32 The Cooper School, Bicester
PDF 73 KB
|
Cabinet Member: |
Schools
Improvement |
||
|
Forward Plan Ref: |
2009/238 |
||
|
Contact: |
Kevin Griffin, Service Manager - School
Organisation & Planning Tel: (01865) 816457 Ref: 2009/238 |
||
|
|
|
||
|
Report By: |
Director
for Children, Young People & Families |
||
This Project Approval Report is for the construction of a new Sixth Form Centre at The Cooper School, Bicester. Cabinet approved a statutory proposal to extend the age range of The Cooper School to include a new sixth form at its meeting 26 May 2009. The new sixth form is required to be operational from 1 September 2011.
The addition of a Sixth Form at
The Cooper School is part of a broader 14 - 19 strategy in Bicester. The
The sixth form centre will be housed in a new purpose built building. To ensure that sufficient accommodation is in place to support the change in age range at the school the project also includes an extension to the school’s science faculty to provide 2 additional science laboratories and alterations to the Design & Technology area to create an engineering workshop.
The
Cabinet is RECOMMENDED to approve Project Appraisal ED747
for the provision of new Sixth Form Accommodation at Cooper
School, Bicester.
Additional documents:
Minutes:
Cabinet considered a Project Approval Report for the construction of a
new Sixth Form Centre at The Cooper School, Bicester.
The sixth form centre will be housed in a new purpose built building. To
ensure that sufficient accommodation is in place to support the change in age
range at the school the project also includes an extension to the school’s
science faculty to provide 2 additional science laboratories and alterations to
the Design & Technology area to create an engineering workshop.
The Cabinet Member for Schools Improvement commented that the scheme was
a major capital commitment that would deliver the most significant improvement
in post 16 education in a generation. It would raise the expectation and
aspirations in the area.
Cabinet noted that officers continued to seek funding from the learning
& Skills Council. Councillor Hudspeth welcomed the funding from the
Department for Communities and Local Government and stated that he would work
with Cherwell DC to see if there was any additional funding.
RESOLVED; to approve Project
Appraisal ED747 for the provision of new Sixth Form Accommodation at Cooper School, Bicester.
.