Any
county councillor may, by giving notice to the Proper Officer by 9 am two working
days before the meeting, ask a question on any matter in respect of the
Cabinet’s delegated powers.
The
number of questions which may be asked by any councillor at any one meeting is
limited to two (or one question with notice and a supplementary question at the
meeting) and the time for questions will be limited to 30 minutes in total. As
with questions at Council, any questions which remain unanswered at the end of
this item will receive a written response.
Questions submitted prior to the agenda being despatched are shown below and will be the subject of a response from the appropriate Cabinet Member or such other councillor or officer as is determined by the Cabinet Member, and shall not be the subject of further debate at this meeting. Questions received after the despatch of the agenda, but before the deadline, will be shown on the Schedule of Addenda circulated at the meeting, together with any written response which is available at that time.
Minutes:
Councillor Howson had given notice of the
following question to Councillor Tilley:
" What
are the consequences for Oxfordshire of the letter from Lord Nash, the PUS at
the DfE taking away the responsibility of the local
authority to help choose sponsors for new schools from 1st July 2015?"
Councillor Tilley replied:
"Up until now decisions
about sponsors for underperforming schools have, ultimately, been taken by the
Secretary of State acting on the advice of 'brokers' who have worked with Council
officers to identify the most appropriate sponsor to tackle the underlying
issues and to support long term sustained
improvements. Delegating the decision making to the Regional
Schools Commissioner who will, over time, develop an understanding of the
'education landscape' of Oxfordshire, strikes me as much more sensible than a
remote Secretary of State, or PUS, making the decision. Officers will be
meeting with the Regional Schools Commissioner next week and Lord Nash's letter
will be on the agenda. I hope that we can build upon our already positive
working relationship with him and I am confident that he will wish to call upon
officers' local knowledge and expertise in order to make the best possible
decisions about which organisations are best placed to sponsor Oxfordshire
schools in need of support."
Supplementary: Councillor Tilley responding to a further question
from Councillor Howson replied that no, she was unable to give an assurance
that the Regional Schools Commissioner will take decisions based on the
suggestions of council officers.
Councillor Godden had given notice of the
following question to Councillor Carter:
“The message below was
received from Botley School on 1 June. My question is
not What has happened since then, but How did this
happen in the first place, and what measures are we taking
to improve performance and communication?
“The
building work has been delayed unfortunately, as it should have been finished
by now. The initial delay was due to the steel structure (to support the new
reception classroom) being built to incorrect measurements which caused a 12
week delay. There was supposed to be a meeting with Carillion staff to complete
a snagging list on 20th May, but this was cancelled as the build wasn't
sufficiently advanced for that meeting to happen. I have not had a response from Carillion with
an update, since my last meeting with them on 20th April.”
Councillor
Carter replied:
“The last progress meeting with Botley
School was held by the Project Manager on the 18th of June, as part
of regular formal monthly progress meetings, in addition to weekly site
meetings which are held between the construction lead and the School site
representative, during this meeting the practical completion date was
communicated to the school as being the 15th of July, the team also
agreed that a snagging session would be completed on the 25th of
June, with the school invited, with a view to have all outstanding snagging
items cleared by the practical completion date.
The delays during construction have been approximately
6 months, attributable to the following reasons.
-
6-8 weeks for an unidentified Gas Main which required re-routing before
commencement of work. This was not present on any existing service drawings was
not picked up during ground surveys
-
12 week delay due to inaccuracies in the steel frame when delivered, which
required the Frame to be re worked. This was a subcontracted package of works,
the reworking of which did not financially cost Oxfordshire,
however there is recognition of the disruption to the school by being on site
longer than anticipated.
-
There have been another 4 weeks or so of minor delays which have contributed to
this delay.
All of the delays have been communicated with the
school and have been verified by Oxfordshire’s Employers Agent and have been
managed to their conclusion in the context of the contracts that were agreed at
the outset of the project. These delays have materially not affected the cost
of the project to Oxfordshire, however final accounts
are still to be established.
In order to mitigate these types of delay’s in the
future the Properties & Facilities Department and Carillion are currently
redefining the requirements, outputs and processes needed during the design
phase of projects as the length of time it has taken for some jobs to progress
through this process has been longer than originally scheduled and has put
subsequent pressure on the construction periods. In addition to this all School
Projects will be targeted for completion 8 weeks prior to when the Asset is
required for use, which will allow some time for unforeseen events to be
addressed should they occur, prior to their required need.”
Councillor Fooks had given notice of the
following question to Councillor Carter:
"Both the primary schools
in my division of Wolvercote and Summertown have
suffered from delays to building work being carried out at the schools. Will
the Cabinet member tell me how he will ensure that such delays do not happen in
future, as it is immensely disruptive to the education of the children in the
school?"
Councillor Carter replied:
“There has already been a
major overhaul of personnel who are working on the professional services and
construction teams within the Property and Facilities contract, some of the
current issues we face are as a result of work that had been progressed prior
to this overhaul, given that most building projects are several years from
inception to delivery the time lag is a critical
factor that has to be taken into account.
Coupled with the changes to the professional services and construction
teams, the Properties & Facilities Department and Carillion are currently
redefining the requirements, outputs and processes needed during the design
phase of projects as the length of time it has taken for some projects to progress
through this early part of the process has been longer than originally
scheduled and has put subsequent pressure on the construction periods. As part
of the review of our processes all School projects will be targeted for
completion 8 weeks prior to when the Asset is required for use, which will
allow some time for unforeseen events to be addressed should they occur, prior
to their required need. To further improve efficiency, Carillon are
introducing Standardised Design processes and alternative construction routes
(such as Modular Buildings) to reduce overall project durations.
In addition to this the OCC Corporate Landlord Function (Contract
Performance Management) will be ensuring that a robust Project closure process
is in place to capture lessons learned and ensure that these are incorporated
into future projects.
Specifically regarding the project at Wolvercote,
the time taken in design meant that there was little or no time to absorb
delays due to unforeseen events, in this case an ancient well was discovered
during the excavation of the foundations for the new building, upon this
discovery works were halted for Archaeological investigation to take place in
order to establish whether anything of significance was found. As part of
this work a Roman Brooch was found and is
currently with the Archaeological team in OCC.
With regards to Cutteslowe the other school in this area which has had
works completed recently, these were practically completed in time for
September 2014, however the snagging at this site took
an unacceptably long time to complete. The process for this has been
addressed and is now part of pre completion works, prior to handover, there
have also been several other works which have continued into this Academic
year, these were either not in the original scope or were late variations to
the design as a result of the school not being happy with the agreed final
design once it was observed when finished. There have also
been some on-going work with the school to close out issues affecting
previous phases of work from the past.”
Supplementary: Councillor Fooks requested that local members
be kept informed.
Supporting documents: