Issue history
A423 Kennington Improvement Programme - Contracts and Agreements
- 01/08/2023 - Published in plan, August to November 2023
- 11/08/2023 - Decision due date for Delegated Decisions by Cabinet Member for Travel & Development Strategy changed from 07/09/2023 to 12/10/2023. Reason: further work required.
- 01/09/2023 - Published in plan, September to December 2023
- 26/09/2023 - Decision due date for Delegated Decisions by Cabinet Member for Travel & Development Strategy changed from 12/10/2023 to 14/12/2023. Reason: further work required.
- 01/10/2023 - Published in plan, October 2023 to January 2024
- 01/11/2023 - Published in plan, November 2023 to February 2024
- 14/11/2023 - Decision due date for Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy changed from 14/12/2023 to 21/03/2024. Reason: Further work required
- 01/01/2024 - Published in plan, January 2024 to April 2024
- 01/02/2024 - Published in plan, February 2024 to May 2024
- 15/02/2024 - Decision due date for Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy changed from 21/03/2024 to 18/07/2024. Reason: Further work required
- 01/03/2024 - Published in plan, March to June 2024
- 29/05/2024 - Decision due date for Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy changed from 18/07/2024 to 05/09/2024. Reason: Further work required
- 01/07/2024 - Published in plan, August to November 2024
- 19/07/2024 - Decision due date for Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy changed from 05/09/2024 to 23/01/2025. Reason: Further work required
- 01/09/2024 - Published in plan, September to December 2024
- 23/01/2025 - Agenda item scheduled, Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy