73 Capital Programme Approvals - April 2025
PDF 208 KB
Forward Plan Ref: 2025/011
Contact: Natalie Crawford, Capital Programme Manager
Natalie.crawford@oxfordshire.gov.uk
Report by Executive Director of Resources and Section 151 Officer
The Cabinet is
RECOMMENDED to:
a.
approve
the addition of a new phase of energy saving measures into the capital
programme, at a total cost of £10.360m. The two-year programme will run from
2025-2027 and is to be funded by £10.000m from corporate resources, as approved
by Council in February 2025, with the remaining £0.360m to be funded by a
successful bid to Phase 4 of the Public Sector Decarbonisation Scheme
(PSDS4).
b.
approve
the inclusion of phase 2 and 3 of Fire Compartmentation Remedial works into the
capital programme, at a cost of £3.700m.
The programme of work is to be funded from £2.000m corporate resources
agreed by Council in February 2024 and a further £1.700m agreed by Council in
February 2025.
Decision:
Recommendations approved.
Minutes:
Cabinet had before it
which set out change requests requiring Cabinet approval that will be
incorporated into the agreed Capital programme and included in the next update
to programme in June 2025.
Councillor Dan
Levy, Cabinet Member for Finance, presented the report. He referred to the two schemes detailed in
the report relating to energy saving measures funded through corporate
resources and a government decarbonisation scheme and fire safety improvements
in council buildings, ensuring compliance with safety regulations. Both initiatives reflected the council's
commitment to reducing carbon emissions and maintaining safe facilities.
RESOLVED to:
a)
approve the addition of a new phase of
energy saving measures into the capital programme, at a total cost of £10.360m.
The two-year programme will run from 2025-2027 and is to be funded by £10.000m
from corporate resources, as approved by Council in February 2025, with the
remaining £0.360m to be funded by a successful bid to Phase 4 of the Public
Sector Decarbonisation Scheme (PSDS4).
b)
approve the inclusion of phase 2 and 3 of
Fire Compartmentation Remedial works into the capital programme, at a cost of
£3.700m. The programme of work is to be
funded from £2.000m corporate resources agreed by Council in February 2024 and
a further £1.700m agreed by Council in February 2025.