197 Capital Programme Update and Monitoring Report
PDF 359 KB
Forward Plan Ref: 2025/014
Contact: Natalie Crawford, Capital Programme Manager
Natalie.crawford@oxfordshire.gov.uk
Report by Executive
Director of Resources and Section 151 Officer (CA10)
Cabinet is RECOMMENDED to:
b.
Approve the updated Capital Programme at Annex
2 incorporating the changes set out in this report.
Additional documents:
Decision:
Recommendations approved.
Minutes:
Cabinet had before
it the third capital programme update and monitoring report for 2025/26 which
set out the monitoring position based on activity to the end of October 2025.
Councillor Dan
Levy, Cabinet Member for Finance, Property and Transformation, presented the
report.
Councillor
Levy reported that the 10-year capital programme totals £1.43 billion, with
actual expenditure at the end of October just over £103 million and a forecast
of £186 million for the year, noting some slippages due to design and
contractor delays. Highlights included progress on active travel schemes, the
Whitney access scheme, and the reopening of Whitney Library, as well as
significant investment in new school places and SEND provision.
During discussion, Members discussed the various funding sources, including Section 106 and government grants, and noted the impact of central government funding pressures on future service provision.
Councillor Levy moved and Councillor Leffman seconded the recommendations and they were approved.
RESOLVED to:
b.
Approve the updated Capital Programme at
Annex 2 incorporating the changes set out in this report.