Approval to proceed with the Cloud Migration Programme
with a total capital budget of £1,100,000, as outlined in the Initial Business
Case submitted. Fully funded from an earmarked capital
reserves approved by Cabinet in February 2025 (£150,000) and February 2026
(£950,000).
Ongoing revenue costs for migrated systems will remain with the original system
owner.
The cost of
each migration will be confirmed through supplier quotes, for approval by the
Cloud Migration Programme Board.