Issue - meetings

Captial Programme Approvals - June 2025

Meeting: 17/06/2025 - Cabinet (Item 89)

89 Capital Programme Approvals - June 2025 pdf icon PDF 218 KB

Cabinet Member: Finance, Property and Transformation

Forward Plan Ref: 2025/124

Contact: Natalie Crawford, Capital Programme Manager, natalie.crawford@oxfordshire.gov.uk

 

Report by Executive Director of Resources and Section 151 Officer

 

The Capital Programme was approved by Council in February 2025 and will be updated during the year through the capital programme and monitoring reports.  This report sets out change requests requiring Cabinet approval that will be incorporated into the agreed programme and included in the next update to the Capital Programme in July 2025.

 

The Cabinet is RECOMMENDED to:

 

a)               to approve the inclusion of a programme of work into the capital programme with an indicative budget of £5.906m to be funded from the Traffic Congestion Improvement Fund (TCIF), agreed through Council in February 2024.

b)              to note the proposed schemes to be delivered under the TCIF programme of work.

c)               approve a budget increase of £1.800m for the Access to Witney Scheme from £25.025m to £26.825m to be funded by incorporating £1.800m from the Traffic Congestion Improvement Fund.

d)              approve the inclusion of the Benson Lane Bus Service Improvement Plan (BSIP) into the capital programme, with an indicative budget of £1.232m, to be funded by a combination of developer contributions, Transport Provision funding, BSIP programme funds and the Traffic Congestion Improvement Fund.

 

Decision:

Recommendations approved.

Minutes:

The Capital Programme was approved by Council in February 2025 and will be updated during the year through the capital programme and monitoring reports.  This report sets out change requests requiring Cabinet approval that will be incorporated into the agreed programme and included in the next update to the Capital Programme in July 2025.

 

In the absence of the Cabinet Member for Finance, Property and Transformation, Councillor Liz Leffman, Leader of the Council, presented the report. She referred to the various schemes requiring approval and inclusion in the capital programme.

 

Councillor Leffman moved, and Councillor Roberts seconded the recommendations, and they were approved.

 

RESOLVED to:-

 

a)    approve the inclusion of a programme of work into the capital programme with an indicative budget of £5.906m to be funded from the Traffic Congestion Improvement Fund (TCIF), agreed through Council in February 2024.

b)    note the proposed schemes to be delivered under the TCIF programme of work.

c)    approve a budget increase of £1.800m for the Access to Witney Scheme from £25.025m to £26.825m to be funded by incorporating £1.800m from the Traffic Congestion Improvement Fund.

d)    approve the inclusion of the Benson Lane Bus Service Improvement Plan (BSIP) into the capital programme, with an indicative budget of £1.232m, to be funded by a combination of developer contributions, Transport Provision funding, BSIP programme funds and the Traffic Congestion Improvement Fund.