Report by Deputy Director for Environment & Economy (Strategy & Infrastructure Planning) (PN6)
This application is to continue the development of a
permitted recycling facility at Sutton Courtenay landfill site, with changes to
a number of conditions. The changes would allow the Materials Recycling
Facility (MRF) to operate until 2030, in line with the life of the adjacent
landfill site. The current permission for the MRF runs to 2019. The changes
proposed would also allow the building to process 200,000 tonnes of waste per
year rather than 70,000 allowing a higher proportion of the waste imported to
the landfill site to be processed through the MRF.
Changes are proposed to the elevations of the building. No
changes are proposed to the footprint, height or dimensions.
The application is being reported to this Committee as there
have been objections from local residents.
The report sets out the proposals and outlines the
objections and other responses to the application. Relevant planning policies are included along
with the comments and recommendation of the Deputy Director (Strategy and
Infrastructure Planning) on the proposal.
The report concludes that the changes proposed to the
condition are in accordance with waste planning policy allowing for the proportion
of waste diverted from landfill to be maximised as the operational life of the
MRF would match the landfill and for a higher proportion of the waste to the
landfill would be permitted to be treated in the MRF. There would be no
significant impacts on the environment as a result of the proposed changes.
It is RECOMMENDED
that Application MW.0174/12 be approved subject to conditions attached to the original consent
(APF/616/57-CM) but amended specifically
in respect of conditions 1, 3 and 22 as detailed at Annex 3 to this report and
to further updating of conditions 15, 16, 18, 19, 20 and 21 by the Deputy
Director for Environment & Economy (Strategy & Infrastructure Planning)
to reflect that schemes have now been approved and must be implemented.
Minutes:
The Committee considered (PN6) an application to continue development of a permitted recycling facility at Sutton Courtenay landfill site but with changes to a number of conditions to allow the materials recycling facility to operate until 2030 in line with the life of the adjacent landfill site and process 200,000 tonnes of waste per year and for changes to the elevations of the building, although no changes were being proposed to the footprint, height or dimensions.
Mr Lerner responded to concerns which had been expressed regarding the appropriateness of a Section 73 application in this case. His statement had been circulated with the tabled addenda.
Mark Baker considered the
application flawed. Firstly it had
originally presented proposals for the Ardley bulk
transfer contract but was now dealing with proposals for increased throughput
for sorting landfill waste, an entirely unrelated and undisclosed activity and
one which had offered local people and consultees no
proper opportunity to comment. It had
not therefore followed due process. The
application was procedurally invalid as Section 73 could not be used to approve
new development and should be considered again as a full planning application,
which provided a real basis and case to approve an increased throughput and
life of the facility. He considered planning officers had put forward totally
different justifications for these two major components and asked the Committee to decline to consider the application as presented as
the applicant had made no case at all for the first element and an invalidated
case for the second. Section 73 was not
an appropriate means for dealing with such contentious matters and a planning
application was needed which explained comprehensively proposals for trebling throughput
and which put the life extension into the full context of the life of the site
itself.
Robin Draper
also considered this a faulty application and one which should not have been
considered under Section 73. He referred
to a detailed list of 8 applications submitted at this site over the past two
years which in his view represented planning creep. Setting out material changes for an 18 year
extension and a trebling of throughput warranted a new application. In May agreement had been given for a 70,000
tonne throughput for the MRF facility which FCC had accepted. They were now building a larger plant and
were in breach of the May permission.
There was no basis to grant an extension of time in this way and the
Committee should not approve it. The
Company had shown complete disdain for conditions. He also advised that the local County
Councillor opposed the application.
Nicola
Simonson spoke as a local resident and environmental consultant. With particular concerns regarding the
extension of time. She considered this
constituted a permanent facility in the countryside and not a temporary
one. The site was still classified as
Greenfield, which is why previous schemes such as the MBT facility had been
rejected. The application was contrary to
policies NE9, 10 and 11 in the local plan which sought to prevent development
with impact on views and the site itself was particularly sensitive especially
with the imminent closure and demolition of Didcot
power station, which offered a unique opportunity to reclaim the lowland vale.
Allowing this application represented a retrograde step.
Nick Hards referred to the significant visual impact this
facility would have on planned housing development in Didcot.
Traffic levels, which were set to increase dramatically as a result of that
development, would not be helped by this proposal and it seemed
incomprehensible with that development as a backdrop to be now seeking to
increase operations together with an extension of time for the facility
particularly when, at the May meeting of the Planning & Regulation
Committee, the applicants had been content with the original proposal and yet
here they were months later and despite assurances given at that meeting
seeking significant changes to that proposal.
Dr Angela
Jones endorsed all the comments made by the previous speakers and referred to
the despair felt by Appleford Parish Council
regarding this application. She had said
in May that there were likely to be changes made and sure enough that had happened.
The Parish Council felt bullied by FCC and the Committee should support
local concerns and refuse the application.
The Chairman
referred to an email which he had received from Councillor Stewart Lilly who
had asked that the Committee seriously consider refusing the application.
Oxfordshire county council were currently taking enforcement action against FCC
at Sutton Courtenay for other planning conditions that were not only being
ignored but totally flouted and it would be sheer folly to grant yet another conditional
approval if they continued to ignore existing conditions already imposed on
them.
Mike Graham
on behalf of the applicants advised that FCC had addressed the level of criticism levelled at them in
May by establishing a dedicated team to deal with these issues which had
included a full and comprehensive list of every application required in order
to complete the landfill operation by 2030.
He advised that the company were seeking confirmation whether or not Ardley were able to accept treated waste. With regard to throughput he confirmed that
they were not asking for a single additional tonne to be imported but would
only be dealing with waste which was already coming to the site and were
looking to treat waste in order to recover and divert recyclables from landfill
and there would be no transport impact as there would be no additional waste
being brought in. The company were
seeking to tie the MRF operation into the life of the landfill. Waste disposal needed a strategy in order to
get waste away from landfill but needed to get waste into the site in order to
meet the end date and then restoration. Hoever, if the MRF facility was decommissioned in 2019 then
the Company would need to use recyclables to fill the site which was not
possible under EU regulations. They were
not looking to increase the size of the building and confirmed that the site
was in fact brownfield (under the National Policy
Planning Framework) and would only revert to greenfield
status after 2030. The landscape would
be reclaimed by 2036. Some areas had already been restored and the company was
doing its utmost to get the site completed but by its very nature waste would
be always be a contentious issue. The company took cognisance of local concerns
but in their view this was what was required to meet the completion date for
landfill.
Mr Graham
then responded to questions from:
Councillor
Tanner – waste import was currently split between rail (350,000 tonnes) and
road (250,000 tonnes) with treated waste coming from road imports.
Councillor
Greene – rail imports would continue to 2030.
With regard to the comments by Councillor Lilly concerning enforcement
there had been breach of a pre-commencement condition which had arisen as the company
had been told that all responses had been submitted. However, there had been a delay of two weeks
getting a written response from the Environment Agency although they had been
told verbally that all was well. In
these cases it was normal practice to proceed on that basis but due to the
sensitivity of the Sutton Courtenay site and with hindsight that had been
ill. However he did not regard that as
flouting and indeed following comments made at the May meeting the company were
trying to improve liaison.
Councillor Hallchurch – he confirmed that there would be no increase
in traffic as waste to be treated would come from levels currently imported
into the site. He referred to the
clarification of throughput documentation which he had tabled which illustrated
that the current level was 70,000 tonnes but more could be processed and the
hope that 60,000 tonnes could be diverted to Ardley
as treated waste rather than build a waste transfer station.
Councillor Hannaby – the company did keep records and in May the
Company had asked for capacity not to be conditioned to 70,000 tonnes as they
felt more could be achieved.
Ms Thompson
drew the Committee’s attention to the tabled addenda sheet which set out
comments from the Vale of White Horse District Council and a revised Annex 3. If approved this permission would not cover
the waste transfer or clinical waste elements and therefore the information
regarding traffic levels associated with those elements as set out in paragraph
18 did not apply to this application.
Responding
to:
Councillor Armitage - she confirmed that any permission for this
application would not include clinical waste.
Councillor
Tanner – the original application had proposed the life of the MRF to 2019
which had tied in with the lifetime of the landfill operation at that
time. However, that had been amended to
2030 with restoration in 2036 when the the site would
revert to greenfield status.
Councillor
Greene – the report dealt with the environmental impact of the facility.
Councillor Hannaby supported the aims of recycling but had sympathy
for the plight of local residents. It had came as no surprise to her that
having granted an extension of time for the landfill FCC were now seeking a
similar extension for the MRF facility.
Councillor
Fitzgerald-O’Connor felt that having weighed the impact of the development
against the desirable aims of recycling the application should be approved and
she so moved. Councillor Nimmo-Smith seconding.
Councillor
Reynolds considered that as import levels were not set to increase there seemed
to be no real planning reason to refuse.
Councillor Armitage however felt that the application went against
local plan policies and it was not appropriate to say that good recycling
should overweigh those policies.
Councillor
Tanner agreed and felt MRFs encouraged landfill which
we should be looking to reduce. He could
see little justification to allow this proposal which if approved would
continue to be blot on the landscape.
The motion
was put to the Committee and –
RESOLVED: (by 8 votes to 3, Councillor Greene and Councillor Hannaby
recorded as having abstained) that Application MW.0174/12 be approved subject to
conditions attached to the original
consent (APF/616/57-CM) but amended
specifically in respect of conditions 1, 3 and 22 as detailed in the revised
Annex 3 as attached to the addenda sheet and tabled at the meeting and to
further updating of conditions 15, 16, 18, 19, 20 and 21 by the Deputy Director
for Environment & Economy (Strategy & Infrastructure Planning) to
reflect that schemes had now been approved and must be implemented.
Supporting documents: