Cabinet
Member: Place, Environment and
Climate Action
Forward Plan Ref: 2025/057
Non-key decision
Contact: Caroline Coyne, Project Manager (BPSI Team)
Caroline.coyne@oxfordshire.gov.uk
Report by Director
of Economy and Place (CA11)
Oxfordshire County Council’s current household waste recycling centres management contract is in its final extension period and comes to an end on 30th September 2027. A future model for the service delivery is required to be in place and mobilised prior to the expiry of the existing contract. The paper is to approve the preferred model.
Cabinet is RECOMMENDED to
b)
Authorise
Officers to prepare and commence the procurement of a new 8-year HWRC
management contract to start on 1 October 2027 (following a mobilisation
period) with options to support flexibility in Local Government Reorganisation
(LGR).
c)
Endorse
exploration and feasibility of the capital purchase of HWRC plant and equipment
during the tender bidding, with a view to having an agreed final revenue and
capital cost of the contract at the final tender stage.
d)
Delegate
the decision to award the contract, and any extension to the Director of
Environment and Highways in consultation with the Cabinet Member for Place,
Environment and Climate Action.
Minutes:
RESOLVED: that the public be excluded for the duration of
this item since it is likely that if they were present during that item there
would be disclosure of exempt information as defined in Part I of Schedule 12A
to the Local Government Act 1972 (as amended) and specified below in relation
to those items and since it is considered that, in all the circumstances of the
case, the public interest in maintaining the exemption outweighs the public
interest in disclosing the information
Cabinet had before it a
report This document details a proposal for the procurement of a new management
contract for Household Waste Recycling Centres (HWRCs). The contract was
intended to cover the management of HWRCs across Oxfordshire for an 8-year period
starting 1 October 2027, with flexibility provisions related to Local
Government Reorganisation (LGR). The report includes background information,
options appraisal, financial and legal considerations, and outlines key dates
for the procurement process.
Councillor Judy
Roberts, Cabinet Member for Place, Environment and Climate Action presented the
report.
Councillor Roberts
moved and Councillor Hannaby seconded the recommendations and they were
approved.
RESOLVED to:-
b) Authorise
Officers to prepare and commence the procurement of a new 8-year HWRC
management contract to start on 1 October 2027 (following a mobilisation
period) with options to support flexibility in Local Government Reorganisation
(LGR).
c) Endorse
exploration and feasibility of the capital purchase of HWRC plant and equipment
during the tender bidding, with a view to having an agreed final revenue and
capital cost of the contract at the final tender stage.
d) Delegate
the decision to award the contract, and any extension to that contract to the
Director of Environment and Highways in consultation with the Cabinet Member
for Place, Environment and Climate Action.