58 Capital Programme Approvals - April 2024
PDF 211 KB
Cabinet Member: Finance
Forward Plan Ref: 2024/059
Contact: Natalie Crawford, Capital Programme Manager
Natalie.crawford@oxfordshire.gov.uk
Report by Executive
Director of Resources and Section 151 Officer (CA11)
The Cabinet is RECOMMENDED
to:
a.
approve
the inclusion of the £2.384m Active Travel Fund 4 Extension (ATF4e) Grant into
the capital programme to deliver active travel schemes across Oxfordshire.
b.
approve
the inclusion of £1.260m grant funding from the Department for Transport Safer
Roads Funds to carry out a specific package of road safety works.
c.
approve
the drawdown of £2.000m of funds from the Parking Account to reinvest into
three Park and Ride sites requiring maintenance work.
d.
approve the inclusion of Faringdon Community College, a scheme to
replace temporary buildings with permanent accommodation, into the Capital
Programme with an indicative budget of £6.006m to be fully funded from held & secure
s106 contributions.
Decision:
Recommendations approved.
Minutes:
Cabinet had before it a report which set out changes to the Capital Programme requiring Cabinet approval that would be incorporated into the agreed programme and included in the next update to the Capital Programme in June 2024.
The Chair presented the report on behalf of the Cabinet
Member for Finance.
Councillor Andrew Gant, Cabinet Member for Transport
Management and Councillor John Howson, Cabinet Member for Children, Education
and Young People’s Services, explained details of the additional schemes within
their respective portfolios.
Councillor Leffman moved and Councillor Howson seconded the
recommendations, and they were approved.
RESOLVED to:
a) approve the inclusion of the £2.384m Active
Travel Fund 4 Extension (ATF4e) Grant into the capital programme to deliver
active travel schemes across Oxfordshire.
b) approve the inclusion of £1.260m grant
funding from the Department for Transport Safer Roads Funds to carry out a
specific package of road safety works.
c) approve the drawdown of £2.000m of funds
from the Parking Account to reinvest into three Park and Ride sites requiring
maintenance work.
d)
approve
the inclusion of Faringdon Community College, a scheme to replace temporary
buildings with permanent accommodation, into the Capital Programme with an
indicative budget of £6.006m to
be fully funded from held & secure s106 contributions