A40 HIF2 Dukes Cut Wolvercote Bridge Maintenance Works - Decision to Progress to Construction

Meeting: 16/07/2026 - Delegated Decisions by Cabinet Member for Highway Construction and Repair (Item 10)

10 A40 HIF2 Dukes Cut Wolvercote Bridge Maintenance Works - Decision to Progress to Construction pdf icon PDF 124 KB

Cabinet Member: Highways Construction and Repair 

Forward Plan Ref: 2026/163 

Key Decision 

Contact: Mo Fazlie, Senior Project Manager – A40 Programme (Mo.Fazlie@oxfordshire.gov.uk)

 

Report by Director of Environment and Highways (CMDHCR6). 

 

The Cabinet Member is RECOMMENDED to:

 

a)    Approve the award of contract (NEC4 Engineering and Construction Contract, Pricing Option C with secondary Option X22), to M-Group Highways Limited (reg#13007933) for an estimated total value of £4,855,610 (ex VAT), for the HIF2 – Wolvercote Bridge Strengthening and Maintenance Works Scheme under the Pagabo Civil and Infrastructure Framework (Lot 1).

 

Additional documents:

Minutes:

The Chair introduced the item to the meeting.

 

The Chair noted the Council had been looking at ways to improve the A40 corridor for a long time, through bus lanes and active travel infrastructure. The Chair further noted that this issue was time-sensitive given the bridge strengthening works proposed were on a Network Rail bridge which needed to be handed back to them.

 

The Chair thanked officers and agreed to the recommendations in the report.

 

RESOLVED to:

 

a)    Approve the award of contract (NEC4 Engineering and Construction Contract, Pricing Option C with secondary Option X22), to M-Group Highways Limited (reg#13007933) for an estimated total value of £4,855,610 (ex VAT), for the HIF2 – Wolvercote Bridge Strengthening and Maintenance Works Scheme under the Pagabo Civil and Infrastructure Framework (Lot 1).