Report by the Deputy Director for Environment & Economy (Strategy & Infrastructure Planning) (PN7)
This report
describes an application to allow part of the MRF building to be used for waste
transfer operations. Waste collected from households would be brought to the
building and transferred onto larger vehicles for transport to the Energy from
Waste facility at Ardley. The building would also
accept clinical waste and have some capacity for commercial and industrial
waste.
The consultation responses and third party
representations received are outlined in the report along with the relevant
development plan policy implications and the views of the Deputy Director of
Environment and Economy (Strategy and Infrastructure Planning) who recommends that
the application be approved as the proposed development is in accordance with
relevant planning policy relating to waste management and protection of
amenity.
It is RECOMMENDED that subject to:
i)
a Section 106 agreement to ensure that waste
imports to the waste transfer operation are only from within the catchment area
(Oxfordshire, West Berkshire, Reading, Wokingham and Bracknell) secured by the
Section 106 agreement dated 4 November 2008 for the landfill site and that the
total waste import to the MRF and WTS building is 200 000tpa and this is part
of and not additional to the 600,000 tpa limit on the
landfill; and
ii)
a routeing agreement to ensure that vehicles
associated with the development are routed via the A4130 and A34 as for other
developments on the site,
application
MW.0136/13 be approved subject to conditions to be determined by the Deputy
Director (Strategy and Infrastructure Planning) but in accordance with those
set out at Annex 3 to the report.
Minutes:
The Committee considered (PN7) an application to allow part of the MRF building at the Sutton Courtenay waste management centre to be used for waste transfer operations. The Committee also noted 2 late representations which had been set out in the tabled addenda. The application had been refused at the September meeting but then modified to overcome the objections raised and resubmitted.
Sally Furze reiterated her previous objections from the September meeting still stood. There were no visible signs of flood prevention work. Bunds at the site were higher and yet there was still light spillage. Smells were horrendous and it remained an example of planning creep. She could not accept that waste being brought in to the site in small vehicles and then loaded onto bigger vehicles to be transported away again was sustainable or efficient.
Robin Draper
supported the Committee’s previous decision to refuse permission which had been
based on a step to far and on flawed statistics in a Minerals and Waste Strategy
which was having to be rewritten as a result.
He hoped the Committee would sustain that view. It was true the amended
version was a considerable improvement but it left questions unanswered as to
future applications. It was imperative that the 2030 end date was treated as
definitive and honoured by both FCC and Oxfordshire County Council,
particularly in view of FCCs record of layering
planning application on application and extending its activities and the landfill site end date from 2012 to 2021
and now currently to 2030. This application was for a change of usage to meet
an OCC contract and permission should therefore be restricted to meeting the
terms of that contract from within the county and not from imports from across
the so called catchment area. To allow that could only increase pressure for
further applications. He considered the recommendation weak and that it should
specifically refer to the Waste Transfer Facility and the 50,00tpa and
10,000limits, reinforcement of the 2030 deadline and minimising the risks of FCC expanding the
envelope of its activities further by deleting reference to the catchment area,
and restricting its activities to transferring Oxfordshire’s waste. He also suggested that conditions should be
determined by the Chairman of the Planning Committee in conjunction with the
Deputy Director. Clinical waste breached the non-hazardous waste status of the
landfill site, which had been robustly defended in the past. That should be
maintained and he could not accept the rationale for setting up a clinical
waste transfer site to facilitate just one vehicle in and one out a fortnight,
when that could go straight to the Maidenhead facility, unless the intention
was to build on that by seeking to import more clinical waste in future. To
protect the local community no extension of the hours of work to Bank holidays
should be permitted although the increase of hours on Saturdays following a
Bank holiday seemed reasonable. He urged that the application be rejected or at
least deferred until the County Council had agreed a Minerals and Waste
Strategy. However, if the Committee were minded to approve then any decision
should clearly state that the waste transfer facility was only permitted until
the end of 2030, be dismantled by 31 December of that year; restricted to the
transfer of the 50,000tpa arising from the Oxfordshire contract and to
10,000tpa of C&I from within the county only. He also urged refusal for the
importation of clinical waste as it breached the non hazardous waste status of
the landfill site and finally that no working should be allowed on any Bank
holidays.
Mark Baker
welcomed the decision taken in September and the recommitment to the 2030 end
date. However, that date fell well short of the end date of the 25 year waste
contract awarded by the County Council which ended in 2035. Any further
application to extend the end date at Sutton Courtenay should be strongly
resisted and any such application needed to demonstrate a strong and clear
specific need in accordance with paragraph 37 of the officer’s report and
county policies. A clear system of review needed to be arrived at to monitor
the situation in the future.
Responding
to a question from Councillor Lilly Mr Baker stated that there were alternative
sites available for FCC to set up operations.
Dr Angela
Jones stated that continual extensions to the end date for operations at this
site had taken working from 2012 to 2030 and local people felt that nothing had
really changed. That needed to be met
head on and working on bank holidays resisted. She considered acceptance of
clinical waste to tbe the thin end of the wedge and
that part of the application should be resisted.
Colin
Woodward also considered the transfer operation of waste an additional and
unnecessary operation. He was concerned
that no specific firm limit had been placed on future expansion at this
site. There would be an immense impact
on local roads around the site and flies, dust, litter and odour continued to
be a real nuisance. 47 complaints had
been made of which only 2 had been non compliance. The remainder had been
unsubstantiated, that was not acceptable.
Paul Marsh
for the applicants confirmed that this was a resubmission of the application
refused in September the Company having reviewed the reasons for refusal given
at that time namely perceived impact on roads and local residents. He stated
that the tonnage of waste into the facility was part of the existing volume of
waste currently going into the site, there would be no additional waste. There had been no highway objections to the
revised application. The MRF building
had consent to handle 200,000 tonnes and the operation would be absorbed within
the existing contract with no increased activity or intensification. Noise
remained within acceptable limits and similarly dust and odour did not exceed
permitted levels. There had been shown to be an identified need in order to
maintain a level of sustainability. He
reiterated the Company’s commitment to removing the building in 2030 and
restoring the land and they were not seeking to amend that.
Mr Marsh
then responded to questions from:
Councillor
Bartholomew – the company were surrendering some capacity at the site.
Councillor
Tanner – it was a requirement of the contract to include an element for clinical
waste.
Councillor
Cherry – the operation was not expected to have any impact on current drainage
issues regarding surface water drainage which were currently being
investigated.
Councillor
Lilly – the Company were not currently looking at an alternative site for post
2031. He reiterated the Company’s intention to cease operations in 2030.
Councillor
Handley – when not in use the doors into the building would remain closed.
Additionally clinical waste would not necessarily go to Ardley
as there were other sites available.
Councillor Fulljames – regarding the discrepancy between the contract
length and this life of this site the contract was not site specific.
Councillor
Richard Webber spoke as local member. He thanked those members of the Committee
who had visited the site. Even though
FCC had in fact addressed many of the issues raised at the September meeting
there had still been 64 objections to this resubmission and a lot of local
concern remained and as local member it was for him to see how that could be
taken forward. There were 4 issues:
·
Completion date which needed to be quoted in all
notices.
·
Catchment area – there was a feeling of ambiguity
regarding the phrase service to Oxfordshire and unease that that area could be
extended.
·
Clinical waste – he could not understand the
justification for this with marginal benefits when compared to potential
risks. Again there was concern this
could be extended and specific limits should be imposed now.
·
Hours of working – extended hours should be
refused.
On the basis
that these four issues above could be addressed and where necessary written
into decision notices he felt progress could be made.
Responding
to Councillor Greene Ms Thompson confirmed that Condition 3 covered the closing
date of the operation. However, there
was no justification in planning terms to stop bank holiday working and limit
it to when refuse was collected by the relevant district councils.
Responding
to Councillor Lilly Mrs Crouch confirmed that a closing date could be embodied
in a S106 agreement but could be amended after 5 years. In this instance a condition would fulfil the
same purpose.
A motion by
Councillor Tanner to approve the application but excluding the element for
clinical waste was not seconded.
Mr Periam confirmed that the two elements could not be
considered separately and the only alternative would be to refuse the whole
application.
Councillor
Owen, Councillor Lilly and Councillor Bartholomew had no real concerns
regarding clinical waste which they considered would be controlled and well
monitored.
Councillor
Greene then moved that application MW.0136/13 be approved but with an amendment
to the hours of operation to restrict bank holiday working to those when
district councils were making collections. Councillor Phillips seconding.
Councillor
Greene with the permission of his seconder accepted
an amendment by Councillor Mrs Fulljames to amend the
routeing agreement to ensure vehicles were routed to Ardley
via the A4130 and A34 and M40 (junction 10 only).
Councillor
Mrs Fulljames also expressed concern regarding the
discrepancy between the completion date for this site at 2030 and the end of
the Ardley permission date of 2035 and also the need
to prevent waste from outside Oxfordshire travelling through the county.
The motion
as amended was then put to the Committee and –
RESOLVED: (9 votes to 0,1 abstention recorded) that
subject to:
i)
a Section 106 agreement to ensure that waste imports to the waste
transfer operation are only from within the catchment area (Oxfordshire, West
Berkshire, Reading, Wokingham and Bracknell) secured by the Section 106
agreement dated 4 November 2008 for the landfill site and that the total waste
import to the MRF and WTS building is 200 000tpa and this is part of and not
additional to the 600,000 tpa limit on the landfill;
and
ii)
a routeing agreement to ensure that vehicles associated with the
development are routed via the A4130 and A34 and M40 (Junction 10 only) as
for other developments on the site;
application MW.0136/13 be approved subject to conditions to be
determined by the Deputy Director for Environment & Economy (Strategy &
Infrastructure Planning) but in accordance with those set out at Annex 3 to the
report PN7 and that hours of working as set out in that Annex be amended to
restrict bank holiday working to reflect those days when District Councils made
refuse collections.
Supporting documents: