To seek to award
a contract to deliver remediation works at Oakley Wood closed landfill site.
The delivery of works is in two phases. Phase 1 is for a detailed costed proposal for completion of site works to enact the
preferred option (approx £15k). Phase 2 is for the actual remediation works (in
excess of £1m) subject to the award of capital funding from the Environment
Agency. If grant funding is not secured there will be no commitment by the
Council to deliver the works.
Decision type: Key
Decision status: Withdrawn
Lead member: Cabinet Member for Growth & Infrastructure
Lead director: Deputy Director for Environment & Economy - Growth & Infrastructure
Contact: Mark Watson, Waste Contracts Officer Email: mark.watson@oxfordshire.gov.uk Tel: (01865) 815747.
Consultees
N/A – SODC, EA
involved as land is designated Contaminated Land. OCC planners will also need
to agree the final restoration scheme.
Plan Reference: 2010/173