 Engineering and
Construction Short Contract for the pre-order of steel for the Didcot to Culham
River Crossing scheme.
Lead officer: Lynsey Turner
Enables the Trust to drawdown funding to progress with the next stage of the project as detailed in the Outline Business Case.
Decision Maker: Director of Property & Assets
Decision published: 02/06/2026
Effective from: 28/05/2026
Decision:
To enter
into an initial funding agreement to provide funding to Oxford Diocesan Schools
Trust in the sum of £0.760m to progress with the detailed design development
and planning permission for the relocation and expansion of Brize Norton
Primary School to the new school site at East Carterton.
Significant Change to expand and relocate the school has been received from the Department for Education.
Lead officer: Deborah Wyatt
Decision Maker: Performance & Corporate Services Overview & Scrutiny Committee
Made at meeting: 17/04/2026 - Performance & Corporate Services Overview & Scrutiny Committee
Decision published: 02/06/2026
Effective from: 17/04/2026
Decision:
Apologies were received from the following:
- Cllr Boucher-Giles
- Cllr Ley (for whom Cllr Batstone was substituting)
A proposal to approve the Housing Infrastructure Fund (HIF2) – A40 Eynsham to Wolvercote construction contract.
Decision Maker: Delegated Decisions by Cabinet Member for Highway Construction and Repair
Made at meeting: 01/06/2026 - Delegated Decisions by Cabinet Member for Highway Construction and Repair
Decision published: 01/06/2026
Effective from: 05/06/2026
Lead officer: Mohammed Ilyas, Yousuf Javed
Decision Maker: Delegated Decisions by Cabinet Member for Resources and Deputy Leader
Made at meeting: 19/05/2026 - Delegated Decisions by Cabinet Member for Resources and Deputy Leader
Decision published: 21/05/2026
Effective from: 19/05/2026
Decision:
None.
Decision Maker: Delegated Decisions by Cabinet Member for Resources and Deputy Leader
Made at meeting: 19/05/2026 - Delegated Decisions by Cabinet Member for Resources and Deputy Leader
Decision published: 21/05/2026
Effective from: 19/05/2026
Decision:
None.
Decision Maker: Delegated Decisions by Cabinet Member for Resources and Deputy Leader
Made at meeting: 19/05/2026 - Delegated Decisions by Cabinet Member for Resources and Deputy Leader
Decision published: 21/05/2026
Effective from: 19/05/2026
Decision:
None.
This is a request to extend our support and maintenance contract for 3 years with an option to extend for a further 2 years
Decision Maker: Delegated Decisions by Cabinet Member for Resources and Deputy Leader
Made at meeting: 19/05/2026 - Delegated Decisions by Cabinet Member for Resources and Deputy Leader
Decision published: 21/05/2026
Effective from: 19/05/2026
Decision:
Decisions approved.
Lead officer: Alastair Read
To seek agreement of proposed allocation split of rolled over flood risk management funding £1.39m
Decision Maker: Delegated Decisions by Leader of the Council
Made at meeting: 21/05/2026 - Delegated Decisions by Leader of the Council
Decision published: 21/05/2026
Effective from: 28/05/2026
Lead officer: Clare Mills
The bus stops, 3m shared footway/cycleway and the two signalised crossing is maintaining pedestrian and cyclist safety. The highway improvement will help future and current residents to safely gain access to the existing and proposed footway/cycleway on either side of Bicester Road and the amenities in the area.
Decision Maker: Delegated Decisions by Leader of the Council
Made at meeting: 21/05/2026 - Delegated Decisions by Leader of the Council
Decision published: 21/05/2026
Effective from: 28/05/2026
Lead officer: Angelo Antenucci
Option assessment
and feasibility advice on the
western section of SEPR. Also a greater
understanding of the scope, benefits and cost of A41 corridor complementary
works (to provide walking, cycling and bus prioritisation infrastructure).
Decision Maker: Head of Place Shaping
Decision published: 21/05/2026
Effective from: 13/05/2026
Decision:
To enter
into consultancy contract
-
SEPR
and A41 Corridor Improvement Study
-
Aecom
Limited
-
£144,350
& £15,000 for contingency and compensation events (exc. VAT)
Lead officer: Richard Humble
To continue
provision of support for Ukrainians, both newly arrived and those who have been
here for over 4 years (since the start of the war in Ukraine in February 2022).
Decision Maker: Director of Public Health & Communities
Decision published: 21/05/2026
Effective from: 20/05/2026
Decision:
To directly
award a 12-month contract to Connection Support to continue to deliver the
Homes for Ukraine Wraparound Support Service at a value of £239,000 with an
option to extend for 12 months with a total overall value of £439,000.
Lead officer: Elaine Swapp
An extension of the date for the completion of Oxpens bridge set out in the collaboration agreement to 31st March 2027.
Decision Maker: Deputy Chief Executive (Section 151 Officer)
Decision published: 21/05/2026
Effective from: 14/05/2026
Decision:
Approval of
a Variation Agreement between Oxfordshire County Council and Oxford City
Council for the designs and construction of a new pedestrian and cycle bridge
over the river Thames and its onward connections at Oxpens, Oxford. The agreement is a second variation to a
collaboration agreement between the authorities related to the design and
delivery of the bridge which is being led by Oxford city council. The variation to the agreement has no
financial implication.
Lead officer: Rob Freshwater