Return to Items for DecisionDelegated Decisions by Cabinet Member for Schools Improvement – 6 May 2008Statement of Decision
Education Project Appraisal, The Marlborough C of E School, Woodstock
Present:
Also in attendance:
Documentation considered:
A copy is attached to the signed copy of this decision.
Summary of representations in person
Councillor Fooks welcomed the incorporation of a fire sprinkler system in the Project Appraisal which was in line with a motion put to Council regarding risk assessment in schools and fire protection. She expressed hope that this was the way of things in the future.
Cabinet Member’s Comments
This Project Appraisal is a very creative proposal. The project not only provides a state of the art science department, providing new laboratories and science area, it removes a HORSA and two temporary buildings, refurbishes 6 fixed science laboratories that can be used for other purposes and provides a much needed central focus for the School.
Further creative work is also necessary, looking at changing facilities in the school to meet growth needs of the school and the Council are currently working with the school on proposals to finance this. Decision
Having regard to the arguments and options set out in the documentation before me, the representations made to me and the further considerations set out above, I confirm my decisions on this matter as follows:
to approve detailed Project Appraisal ED692
Signed ...................................................................... Cabinet Member for Schools Improvement