5. Deddington Depot Salt Barn
PDF 286 KB
Cabinet Member: Finance
Forward Plan Ref: 2024/055
Contact: Liz Clutterbrook, Head of
Major Projects,
liz.clutterbrook@oxfordshire.gov.uk
Report by Executive Director of Resources and Section 151 Officer
The Cabinet Member of Finance is RECOMMENDED to approve:
a)
The
Deddington salt barn, washdown facility and demolition of condemned site cabins
(Phase 1) proceeding into Stage 3 and entering a JCT D&B 2016 contract with
Ryebridge Ltd.
Note: the
above is subject to receiving full planning permission by 5th April
2024, prior to going into contract with Ryebridge Ltd to commence the Phase 1
main construction works.
b)
Progressing
with the tender of the design, planning and installation of new site offices
and then entering a contract as long as the total project cost of Phase 1 and
Phase 2 does not exceed £2.830m.