Meeting documents

Delegated Decisions by Cabinet Member for Schools Improvement
Tuesday, 31 July 2007

 

 

Return to Items for Decision

ITEM CMDSI2

 

CABINET MEMBER FOR SCHOOLS IMPROVEMENT – 31 JULY 2007

 

SCHOOL ORGANISATION PROPOSALS TO EXTEND THE AGE RANGE OF LAUNTON , BURFORD AND CHARLTON-ON-OTMOOR PRIMARY SCHOOLS FROM 4 - 11 TO 3 - 11 BY ADDITION OF A NURSERY CLASS

 

Report by Strategic Manager (Property & Assets), Strategy and Performance

 

Introduction

 

1.                  These statutory proposals are to be considered under the transitional arrangements brought about by the Education & Inspections Act 2006. All three proposals involve the extension of the age range of the school from 4 - 11 to 3 - 11 with the opening of a nursery class at the schools. The notices (attached as an Annex) were published before 31 May 2007 and were therefore in the format in force at the time. Because School Organisation Committee s (SOCs) were abolished on 31 May 2007 all proposals, whether published under the old regulations or not, need to be considered under the new arrangements, i.e. with the County Council as decision-maker.  Two of the proposals are from Voluntary Controlled schools and the Governors are the proposers; the third, Burford, is a community school and the local authority is the proposer. The notices were published in the week beginning 14 May 2007 and the statutory period expired at the end of June. In each case no formal objections were received.

(Annex 1 - Copy of Newspaper advert for Burford Primary School - download as .pdf file)

(Annex 2 - Copy of Newspaper Advert for Charlton-on-Otmoor Primary School CE(C) - download as .pdf file)

(Annex 3 - Copy of Newspaper advert for Launton CE Primary School - download as .pdf file)

 

Background

 

2.                  A report was approved by the Cabinet Member for Schools Improvement to support the publication of statutory notices for Burford Primary School and Charlton-on-Otmoor C of E Primary School.  The proposals for Launton C of E Primary School are a re-publication of proposals considered by the SOC last year but rejected as there was no evidence of appropriate consultation having taken place.

 

Decision making process

 

3.                  Decision makers are required to have regard to the appropriate guidance. In this case the guidance in operation prior to 31 May 2007 . This requires the following to be considered:

 

    • The legality of the notices
    • Understand the objectives of the proposal
    • Be satisfied that appropriate consultation has taken place
    • Details on admission numbers of the school and schools within 2 miles, capacity, number on roll and forecasts
    • Details of Ofsted reports from last 3 years
    • Premises and planning implications
    • The type of provision to be provided

 

4.                  The proportion of children under compulsory school age in the area of the local education authority who are educated at schools maintained by the local education authority is approximately 48%, averaged over the school year.

 

5.                  The proportion of children who are educated at schools not maintained by the local education authority is approximately 44%, averaged over the school year.

 

Burford Primary School

 

6.                  The proposal is to open a nursery class for 15 x 4-year olds and 15 x 3-year olds some of whom will attend part time. If there is sufficient interest the school will look into the viability of offering ‘wrap around’ care.  The current number of children on the roll is 75.  The admission number for the school is 15, however, since 2004, the actual number of children applying for a place each year has been lower: between four and ten.  The school came out of the Ofsted category of Special Measures in July 2005 which had identified underachievement in the Early Years.  The school believes that its progress in addressing the weaknesses will be reflected in higher numbers of parents requesting a place at the school in the future and that admitting younger children will also boost their popularity. At the present time there are likely to be 17 x 4-year old children starting at the school in September 2007.

 

7.                  The report carried out by the Senior Advisory Teacher is positive and recognizes the benefits of the current Head Teacher’s Early Years expertise.  An extra teacher would need to be employed to job share with the Head Teacher in this new class.  The premises report indicates that the school has sufficient capital funding to develop the proposed alterations to the accommodation which will then meet the space requirements for both indoors and outdoors for the anticipated number of Foundation Stage children; there will also be sufficient toilet provision.  This report raises concerns over the sustainability of this venture.  Whilst the Head Teacher feels the school is well placed to expand there is a risk that if this does not happen, the budget will not support this proposal.

 

8.                  The school is demonstrating a gradual trend in growing numbers since coming out of special measures in July 2005; however there is currently no surplus budget available to accommodate any variations in the plans put forward for this new nursery class.  The plan relies on the predicted pupil numbers put forward in the proposal that may be optimistic based on the past few years.  The local pre-school is not full either.  The proposed budget allows for a basic grade teacher with a maximum of three years experience and would require the Head Teacher to teach two days a week in the nursery class, as well as covering teacher absence in the school.   The finance officer has, therefore, concluded that this proposal could put the school in a financially vulnerable position.

 

9.                  The school held a consultation evening, sent out letters to local providers and held a meeting for parents.  The local pre-school, which has operated for over 40 years and developed its provision, has attended all meetings and sent a written response to the school and the local authority raising objections.  The pre-school suggests that this development would put them seriously at risk of closure because it would directly compete for the same children.  It currently offers places for children younger than 3 years so this service for parents could be lost.  The pre-school received a good Ofsted report and operates in its own building up the hill from the primary school.  It states it would like to develop a stronger partnership with the school and build good links which would be of benefit to both children and parents.

 

10.             Taking into account the uncertainty of pupil numbers and, therefore, the delicate financial position of the school, together with the concerns raised by the pre-school, there is a risk that the school will struggle to be able to maintain this provision.  However, the Head Teacher has worked very hard to bring the school out of Special Measures and in so doing, she has been successful in raising standards of teaching and learning and, as a consequence, attracting families back to the school.  The Head Teacher and Governors are committed to making this project a success and further developing its potential.  Following a series of meetings with the playgroup those objections have been withdrawn and the 2 are planning to work in partnership.

 

11.             The current capacity is 60 pupils, with one spare classroom; 90, including the spare classroom (excluding F1 areas); 105 including F1.  However, the school has carried out a major internal remodel, and the spare classroom will be in use and a larger, more suitable area will be available for F1 and F2 pupils.  There are no other planning issues. The number on the roll is 76 including F1 pupils.  There are no other schools within a 2 mile radius.

 

12.             Forecast pupils numbers for the next five years are stable.  Assuming the proposals are approved, the school would rise to 8 year groups, without affecting the capacity of the school as F2 pupils would share the same accommodation as F1 pupils, where there are currently surplus places.  The admission arrangements for F2 children will be handled by the school direct.  The admission arrangements for F1 children will be handled by the County Council’s admissions team.  The Ofsted report in 2005 removed the school from special measures.

 

Charlton-on-Otmoor

 

13.             The proposal from this school is to admit younger children from the age of 3 years who are currently on the pre-school roll within the school building.  This situation has arisen because the pre-school has been unable to maintain a committee and the necessary staffing over the past year.  They are managing to keep the pre-school open but have asked the School Governors and Head Teacher to take over the responsibility from them from September 2007.  At the present time they operate as a Partnership Foundation Stage Unit and work together sharing staff and resources.  There are currently 26 children attending each of the two half day sessions.  The school has just lost its Foundation Stage teacher but will be recruiting for September.  The advisory teacher‘s report is positive and highlights good staffing ratios and facilities and a sound understanding of the needs of young children.  The school is well-placed to develop further.  The recent Ofsted concluded the Foundation Stage in the School is ‘good’.  The children will remain in the same room in which they are currently accommodated.  This space is of sufficient size to accommodate the number of children already there and this will remain the same. The outdoor garden is fenced and there is a covered area. There are sufficient toilets. Children attend for 2 ½ hours a day. There are no additional childcare arrangements.

 

14.             The School finance officer has confirmed that at the present time the School can afford to recruit support staff for the new class. The staff currently employed by the preschool will transfer to work in the school under T.U.P.E arrangements. The school already employs the Foundation Stage teacher.

 

15.             All the required consultations have been carried out and this indicated that there is complete support from the community, local providers and parents.

 

16.             The current capacity for the school is 90 and the number on roll is 77 and forecasts for the school remain stable. The admission number is 15. There are no other schools within 2 miles. The school was inspected in November 2006 and was deemed to be good.

 

Launton VC Primary school

 

17.              The  objective of the proposal is to continue to maintain current provision. A staggered entry to the school has always worked well. Most children are familiar with the school context prior to their F1 year. Parents, children and the community in general have been happy with this including other ‘early years’ providers. The current provision involves maintaining Foundation stage Unit for upto 24 pupils. The autumn born and spring born children come to the school for ½ days either morning or afternoon depending on numbers 2 terms before the term in which they are 5. The numbers are never above 30 in the FSU. The education provided will be consistent with integration of nursery education for this age of child. Children attend for 2 ½ hours a day. There are no additional childcare arrangements.

 

18.             The early years adviser initially met with the head teacher in October 2005 to set up a system of consultation between governors, parents and the local pre-school with wider consultation in September 2006 with positive comments received from a number of local schools and the local playgroup on site. As these proposals confirm the current position there will be no change to the operation of the playgroup at the present time.

 

19.             The following Primary schools are within 2 miles radius of the school. They mostly have early years facilities. The children attending Launton are mainly local and there is no impact on other schools as these proposals regularize a practice that has been in place for some time.

 

School

AN

Capacity

No on roll

Forecast

Brookside

45

240

195

Steady

Glory Farm

60

360

339

Slow decline

Langford Village

69

360

371

Slow decline

Longfields

40

180

179

Steady

St Mary’s

45

269

221

Steady

Southwold

60

356

 

Slow decline

St Edburg’s

30

145

145

Steady

 

20.             The school has an admission number of 27 a capacity of 115 and 95 on roll with 24 F1’s and 5 F2’s. The forecasts are stable. The school was inspected in May 2006 and was judged as satisfactory. The school is voluntary controlled but there are no planning or capital costs associated with these proposals.

 

RECOMMENDATION

 

21.             The Cabinet Member for School Improvement is RECOMMENDED to approve the statutory proposals extending the age range of Launton, Burford and Charlton-on-Otmoor Primary schools from 4 - 11 to 3 - 11 by the addition of a nursery class.

 

 

MICHAEL MILL

Strategic Manager (Property & Assets), Strategy and Performance Service

Children, Young People & Families

 

Background papers:            

 

Contact Officer:                     Michael Mill, Strategic Manager (Property & Assets), Strategy and Performance Service Tel: (01865) 816458

July 2007

Return to TOP