To seek approval to appoint a contractor under an NEC4 Professional Service Contract (PSC) Option A for planning, detailed design, ECI and target cost setting and an NEC4 Engineering Construction Short Contract (ECSC) for any enabling works, surveys and/or investigation works (if required)
Decision type: Key
Reason Key: - Capital Expenditure >£1m;
Decision status: Recommendations Approved
Notice of proposed decision first published: 02/04/2024
Decision due: 23 May 2024 by Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy
Lead member: Cabinet Member for Infrastructure and Development Strategy
Lead director: Corporate Director Environment & Place
Contact: Dan Hammond, Senior Project Manager Email: dan.hammond@oxfordshire.gov.uk.
Consultees
N/A
Plan Reference: 2024/112
Reason No Public Access: None