Return
to Items for Decision
Division(s): Didcot South
|
ITEM CMDSI3
DETAILED PROJECT APPRAISAL APPRAI9SAL
NO. ED 657
NAME OF
SCHEME: St Birinus School, Didcot
Provision of New Science
Block START YEAR: 2007/08
BASIS OF ESTIMATE: Mouchel Parkman cost estimate based on agreed
scheme developed with partnering contractor Mansell Construction
- INTRODUCTION AND DESCRIPTION
OF PROJECT
The Site Development Plan
(SDP) produced for St Birinus School seeks to identify the best way
of developing the agreed needs and aspirations of the County Council
and the school taking into account the following accommodation issues:
Suitability;
Condition;
Sufficiency (including
projected future growth within the area).
One outcome
of the SDP process was the need to make better use of the large campus
site shared by St Birinus Secondary School and Greenmere Primary School.
Phase 1 of implementing the SDP, the construction of a new primary
school to replace the Greenmere building, was approved by the full
Executive at its meeting 6 July 2004 (Project Appraisal ref ED615).
The primary school will be moving into their new building at Easter
2007, this will allow the vacated Greenmere buildings to be demolished
and the land released for development to meet the site and accommodation
needs of St Birinus School.
This project
appraisal is for phase 2 of implementing the SDP, the construction
of a new three storey 13-laboratory science facility for St Birinus
School on the site of the former Greenmere Primary School buildings.
The project also includes the conversion of a number of existing science
rooms to provide general teaching classrooms within the main school
buildings and allow for the eventual removal of temporary classrooms
from the site.
When completed
the new science building will includes:
13 purpose designed laboratories;
preparation rooms;
staff work area;
office accommodation;
storage; and
staff and pupil WC’s.
The building
is designed to be fully accessible to users with special needs and
will include a lift providing access to all floors, disabled WC’s
and specialist height adjustable furniture within the laboratories.
Externally
the project includes landscaping and the reconfiguration of the vehicle
access point to allow for separation of vehicle and pedestrian traffic.
The project has been designed to retain space to the rear of the new
building for future development.
-
JUSTIFICATION AND
ASSESSMENT OF NEED
The site
capacity of St Birinus School is within the DfES area guidelines for
the size of the school. However, the site area calculation includes
off site playing field provision at what is known as the Hagbourne
Triangle. The school site is therefore constrained because it is essentially
working as a split site. Building development can only take place
on the main school site, leading to further constraints and potential
disruption. There is already limited scope on the main school site
for outdoor pupil recreation and hard play areas.
Four of
the existing science labs being replaced are identified in the Education
Asset Management Plan as having the following suitability problems.
Chemistry Laboratory (Room
0036)
Category B suitability
problem (Preferred Teaching Methods are inhibited) – room too small.
Biology Laboratory (Room
0041)
Category
C suitability problem (Management or organisation of the school
affected adversely) – room located on first floor, accessed via
steep/barrow staircase.
Biology Laboratory (Room
0044)
Category
B suitability problem (Preferred Teaching Methods are inhibited)
– room too small and located on first floor, accessed via steep/barrow
staircase.
Biology Laboratory (Room
0045)
Category
B suitability problem (Preferred Teaching Methods are inhibited)
– room too small and located on first floor, accessed via steep/barrow
staircase.
The school
currently has 18 temporary classrooms, three of which provide science
accommodation. The removal of temporary classrooms is an agreed priority
in the Education Asset Management Plan. On completion of the project
it is intended to start a phased removal of temporary buildings. This
will have to be planned in light of developing proposals for major
housing growth within the town and the timing for delivery of additional
educational infrastructure.
-
OTHER OPTIONS
The only
other option is to do nothing. This would still leave the school with
a large number of temporary buildings and the teaching accommodation
spread across several detached buildings. Over time this would incur
increasing repair and maintenance liabilities. As the buildings reach
the end of their life they could be replaced with further temporary
buildings. The relocation of the Greenmere Primary School provides the
starting point for increasing the size of the main school site and addressing
the long-term accommodation needs of the school.
-
FINANCIAL IMPLICATIONS
The project
will be procured through Mansell Construction Ltd as a fully partnered
project. The contractor has been involved in the design process and
has worked with the County Council’s property consultant to identify
efficiencies and reduce risks.
-
Capital
The
scheme is already identified in the Capital Programme and Forward
Plan. The estimated cost of the scheme inclusive of professional
fees is £4,780,204. This cost will be met from supported borrowing
provided as part of the School's Capital Formulaic Allocation.
Any future developer funding secured through section 106 agreement
may be used to offset the expenditure incurred against supported
borrowing.
-
Revenue
Day to day
revenue costs will be met through the schools delegated budget. The
replacement of aging temporary buildings will reduce the ongoing repair
and maintenance and energy costs.
-
ENVIRONMENTAL IMPLICATIONS
The new
building will replace an existing brick and tile single storey structure.
It has been designed to respond to key relationships with the new
single storey primary school and the existing buildings within the
St Birinus School campus. The new building will relate to and complement
the adjacent buildings and express itself as a focal point of the
St Birinus School campus whilst also reflecting the importance of
science as an aspect of the schools specialist technology status.
The County
Council property consultant has been required to utilise whole life
appraisal techniques during the design phase and bring forward recommendations
that take account of energy efficiency, repair and maintenance and
durability.
The design
brief for the project specified that the building should achieve a
BREEAM (Building Research Establishment Environmental Assessment Method)
rating of ‘Very Good’, this reflects the advantages of the proposed
three storey compact construction and the Councils intention to elevate
some project work beyond the ‘good’ level. The brief also includes
a CO2 target as defined within the KPI requirements of 40kg/m2.
The building
work will be carried out in accordance with the planning permission
issued by the County Council. The design, materials and landscaping
will be as specified in the planning permission. The construction
will be in accordance with Oxfordshire County Council requirements.
(Resource Appraisal - download as
.xls file)
(Statement of Decision)
KEITH BARTLEY
Director for Children, Head of Finance & Procurement
SUE SCANE
Young People & Families
NEIL MONAGHAN
Head of Property
Contact: Kevin Griffin, Service Manager, Property & Assets, Strategy
& Performance, Children, Young People & Families Directorate Tel:
(01865) 816457
February 2007
Return to TOP
|