103 Capital Programme Update and Monitoring Report - July 2024
PDF 507 KB
Cabinet Member: Finance
Forward Plan Ref: 2024/205
Contact: Natalie Crawford, Capital Programme Manager,
Natalie.crawford@oxfordshire,gov.uk
Report by Executive Director of Finance and Section 151
Officer (CA11)
The Cabinet is
RECOMMENDED to:
Capital Programme
2.
Approve
the updated Capital Programme at Annex 2 incorporating the changes set out in
this report.
Budget Changes / Budget Release
3.
approve to release £4m of corporate funds
back to the capital programme from the Special Education Needs (SEN) Provision
Programme due to the additional SEN High Needs Grant funding received between
2021/22 and 2024/25 following the announced funding allocations (paragraph 76).
4.
approve
the inclusion of Oxford Community Support Service (CSS) Cowley into the Capital
Programme with an indicative budget of £1.078m to be funded from the Asset
Rationalisation Programme, Property Decarbonisation Programme and Section 106
funding (paragraph 68).
5.
approve
the change of the use of the budget for the purposes of relocating Banbury
Library (paragraph 70).
Additional documents:
Decision:
Recommendations approved.
Minutes:
Cabinet had before it the first quarterly capital programme
update and monitoring report for 2024/25 which set out the monitoring position
based on activity to the end of May 2024. The report also provided an update to the Capital Programme
approved by Council in February 2024, taking into account additional funding
and new schemes.
Councillor Dan Levy, Cabinet Member for Finance, presented
the report and explained the background to the schemes for which approval was
requested.
During discussion members welcomed the proposals in the
report and referred, in particular, to the opening of Shrivenham Primary School
and the relocation of Banbury Library.
RESOLVED to:-
Capital Programme
b) approve
the updated Capital Programme at Annex 2 incorporating the changes set out in
this report.
Budget Changes / Budget Release
c) approve
to release £4m of corporate funds back to the capital programme from the
Special Education Needs (SEN) Provision Programme due to the additional SEN
High Needs Grant funding received between 2021/22 and 2024/25 following the
announced funding allocations (paragraph 76).
d) approve
the inclusion of Oxford Community Support Service (CSS) Cowley into the Capital
Programme with an indicative budget of £1.078m to be funded from the Asset
Rationalisation Programme, Property Decarbonisation Programme and Section 106
funding (paragraph 68).
e) approve
the change of the use of the budget for the purposes of relocating Banbury
Library (paragraph 70).