Amended recommendations approved as follows:-
RESOLVED to:-
a)
approve the implementation of six temporary congestion
charging points in Oxford as described in Annex 1, for a maximum of two years
from the date of implementation
b)
authorise the Director of Environment and
Highways (in consultation with the Cabinet Member for Transport Management) to
make any necessary changes to the scheme to ensure its successful delivery;
provided that these do not substantially alter the scheme’s impact
c)
authorise the Director of Environment and
Highways (in consultation with the Director for Law and Governance and
Monitoring Officer) to make and implement the necessary Charging Order under
the Transport Act 2000
d)
approve the development and implementation of
the necessary infrastructure and supporting systems at an estimated cost of
£190,000
e)
instruct officers to develop and
implement the investment plan outlined in paragraph 96 along with any
additional measures in consultation with the Cabinet Member for Transport
Management
e)
delegate approval for future surplus investment to the Director
for Environment and Highways, in consultation with the Executive
Director of Resources and Section 151 Officer, Cabinet Member for Transport
Management and Cabinet Member for Finance, Property and Transformation.
f)
delegate responsibility for implementation of the scheme to the
Director for Environment and Highways in consultation with Cabinet Member for
Transport Management, with the intent to be operational no later than 10th
November 2025.