43 Capital Programme Update and Monitoring Report
PDF 356 KB
Cabinet
Member: Finance, Property and
Transformation
Forward Plan Ref: 2026/028
Key decision
Contact: Natalie Crawford, Capital Programme Manager
Natalie.crawford@oxfordshire.gov.uk
Report by Deputy Chief Executive (Section 151 Officer) (CA15)
Financial Report on capital spending against budget allocations, including any necessary capital programme approvals
Cabinet is RECOMMENDED to:
b. Approve the updated Capital Programme at Annex 2 incorporating the changes set out in this report.
Additions to the Capital Programme
c. Approve the inclusion of Milton Heights Bridge into the capital programme, with a budget of £8.608m, to be funded from a variety of funding sources. (see paragraph 65-66)
Additional documents:
Decision:
Recommendations approved.
Minutes:
Cabinet had before
the fourth capital programme update and monitoring report for 2025/26 which set
out the monitoring position based on activity to the end of January 2026.
The report also updated
the Capital Programme approved by Council in February 2026 taking
into account additional funding, new budget priorities and new
schemes. The updated programme also
incorporated changes agreed through the Capital Programme Approval Reports to
Cabinet during the year as well as new funding.
Councillor Dan Levy, Cabinet Member for Finance, Property and Transformation presented the report. The Milton Heights Bridge had been added to the capital programme, with funding from Section 106 contributions, Council resources, and retained business rates. The bridge would improve walking and cycling connections and was seen as a key piece of infrastructure for the area. The capital programme also included new schools and classroom expansions in response to population growth, with most funding sourced from Section 106 contributions.
Councillor Levy responded to comments made by a speaker concerning delays and cost overruns in major projects by highlighting examples of projects delivered ahead of schedule and emphasised the complexity of funding and delivery.
Councillor Levy moved and Councillor Roberts seconded the recommendations and they were approved.
RESOLVED
to:-
b.
Approve the updated Capital Programme at
Annex 2 incorporating the changes set out in this report.
Additions to the Capital Programme
c.
Approve the inclusion of Milton Heights
Bridge into the capital programme, with a budget of £8.608m, to be funded from
a variety of funding sources. (see
paragraph 65-66)